ID |
Date |
Author |
Location |
Severity |
Subject |
35
|
24 Apr 2019, 10:05 |
Gerd Wellenreuther | General | Information | Minutes of the Technical integration meeting 24.04.19 | SPB/SFX
- SPB/SFX is preparing for the upcoming beamtime.
- CRL motors being tested. --> Still ongoing.
- CSS interlock tests being planned for tomorrow. --> Still ongoing.
- AE needs to know when Loop 9 and 10 are expected to run. SPB to check.
FXE
- AE needs to get information on PLCs loop splitting. FXE to comment.
- Loop 6 is required to drive 2 servo motors. BB will try to bring this into operation this week. NC checked the setup.
SQS
- AE still needs priorities for the next loops. SQS to comment.
SCS
- Discussion with EET ongoing concerning the installation of cables for end stations. Space problem. --> This is a long term issue, to be discussed in the other meetings, ongoing.
- Commissioning of the motion is ongoing. JT is fixing particular motors / issues.
- Further testing is including interlocks, vacuum and chiller.
- Loop 12 is supposed to be up & running by the end of next week
MID
- For Loop 9 CY is preparing a change request. AE involved. --> still pending
- Loop 12 will be operable this week --> an 100V input is needed, but not readily available. To be checked by AE.
- Priorities for next loops needed by AE to plan the work. --> Still required.
HED
- Loop 7 being commissioned --> still being commissioned, encoders are misbehaving / behaving strange.
- Loop9 (Smaract stages) has to be brough up. --> will be done this week
- Next loops are 8 followed by the priority-items from loop 6.
- Loop10 and 11 regarding PPL will be needed in June. HED to confirm. --> Feedback from MN required.
OPT Lasers
- AE support is needed in order to bring the SCS laser up by the end of may. Mail has been sent. NJardon checks. --> Loop extended and running by the end of next week.
XRO
- Motion loop for Hirex 2 has been delayed until June
XPD
- Issue repoeted from CAS: Fast ADC for MCP in SASE3 duplicates data in the 3 % of cases. DAQ is not responsible. Tests have to be made and for that the ADC servers have to undergo to short interruptions. Will be coordinated with XPD. Should not be e problem. CAS to follow the issue up. --> Unclear, CAS not attending.
VAC
DET
AE
ITDM
- New DACHS-area "Balcony rooms" will be setup. Requires local training by ITDM, which is currently being organized.
EET
- Working on MID SDL and SCS day 2 components.
CAS
SRP
- Schedule changes for the Summer shutdown due to modification of the interlock systems. Additional meetings needed. No info is expected before the beginning of May. --> an uncoordinated email was sent around by MDressel (MPS). SRP will take care of clarifying with MPS what has to be done, when, and will communicate this.
TS
AoB
|
46
|
22 May 2019, 09:58 |
Gerd Wellenreuther | General | Information | Minutes of the Technical integration meeting 22.05.19 | FXE
SPB/SFX
- XTD2 attenuator appears to be damaged.
- Beam at lower energies look disturbed, SPB/SFX will contact XRO.
- Digitizers have been requested. HW needs to be installed and set up and the timeline has to be clarified betweek BF and SPB. ==> next week
SQS
- pnCCD: testing the 5 axis of motion. 3 are working, but there are problems, the wiring of the cables is now being checked.
SCS
- Some issues are noticed regarding the triggering of the detector, but BF is on it
MID
- Due to the failed chiller, the user experiment had to be cancelled.
- As a consequence, time is available to commision other hardware. ==> to be clarified with AE which activities can be supported.
- Integration of the LDM: Safety document is needed.
HED
- Loop 6 being commissioned.
- Loop 1 was updated, parameters got lost. :-(
- Detector issues regarding Epix 100: First some HW + assistance from MID was provided to get the detector running. By now, the HED-owned HW for the Epix 10K is being used.
XRO
XPD
VAC
DET
AE
- Loop priorities for HED and MID are needed.
- AE reminds everybody to contact TSchoen if power is required during the middle of June, e.g. in order to keep the vacuum running.
ITDM
EET
CAS
SRP
- A safety walkthrough for SASE2 was done. Several installations are in conflict with the safety regulations regarding e.g. electrical installations. Detailed minutes will be provided. SRP will also involve TS / Süleyman Arslan.
TS
AoB
|
81
|
21 Aug 2019, 11:15 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 21.08.19 | XO
- A review of the procedures in case of power failure is in progress. Thanks to everybody for the efforts during the last days.
FXE
- Remote control of the radiation shutter dows not work. IP of the new computer is needed. Will be solved offline between FXE, CAS and ITDM. ==> Done for FXE. Small issues being fixed for MID.
SPB/SFX
SCS
- Support from EEE is needed to make sure motors needed for the user experiments in 2 weeks are actually working (e.g. Elmo). ==> fine tuning of the support plan will be made between SCS and EEE.
SQS
MID
- DPS turbo pump issue. A software workaround exists. The problem is that the used controller has not been commissioned firmwarewise before. This is not a showstopper and wil be addressed later. ==> The cabling is done differently. EEE is testing the device + firmware. ==> Ongoing
HED
- The smaract stages with the current firmware can be either driven fast or precise. EEE will discuss with the isntruments involved how to modify the stages implementation to be able to have both options available.
Optical lasers
VAC
XRO
- There was an issue with a drift of the HED mirror. As a consequence, VAC and XRO have switched of the mirror cooling. HED and MID should report about the change of the situation. ==> still exchange of information needed. ==> Measurements from MID have been received. HED will do the same. Investigation of the problem will happen next week (shutdown)
XPD
DET
- Calibration database haes been migrated. If problems are experienced please send a ticket to DET.
EEE
- Loop updates in the tunnels and instruments being scheduled together with the involved groups.
CAS
- 2.6.1. being prepared. Deployment plan is still valid.
ITDM
SRP
TS
AoB |
86
|
20 Nov 2019, 10:12 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 20.11.19 | FXE
- Wille was asked by D3 to pull new cables for the Pandora in FXE on 19.11.. This was not known by FXE. Will be discussed with Safety/DNölle.
- Mono was fixed and is now ready for commissioning with beam
SPB/SFX
- uTCA update planned for tomorrow#
- Chris Blöm will leave the company next week. His tasks need to be re assigned.
- Order of loops upgrade will be discussed with M.Stupar as soon as he is back.
- The drag chain will be opened for cables re organization. HV cables will be also replaced by Wille . SPB/SFX will get the new HV cables from Sonay Sayar.
SCS
SQS
MID
- Loop11 (AGIPD) needed. The task was not envisaged in the shutdown task list and is required by the detector group. Will be discussed with MS.
- It has to be checked whether the delivery of the SDL is confirmed and the patch panels infrastructure is ready for cables installation.
HED
Optical lasers
VAC
XRO
XPD
DET
EEE
- Power supplies - firmware update will be performed in the next days. Mail will be sent around.
- Tming system update. No triggers will be available. Will be announced by mail.
- uTCA CPUs migration. The CPUs stored valued will be lost. Karabo devices will need to be re installed. Karabo stored values will not be lost. Will be announced by mail.
Controls
- The overnight and weekend OCD service will stop during the shutdown. OCD only available in the time 6:00 - 18:00
- Karabo 2.7.0 deployment date for the tunnels is the 13.12.- Instruments to follow.
ITDM
SRP
TS
- The power cut works will start at 6:00 in the morning. The electronics should ne put in a safe state the day before.
- TS can provide support for temporary light and powerr during the power cut periods.
AoB |
22
|
20 Mar 2019, 14:07 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 20.03.19 | SPB/SFX
- CRL implementation in the hutch will happen in April. AE and EET involved. ==> ZA needs the documentation of the CRL. The point is SRP to be able to evaluate the focusing properties to give beam permission after installation. TH will ask directly PVagovic. Still pending since PV is not here.==> Still pending.
- AGIPD motion. Prelminary tests are being performed to be ready for the final tests in the march shutdown. ==> Some issues with cabling of limit switches were found. SPB will fix it today/tomorrow.
FXE
SQS
SCS
- When operating the machine in the train pattern (not 10 Hz) mode and pulse on demand mode the data from the XGMs in XTD10 and SCS is not recorded. ==> That's still the case and it is caused by a Doocs update not agreed with CAS. ==> Ongoing
- The dangling cable of the sliding door has to be fixed. This is supposed to be done by ARathjen during the March shutdown.
- A Change in the storage of raw data of the XGM is required. SCS is discussing with XPD (Theo). Later ITDM and CAS will be also involved.
MID
- Issue with the remote control of the ion pumps.MID OPT now ok. MID exp being implemented (waiting for some HW + Support from CY). Basically understood. Will be implemented in agreement with the instrument (requires access + fixed cables)==> Loop update slot to be agreed with the instrument.
- Smaract stages do not work propery and reliably. High priority. Has to be clarified with AE since it is not clear whether this is the same issue that SCS had and for whoch they developed a workaround. ==> no updates.
HED
- Cables and loops for HED instrumentation. LW is monitoring closely the installation of cables to give the go ahead to AE for the starting of tyhe loops. Loop 5 is still the priority. High priority cables for Loops 5, 7,8 should be all installed by the end of this week.
- Vacuul logic has to be implemented int he opt hutch. AE ready. Can be done tomorrow (KS, NJ)
OPT Lasers
- Modules for the time stamp have to be installed by AE. How long does it take? Will be discussed offiline with PG. ==> Installation dates: SASE1 in summer shutdown, SASE3 being worked out, SASE2 will follow. Workaround with time stamp is being investigated. ==> PLCs have to be updated. HW ready.
XRO
XPD
- Hirex 2 will be shipped from Cologne tomorrow and will be brought into the VAC lab. Crates ready, cables ready. AE can support local tests outside the shutdown week.==> Hirex will be installed in the shutdown and probably a couple of testt will need support from AE. These can be scheduled for the 01/02.04. Vac loop is affected.
VAC
DET
- LPD charge injection data seem ok.
- MID gpu calibration foreseen for today
AE
- Data Correlation issue test between MCP detector and XGM - PG: Workplan has been made. Additional tests needed and have to be planned with beam. ==> Beamtime will be requested by JG. ==> No updates
ITDM
EET
CAS
- HED kick off meeting for preparation for users has to happen. ==> Will take place next week.
SRP
oB |
10
|
20 Feb 2019, 11:16 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 20.02.19 | SPB/SFX
- CSS component commissioning. Concept and implementation being finalized.==> Final tests have to be performed at SPB, if OK, the CR will be finalized.
- Loop 14 (Jungfrau) commissionig has started. 3 modules are being controlled. The movable stage should have been shipped from japan today. Then will be mounted and controlled via PLC.
- CRL implementation in the hutch will happen in April. AE and EET involved. ==> ZA needs the documentation of the CRL. before April. MS will ask the responsbile person in SPB.
FXE
SQS
- exhaust line for explosive gases has not been tested so far and no information is available to SQS. Urgent. SRP should comment.==> MMeyer is following up the issue. - NO update.
SCS
MID
- Issue with the remote control of the ion pumps. It is not possible to switch on and off the pumps remotely due to the fact that a wrong terminal was used . It seems this was also the same issue in SASE1 and 3. AE and EET are on it to fix it and update the doucumentation. ==> AE needs to perform a test at MID before deploying the solution. Since there are other priorities now the test has not happened yet. ==> Test has been shifted to HED.
- An automatic chain of communicaton is needed (TS?) to notify relevant peopole when the power is down. ==> UBr will follow up the automatic notification setup.
- Loop update caused some issues with the motor directions.
- Components in the tunnel hava to be included in the DAQ during the internal commisisoning time. Name of the relevan tunnel components should be comminicated to the CAS contact person.
HED
- Si bounce monochromators - Chiller leaks. Will be repaired in the next shutdown.
- hirex mono water connections will be reworked in March.
OPT Lasers
- SASE1 PP laser available
- SASE2 and 3 in progress.
- Modules for the time stamp have to be installed by AE. How long does it take? Will be discussed offiline with PG.
XRO
- In SASE3 additional safety shutters issue: Hardware will be ready by middle of Feb. On the 24 and 25. the installation and the modification of the EPS loop should take place if D3, SRP agree on the change request proposed by HS and MD. ==> Still no official decision from D3 and SRP. AE would like to get as many info as possible in advance to start preparing the loop update. According to MDommach NJardon is supposed to be already in the loop. ==> Concept in written has not yet been communicated to SRP and AE. ZA will talk to HS.
XPD
VAC
DET
AE
ITDM
EET
CAS
- Hotfix is being tested and probably relesed tomorrow. It is not mandatory. Minor improvements only.
SRP
- FXE beam permission issue form last week: Due to the fact that the CRL can focus the beam on the beamstop and the operation betweek 7 and 14 keV was required, a proper analisys of the radiation safety had to be carried out. Between 7 and 9 keV the air is absorbing mostly of the light and there are no concerns. For energies above 7 keV the transmission increases. In order to allow operation the following requirements were set: 4W max power. B4C in front of the beamstop (efficiency grows with energy in this range)
- The self rescue training is supposed to become part of the access requirement in the DACHS system for the tunnel. This caused a lot of concerns during the meeting (visitors? Access to components only in the very firrt part of the tunnel ). PSPO will discuss with SRP .
AoB
|
56
|
19 Jun 2019, 10:55 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 19.06.19 | FXE
SPB/SFX
- No major issues
- Starting from the end of this week to the beginning of next week the hutch will not be accessible because of works on the AGIPD.
SCS
SQS
MID
- Integration of the LDM: Risk assessment has been finalized and uploaded in the IPW system. Next steps: SRP will review it and forward it to A.Madsen for the signature. PGessler is in the loop. JHallmann will call for a meeting with all the parties involved (e.g. EEE) in the implementation once the risk assessment has been signed by AM.
HED
- Due to missing endswitches / interlock conditions, some YAG-screens have been burnt. HED would like to try to get this fixed in the tunnels and the hutches still in this shutdown by installing endswitches etc., to be negotiated with EEE ==> Software limit switches can be implemented already next week if the definitions are delivered to EEE by the end of this week. ==> definitions still missing.
- Loop 11 being set up by EEE
Optical lasers
- SASE1 timing system will be updated today.
VAC
- Requested to see the first pump + valve of SPB/SFX ==> definitions still needed by EEE
XRO
- Installation of the cooling system for the M1 mirror in SASE2 has been completed.
- SASE1 XTD2 M1 being addressed now.
XPD
DET
EEE
- The timing uTCA will be switched off on the 24.06 between 9 am and 5 pm. No train ID and timing wil be available.
CAS
- Release cycle for the next Karabo version in progress.
ITDM
- New version of the Jddd should be used. Details will be forwarded to the readiness mailing list as soon as available.
SRP
- From SBP/SFX: Currently, it is not clear what to do if one of the Pandoras goes off. This apparently happened @ FXE on the night from Sat.-Sunday, and it took 12 hours to fix it. Update from SRP: Occasionally Pandoras trigger radiation alarms. It is not clear why. One possibility is that this is caused by electronic noise. Discussions with D3 are ongoing. Right now an expert is needed to reboot the system since it is not a simple off/on procedure, but data has to be analysed. There is a a document in preparation by SRP/D3 that will allow more people to be able to perform this procedure, but it is not ready yet. A side note is that there is no OCD agreement in place for these experts and the reboot is done on the best effort level. ==> Z.Ansari will be also able soon to reboot the system. No additioanl news.
- Test panel to test the different alarms will be mounted in the hall soon.
- After the safety walk in SPB/SFX some issues have been found (e.g. concerning the Biolab, Rackroom) and forwarded to A. Mancuso. SRP and AMancuso will follow the issues up.
- Racks in HED outside the rackroom. They are too high and the top cannot be reached. SRP/JE/SRP will follow the issue up.
TS
AoB |
68
|
17 Jul 2019, 10:05 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 17.07.19 | XO
FXE
SPB/SFX
- 2 screens require the intervention of EEE today. Being agreed offline.
SCS
SQS
​​MID
- XRO will agree with MID which functionalities of the attenuators in XTD1 have to be tested. 'to do list' will be issued. XRO will put the results in the operation logbook. If XRO will not make it to test everything, MID will be informed and will help. ==> Ongoing
- M2 bender: motor issue. HSinn is following it up.
- By the end of the week MID should send the requirements for the vacuum interlock to EEE. ==> tests are ongoing. AS will organize a meeting with CAS, VAC and EEE to define a test procedure to be followed by the instruments when testing the vacuum interlocks.
HED
- Lase is fully integrated in Karabo now.
- Yesterday the loop 6 was updated. There were issue with pumps switching off and causing overhead for HED. PG will investigate why this happened...
Optical lasers
- SA1 PP laser: the damage is worst than expected. More info to come.
​VAC
XRO
- M1 in SASE2 and 1 will be commissioned this week end. New positions will be found and written diwn in the logbook. Difference of some mm with respect to the old positions is expected.
XPD
DET
​EEE
CAS
- Karabo 2.5.1. hotfix is being prepared (Fixing 2 bugs in the framework and several GUI issues).
- Tomorrow at 14:00 there will be a test of the pulse on demand feature (conditional triggers) in FXE. (AS/BF)
​ITDM
​SRP
TS
AoB
- People are reminded to send XO/PM the shutdown activities by the 2.08.
|
34
|
17 Apr 2019, 11:34 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 17.04.19 | SPB/SFX
- CRL motors being tested. Today BB (AE) will check the status.
- CSS interlock tests being planned for tomorrow.
- Jungfrau motors - SS (EET) fixed some cable issues. Now ok.
- Julabo chiller: loop 5 has been updated (interlocks definition, setpoints...) AE+DET working on it.
- AE needs to know when Loop 9 is expected to run. SPB to check.
FXE
- AE needs to get information on PLCs loop splitting. FXE to comment.
SQS
- Loop 9 will be updated.
- AE helping for commissioning
- AE needs priorities for the next loops. SQS to comment.
SCS
- DSSC installation progressing. Loop 5 motion loops should run
- In general loops have been updated. Loop 13 (part of it) being commissioned. AE needs to know then the entire loop commissionig will start.
- Discussion with EET ongoing concerning the installation of cables for end stations. Space problem.
- Loop 4. BKF536 and 531 being modified. Clarification with AE/EET needed.
MID
- Epix voltage interlocks definition and implementation. AE (MS) and CAS (CY) working on it.
- For Loop 9 CY is preparing a change request. AE involved.
- Loop 12 will be operable this week
- Priorities for next loops needed by AE to plan the work.
HED
- Mono in XTD6 has been fixed.
- Jungfrau and epix commissioned
- Loop 7 being commissioned
- Loops 1, 2 , 5, 7 could be done
- Loop9 (Smaract stages) has to be brough up.
- Loop10 and 11 will be needed in June. HED to confirm.
OPT Lasers
- SA2 PPL work ongoing this and next week. ready by next week.
- AE support is needed in order to bring the SCS laser up by the end of may. Mail has been sent. NJardon checks.
XRO
XPD
- Loop updates procedure being finalized by AE. NK asked for MOV2 loop update during next week. AE will try to follow this up.
- Issue repoeted from CAS: Fast ADC for MCP in SASE3 duplicates data in the 3 % of cases. DAQ is not responsible. Tests have to be made and for that the ADC servers have to undergo to short interruptions. Will be coordinated with XPD. Should not be e problem. CAS to follow the issue up.
VAC
DET
AE
ITDM
EET
CAS
- 5Hz test follow up is being done by CAS. Especially optimization concerning train id and time stamp with DESY with the goal to make the switch between the different operation mode easier. A meeting will be planned.
- 2,4,1. hotfix (Fast data pipeline) is being prepared
SRP
- Oil cans in and outside SPB rackroom should be removed. A proper cabinet has been requested to TS but it is not yet ready since exhaust lines are needed.
- Patch cables in the racks should be limited to the very necessary amount since there the material storage is not allowed . TS can help finding space for this material in the hall..
- Schedule changes for the Summer shutdown due to modification of the interlock systems. Additional meetings needed. No info is expected before the beginning of May.
TS
- Support for chillers. Contact people by TS are T. Bartsch and P. Schmidt. They can support concerning issues and problems with chillers for the day to day operation. LKersting supports that. For bigger project, a specific request should be made to LK.
AoB |
43
|
15 May 2019, 12:53 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 15.05.19 | SPB/SFX
- Nano KB mirrors and CSS controls are OK
- Digitizers have been requested. HW needs to be installed and set up and the timeline has to be clarified betweek BF and SPB. Not possible to have them running on short notice.
-
Comment from AS: Trigger Test with pulse on demand to test the conditional trigger (5Hz like operation) is done, but failed to deliver a real conditional trigger. The Karabo device is adapted to switch between the present mode and conditional trigger from Karabo (although some issue were identified). The X2Timer configuration still need adjustment, BF is on it.
FXE
- Re shuffling of PLC CPUs drawers will occur during the next winter shutdown.
SQS
- MPODS power supplies are behaving strangely. CY will have a look.
- pnCCD: Commissioning should start today. Maxi cage for interlocks will be installed today by SQS.
SCS
MID
- Axes for users operation being commissed
- Communication between VAC and AE concerning the electronics for the cryo coolers - heaters has to be improved since AE was not involved during the last ZZ intervention on monday. MD will discuss later today with NJ.
HED
- Loop 6 can be operated in its completeness by middle of next week.
- Laser beam has to be deivered to SCS in 2 weeks. Fw has to be uploaded in the PLCs. HW is ready, commissioning has to start.
- There is the request to make the timing signal independent between the SASEs. Will be discussed offline with AE. It should be possible in the winter shutdown. ==> BF is talking to the involved people.
XRO
XPD
VAC
DET
- Karabo 2.4.1. improves the pipieline stability. The deployment is strongly suggested to MID and SPB. ==> Pipeline for SPB has been deployed. Minor issues being addressed. MID has to folllow.
AE
ITDM
EET
- Schedule for the Loop 10 and 11 of HED cables installation is confirmed. IN KW25 would be possible to bring the loop up.
CAS
SRP
TS
AoB |
79
|
14 Aug 2019, 10:01 |
Gerd Wellenreuther | General | Information | Minutes of the Technical integration meeting 14.08.2019 | XO
- On Monday at around 12:20 there was a power glitch at least in Hamburg, affecting the machine.
- In this cause, the startup was delayed due to a missing signal from the Vacuum EPS-MPS-interface. The signal had to be manually enabled again.
- Tuning is estimated to take until 14:00 today.
- In the wake of such events a lot of communication about the machine status is happening. In the future, XO will ensure the readiness mailing list will be updated, too. In this respect, P. Gessler suggested to rethink / rename the multitude of mailing lists inherited from the construction phase.
FXE
- There are concerns about the replacement of the simple motor with the MC2 library, in particular about whether all functionalities will still be available (e.g. step-up/down). According to EEE this should be okay. CAS has already release the new library for testing.
SPB/SFX
- Hexapods are being integrated. ==> This was rescheduled due to the issues with hexapods at HED and MID. Currently, there is no dire need to integrate the SPB/SFX hexapod, it can be run from TwinCAT.
SCS
- There is an issue with the main sample stage. SCS and SEC are working on it, will continue with commissioning the instrument.
SQS
- Loop 14 will be updated today.
MID
- DPS turbo pump issue. A software workaround exists. The problem is that the used controller has not been commissioned firmwarewise before. This is not a showstopper and wil be addressed later. ==> The cabling is done differently. EEE is testing the device + firmware.
HED
- Loop 13 has been commissioned.
Optical lasers
VAC
XRO
- There was an issue with a drift of the HED mirror. As a consequence, VAC and XRO have switched of the mirror cooling. HED and MID should report about the change of the situation.
XPD
- During an intervention in XTD1 the LED for the Self-Seeding setup was replaced.
DET
EEE
CAS
- 2.6.0. being prepared. ==> Sneak peak was deployed in SPB/SFX. Actual deployment datas can be found in the Shutdown planing, will be discussed in the chapters and with the SASE responsibles.
ITDM
SRP
- The primary door of the HED experiment is currently not guarded with a magnet against incidential opening of the door leading to a trip of the machine. KWitt has to redo some cabling, until then, users can set the laser interlock, which will engage the magnet.
TS
- Controller for the hexapod is currently in the MID control room. UBrueggmann should check the installation.
AoB
- Please check the shutdown planning
- No dispatch meeting on Friday.
|
19
|
13 Mar 2019, 11:11 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 13.03.19 | SPB/SFX
- CRL implementation in the hutch will happen in April. AE and EET involved. ==> ZA needs the documentation of the CRL. The point is SRP to be able to evaluate the focusing properties to give beam permission after installation. TH will ask directly PVagovic. Still pending since PV is not here.
- AGIPD motion. Prelminary tests are being performed to be ready for the final tests in the march shutdown. Still planned.
FXE
SQS
SCS
- When operating the machine in the train pattern (not 10 Hz) mode and pulse on demand mode the data from the XGMs in XTD10 and SCS is not recorded. ==> That's still the case and it is caused by a Doocs update not agreed with CAS.
MID
- Issue with the remote control of the ion pumps.MID OPT now ok. MID exp being implemented (waiting for some HW + Support from CY). Basically understood. Will be implemented in agreement with the instrument (requires access + fixed cables)
- Smaract stages do not work propery and reliably. High priority. Has to be clarified with AE since it is not clear whether this is the same issue that SCS had and for whoch they developed a workaround.
HED
- Cables for the experiment hutch are being installed but some quality issues occured. Last pallets of cables have been sent back for proper confectioning. It is possible that there will be some delays. KA will discuss with LW how to prioritize cables to eventually minimize the impact on the commissioning. ==> Quality issues are being addressed. The company increased the manpower for cable confectioning and installation. KS prepared a list of priorities. AE informs that they will be probably able only to provide fw for loops 5 and 7 by the end of March (collision with many shutdown activities). PG will send details to KA. This will eventually require a decision concerning priorities. Ongoing. ==> There will be a dedicated meeting after this one to discuss the details, coordinate the process (Cables/fw export/ Loops start).
- CRL2 in XTD6 - issue with motors losing steps. Will be fixed in the March shutdown. ==> L. Batchelor
- DAQ is ready. Data sources list has been sent to CAS. Will be also sent to ITDM for implementation.==> Status not clear
- For the fixing of the mono's Picomotor, XTD6 will be opened tomorrow and on friday during the day. On the evenings the tunnel will be searched and closed again to allow beam in MID.
OPT Lasers
- Modules for the time stamp have to be installed by AE. How long does it take? Will be discussed offiline with PG. ==> Installation dates: SASE1 in summer shutdown, SASE3 being worked out, SASE2 will follow. Workaround with time stamp is being investigated.
XRO
XPD
- Hirex 2 will be shipped from Cologne tomorrow and will be brought into the VAC lab. Cretes ready, cables ready. AE can support local tests outside the shutdown week.
VAC
- Charge injection test (LPD, FXE) have been perfomed successfully.
DET
AE
- Data Correlation issue test between MCP detector and XGM - PG: Workplan has been made. Additional tests needed and have to be planned with beam. ==> Beamtime will be requested by JG.
- Hirex and DSSC integration and commissioning will most probably not be supported in the shutdown week. AE will try to support them outside that period.
ITDM
EET
CAS
- Who is responsible for the bunch pattern recording for the different instruments? CAS will clarify with ITDM and AE. ==> Ongoing.
- Karabo 2.4.0 test ongoing
- 2.3.7. Hotfix available today (pipieline in middle layer devices has been optimized). To be decided by the instr. whether to install it or not. Recommended.
- HED kick off meeting for preparation for users has to happen.
- XGMs: DOOCS was updated without agreement with CAS and this lead to problems with the controls. In this condition CAS can give only limited support , because they do not know excactly what was deployed and whoch tests were done. In general, this goes against the good practice rule of not updating stuff during the beamtime.
SRP
- The self rescue training is supposed to become part of the access requirement in the DACHS system for the tunnel. This caused a lot of concerns during the meeting (visitors? Access to components only in the very firrt part of the tunnel ). PSPO will discuss with SRP .==> SRP is trying to find a way to minimize the impact of this training on the XFEL employees. Discussion with DESY needed. ==> The implementation date is the 01.05. The legal requirements are quite strict. SRP is trying to find a solution with DESY (proper training every 3 yrs + yearly updates? to be seen). Advice from SRP is to get the training. SScherz can support booking the trainings.
- HED Radiation interlock issues: no agreement yet to get beam permission. Another meeting is planned for tomorrow (SRP chairs).==> Solved
- EUPs: Procedures for the electrical safety trainings and appointments are being clarified (UB, TH, WUS) ==> 2 training per week (in german) are planned for KW 13,14,15. SRP and TS will approach the GLeaders to decide who has to take the trainig first in the different groups. PGessler and SHauff point out that it is not clear whether the policy is olready in place or not. THaas mentioned that we are still in the transition phase and a presentation was given in thre STGL meeting and it was responsibility of the GLs to inform the group members. TH will send AV the material that will be circulated to the readiness mailing list and in this elog ElectricalSafety.pdf.
- SArslan has been appointed Safety responsible for the Exp. Hall. Access for XFEL employees will be granted by him from now on and not anymore by AViolante and GWellenreuther
AoB |
Attachment 1: ElectricalSafety.pdf
|
|
7
|
13 Feb 2019, 10:59 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 13.02.19 | SPB/SFX
- CSS component commissioning. RBean is discussing with AE. Concept and implementation being finalized.
- Loop 14 (Jungfrau) is needed for next week to start the commissioning. IT Cables have been accepted after new measurements. Loop can be switched on.
- Issue about parallel operation of the 3 Jungfrau modules. Being addressed (DET)
- CRL implementation in the hutch will happen in April. AE and EET involved. Safety concept for the handling of Berlillium lenses has been finalized.
FXE
- FXE is working with the SPB spare beam stop (new concept). XRO is in parallel preparing another beamstop for FXE to comply with the new safety standards. SPB needs to get the beamstop back in April.
SQS
- The chain digitizers-triggers-software is being commissioned to allow online analysis. AE, CAS required and involved.==> Specific issues being addressed.
- exhaust line for explosive gases has not been tested so far and no information is available to SQS. Urgent. SRP should comment.==> MMeyer is following up the issue. - NO update.
SCS
- PLCs have been all installed. Firmware deployment has to be pushed. AE is on it.==> Ongoing and high priority.
- Commissioning (Smaract/microscope chamber) ongoing.
- Detector group is working on the fastCCD. Cooling rod has been installed. Cooling is stable. According to DET should be OK.
- Pulses for SASE3 has been delayed, but it will be no issue for the FastCCD.
MID
- Issue with the remote control of the ion pumps. It is not possible to switch on and off the pumps remotely due to the fact that a wrong terminal was used . It seems this was also the same issue in SASE1 and 3. AE and EET are on it to fix it and update the doucumentation. ==> AE needs to perform a test at MID before deploying the solution. Since there are other priorities now the test has not happened yet.
- An automatic chain of communicaton is needed (TS?) to notify relevant peopole when the power is down. ==> UBr will follow up the automatic notification setup.
- Issue with the silicon oil leaks. Even though the system was testes with LN2 up to 5 bar. For now it is not a showstopper but it needs to be addressed.
HED
- Si bounce monochromators - Chiller leaks. Will be repaired in the next shutdown.
- hirex mono water connections will be reworked in March.
- Leak in the cooling unit of the racks in A.27 was repaired on site. (TS+External company)
OPT Lasers
XRO
- In SASE3 additional safety shutters issue: Hardware will be ready by middle of Feb. On the 24 and 25. the installation and the modification of the EPS loop should take place if D3, SRP agree on the change request proposed by HS and MD. ==> Still no official decision from D3 and SRP. AE would like to get as many info as possible in advance to start preparing the loop update. According to MDommach NJardon is supposed to be already in the loop.
- M2 in SASE3 is commissioned and being fine tuned by the instruments.
- There was a DAQ issue concerning the reading of imagers. Should be solved accordina to ITDM, has to be checked and confirmed by XRO.
- CAS is fixing some issue on the middle layer for the slit gap controls.
XPD
VAC
DET
- Jungrfau control issues being addressed
- SPB requires the new trigger solution to be implemented for AGIPD. This is urgent and should be done before the next run. SHauf has to check in the DET group whether this can be pushed also wil Jola coming back only next week.
AE
- DESY reboot of the timing system: small issue with SPB and XRD. Solved.
ITDM
- Storage and logbooks are planned to be divided per week (different buckets for different weeks). It has to be discussed whether it makes sense to try to mergen some of them (e.g. instrument commisioning?). Has to be discussed with the instruments.
EET
CAS
AoB
|
53
|
12 Jun 2019, 12:40 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 12.06.19 | FXE
SPB/SFX
SCS
SQS
MID
- Integration of the LDM: Safety document is needed. ==> This is needed ASAP!!! ==> J. Hallmann is now back and he is in contact with SRP ti finalize the documentation. The statement from MID is that until the documents are finalized no automatic movement of the detector is foreseen.
​HED
- Due to missing endswitches / interlock conditions, some YAG-screens have been burnt. HED would like to try to get this fixed in the tunnels and the hutches still in this shutdown by installing endswitches etc., to be negotiated with EEE ==> Software limit switches can be implemented already next week if the definitions are delivered to EEE by the end of this week.
Optical lasers
​VAC
- Requested to see the first pump + valve of SPB/SFX ==> definitions still needed by EEE
XRO
XPD
DET
EEE
- Improvement of the communication concering loop updates with the XRO has to be achieved. Mails have been sent by PGessler to the STGL and by NJardon to the relevant people. Loops updates already planned for next week in SASE2. Coordination with the involved people ongoing.
CAS
ITDM
SRP
- From SBP/SFX: Currently, it is not clear what to do if one of the Pandoras goes off. This apparently happened @ FXE on the night from Sat.-Sunday, and it took 12 hours to fix it. Update from SRP: Occasionally Pandoras trigger radiation alarms. It is not clear why. One possibility is that this is caused by electronic noise. Discussions with D3 are ongoing. Right now an expert is needed to reboot the system since it is not a simple off/on procedure, but data has to be analysed. There is a a document in preparation by SRP/D3 that will allow more people to be able to perform this procedure, but it is not ready yet. A side note is that there is no OCD agreement in place for these experts and the reboot is done on the best effort level.
TS
​AoB |
66
|
10 Jul 2019, 16:16 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 10.07.19 | XO
- In SASE3 the apertures of the GATT have to be realigned. The upstream apertures have been alreadz realigned. The downstream ones will be probablz realigned tomorrow. If not succesfull some restrictions of the operation have to be evaluated. ==> Done.
- Turnstile issue: 2 days ago the hall was not accessible for some hours because of non functioning turnstiles. The problem was a change in the desy firewall configuration that lead to the transponders system not working.
FXE
- Loops update has to be coordinated between EEE and FXE. No feedback received from EEE. AG will remind TKorsh. Still pending.
SPB/SFX
- No major issues
- BB is coordinating the loops update with SPB/SFX
SCS
- No Major issues
- Loop1 has been updated
SQS
- Aerosol will be commissioned next week. EEE waiting for the precise dates.==> Still waiting.
MID
- XRO will agree with MID which functionalities of the attenuators in XTD1 have to be tested. 'to do list' will be issued. XRO will put the results in the operation logbook. If XRO will not make it to test everything, MID will be informed and will help.
- XTD 6 will be closed tomorrow after lunch. CY points out that there is a list of issues to be fixed in XTD6 (e.g. motors not working) and many people in CAS are ill, hence, not available, NJ checks with MS and CY sends the list to EEE.
- By the end of the week MID should send the requirements for the vacuum interlock to EEE.
HED
- The monochromator can be cooled down now. The vacuul is still not optimal but the device is operable,.
- Today loop 3 will be updated.
Optical lasers
VAC
XRO
- M1 in SASE2 and 1 will be commissioned this week end. New positions will be found and written diwn in the logbook. Difference of some mm with respect to the old positions is expected.
XPD
DET
- Tests with Karabo 2.5.0 OK.
EEE
- Electrical safety regulation. From the beginning of July the new electrical safety regulation is supposed to be in place. According to this regulation the work at the back of the racks in the XHEXP1 and in the entire racks in the tunnels can only be done by certified EFK (Elektrofachkraefte) or by EUPs with an additional training. The additional training can only be provided after summer. The nomination of XFEL EFKs is suffering a delay due to the fact that is not clear who should nominate them (TS, UBR, HR?). PG reported the problem and also the fact that no official statements were made in the past concerning the topic. THaas is trying to clarify the status, and come up with a statement and proposal in the Operations meeting. ==> there was no meeting on Friday. Still pending. ==> implementation of the electrical safety regulation has been postponed to the end of the year (mail from SRP).
CAS
- Deployment of Karabo 2.5.0 has been completed
ITDM
SRP
TS
AoB
|
31
|
10 Apr 2019, 10:54 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 10.04.19 | SPB/SFX
- CRL implementation in the hutch. Tests can start today.
- CSS Test have been started. One elmo devide has to be implemented today. Interlocks have to be tested (later).
- AGIPD motion. Middle layer final tests will be done during next reconfiguration od the detector.
- Julabo chiller: loop 5 has been updated (interlocks definition, setpoints...) AE+DET working on it. seems ok.
FXE
SQS
- Loop 8 and 11 up and running.
SCS
- Loop 4 being updated. Loop 5 (DSSC related) will be updated this and next week.
- Loop 13 running with 1 crate. Part of cables will be delivered by EETf this week.
MID
- Smaract stages do not work propery and reliably. High priority. Has to be clarified with AE since it is not clear whether this is the same issue that SCS had and for whoch they developed a workaround. ==> BB will contact the Smaract company to address the issue.
- Epix power issue has been fixed. The problem was a parameter not properly set in the power supply. No interlocks are being used. MID is aware of that.
- Loop 9, 4 and 12 will be updated with interlocks next week.
- Exapod control vs data policy issue (also affecting HED and SPB, as well as other components). The exapod control implementation via Beckhoff requires time and is planned for the end of April. For the time being SPB and MID control the exapods via software. This make somewhat difficult to store all the data in the correct way and is not fullfilling the data policy. PSPO will report the issue to TT. At this stage a reshuffling of priorities to speed up the HW implementation seems not to help, since it is anyway planned for end of April.
- Loop 12 ready next week.
HED
- Loop 5 being commissioned. Should be completed by today. Loop 7 cables are been reorganized and the commissioning will strat tomorrow. Planned to be completed by the end of the week. Lilla cables between patch panels and components will be asked and discussed with AE.
OPT Lasers
- SA2 PPL work ongoing. ready by next week.
XRO
- Commissioning of M1 in SASE3 took place. An intervention concerning a limit switch has to be done (not critical)
XPD
- Hirex 2 - Commissioning ongoing. Some imporvements, especially concerning DAQ is needed and will be discussed by AK with ITDM.
VAC
- SASE2 beam permission button is hidden in the vacuum expert panel. It is not the case for SASE1 and 3... To be clarified with VAC, XRO and CAS.
DET
AE
- 5Hz operation (HW trigger dependent on the bunch pattern) mode pre tests OK. New tests planned for tomorrow (SPB and SCS). MCP and hirex will also be included in the test with low priority.
ITDM
EET
CAS
SRP
- A power supply was switched off by AE and found on again the next day despite a sign put on the device. This should not happen. SRP advices, in similar cases, also to add a contact of the person who switched off the device for safety reasons.
- XS5000 controller in SCS issue. SRP clarifies that everybody must act in case of clear danger (e.g. preventig the access to a particular area). In this case, it was OK that UB and TS prevented the access to the SCS laser hutch to other people before the controller was put in a safe state. Having said that, the responsibility lies with the scientific group operating the device.
TS
AoB |
40
|
08 May 2019, 10:10 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 08.05.19 | SPB/SFX
- IRDa commissioning ongoing.
- CSS. Limit switches re cabling is ongoing. For the next run the old configuration will still be used. RB and MS will meet to make sure the system can be safely (from the component point of view) operated. ==> Solved.
- Comment from AS: Trigger test with pulse on demand was not succesfull due to missing karabo devices and issues with configuration. For the final fix 10 minutes of beamtine has to be taken from SPB/SFX. This will be agreed with the intrument.
FXE
- Delay servo stages have been commissioned. Right now only one stage is being used.
SQS
- Integration of the photonic science camera is progressing. Status not clear.
- MPODS power supplies are behaving strangely. CY will ahve a look.
- The pnCCD is supposed to be used next week. SQS want to use channels dedicate to other components and work out a temporary solution. AE requested the list of channels to be used but no answer has been received so far. Also, proper CRDs to start preparing the propoer implementation of the controls is still missing.
SCS
- Part of the uTCA system will need to be installed in the hutch (it was planned for the rackroom). Discussion channel is open with AE.
MID
- Servo motors require fw updates. Being agreed with AE.
- Loop 7 update is being coordinated for this week between MS and UBoesemberg.
HED
- For Loop 6 and 8, as well as smaract stages AE is waiting the go ahead from HED to switch on the Beckhoff modules.
OPT Lasers
- Laser beam has to be deivered to SCS in 2 weeks. Fw has to be uploaded in the PLCs. AE got the fw export and should upload it by friday this week.
- There is the request to make the timing signal independent between the SASEs. Will be discussed offline with AE. It should be possible in the winter shutdown.
XRO
XPD
VAC
DET
- Karabo 2.4.1. improves the pipieline stability. The deployment is strongly suggested to MID and SPB. ==> Deployment schedule for next week monday.
AE
ITDM
EET
- GDB cables have been completely produced and are bein installed this week.
- Schedule for the Loop 10 and 11 cables installation is confirmed. IN KW25 would be possible to bring the loop up.
CAS
SRP
TS
AoB
- Presentation showing the MPS schedule is attached and is showing when the emergency power off system will be triggered. The Beckhoff modules shut down is being organized by AE. It is noted that the instruments should organize the temporary power supply for the vacuum system.
|
Attachment 1: Technical_Integration_Meeting_07.05.2019_-_Copy.pptx
|
77
|
07 Aug 2019, 11:55 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 07.08.2019 | XO
The accelerator is now working at 2.25 MHz. Kicker can be used. DET informs that for repetition rates different to the ones been used so far the calibration can be significatively different.
FXE
SPB/SFX
- Hexapods are being integrated.
- Master loop has to be updated. EEE to agree offline with SPB/SFX
SCS
SQS
- Commissioning of smaract stages done. 1 encoder cable is being checked (seems a problem of definition).
MID
- DPS turbo pump issue. A software workaround exists. The problem is that the used controller has not been commissioned firmwarewise before. This is not a showstopper and wil be addressed later.
HED
Optical lasers
VAC
XRO
XPD
DET
- Offline calibration update has been performed in SCS. Tests are foreseen for today.
EEE
- A new karabo device updating the digitizers with the beam parameters in real time has been successfully tested last week.
CAS
ITDM
SRP
TS
AoB
The dispatch/tech. integration meetings will be re organized in the near future. Slides are attached. |
Attachment 1: Technical_Integration_Meeting_07.08.2019_-_Copy_(4).pptx
|
16
|
06 Mar 2019, 10:31 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 06.03.19 | SPB/SFX
- CSS component commissioning. Concept and implementation finalized. EPLAN has been modified. PLC modification has to follow.
- Issues concerning the simultaneous operation of more Jungfrau detector modules has been solved. Additional tests ongoing.
- CRL implementation in the hutch will happen in April. AE and EET involved. ==> ZA needs the documentation of the CRL. The point is SRP to be able to evaluate the focusing properties to give beam permission after installation. TH will ask directly PVagovic.
- AGIPD motion. Prelminary tests are being performed to be ready for the final tests in the march shutdown.
- It is possible to operate simultaneously the Agipd and Jungfrau detector. One issue is the restarting the Agipd afterwards. The issue is non critical and is being solved by DET/CAS.
FXE
SQS
- exhaust line for explosive gases has not been tested so far and no information is available to SQS. Urgent. SRP should comment.==> MMeyer is following up the issue. ==> MM has got all the documentation and approval needed. The line can be used. XPD and CAS on it.
SCS
- When operating the machine in the train pattern (not 10 Hz) mode and pulse on demand mode the data from the XGMs in XTD10 and SCS is not recorded.
MID
- Issue with the remote control of the ion pumps.MID OPT now ok. MID exp being implemented (waiting for some HW + Support from CY)
- AGIPD, Diamond and Epix detector tests succesful. AM thanks the technical groups for the support.
HED
- Si bounce monochromators - Chiller leaks. Will be repaired in the next shutdown. ==> Waiting for delivery of parts. Not clear whether can be fixed in the next shutdown.==> Ongoing.
- Cables for the experiment hutch are being installed but some quality issues occured. Last pallets of cables have been sent back for proper confectioning. It is possible that there will be some delays. KA will discuss with LW how to prioritize cables to eventually minimize the impact on the commissioning. ==> Quality issues are being addressed. The company increased the manpower for cable confectioning and installation. KS prepared a list of priorities. Ongoing.
- Si- mono commissioning ongoing. Cameras for pico motors have been installed.
- CRL2 in XTD6 - issue wit motors losing steps. Will be fixed in the March shutdown.
- DAQ is ready. Data sources list has been sent to CAS. Will be also sent to ITDM for implementation.
- Commissioning run proposal. Elogs to be used will be discussed with ITDM offline.
- AE informs that they will be probably able only to provide fw for loops 5 and 7 by the end of March (collision with many shutdown activities). PG will send details to KA. This will eventually require a decision concerning priorities.
OPT Lasers
- Modules for the time stamp have to be installed by AE. How long does it take? Will be discussed offiline with PG. ==> Installation dates: SASE1 in summer shutdown, SASE3 being worked out, SASE2 will follow. Workaround with time stamp is being investigated.
XRO
- In SASE3 additional safety shutters issue: Hardware will be ready by middle of Feb. On the 24 and 25. the installation and the modification of the EPS loop should take place if D3, SRP agree on the change request proposed by HS and MD. ==> Still no official decision from D3 and SRP. AE would like to get as many info as possible in advance to start preparing the loop update. According to MDommach NJardon is supposed to be already in the loop. ==> Concept in written has not yet been communicated to SRP and AE. ZA will talk to HS. ==> HW is installed. Loop update can happen monday or tuesday. The proposed additional radiation safety measures for SASE3 were discussed with Zunaira Ansari. A test is foreseen for 5 March. Implementation in the SEPS system will be directly coordinated between Zunaira and Nerea. ==> Test successful. Limit for SASE3 has been nor raised to 1.3 keV.
XPD
VAC
DET
AE
- Data Correlation issue test between MCP detector and XGM - PG: Workplan has been made. Additional tests needed and have to be planned with beam.
ITDM
- Commissioning proposals form last year: The data will be moved physically to desy soon. ITDM will send an e mail aroung to inform the relevant people.
EET
CAS
- Who is responsible for the bunch pattern recording for the different instruments? CAS will clarify with ITDM and AE. ==> Ongoing.
SRP
- The self rescue training is supposed to become part of the access requirement in the DACHS system for the tunnel. This caused a lot of concerns during the meeting (visitors? Access to components only in the very firrt part of the tunnel ). PSPO will discuss with SRP .==> SRP is trying to find a way to minimize the impact of this training on the XFEL employees. Discussion with DESY needed. ==> The implementation date is the 01.05. The legal requirements are quite strict. SRP is trying to find a solution with DESY (proper training every 3 yrs + yearly updates? to be seen). Advice from SRP is to get the training. SScherz can support booking the trainings.
- HED Radiation interlock issues: no agreement yet to get beam permission. Another meeting is planned for tomorrow (SRP chairs).
- Procedures for the electrical safety trainings and appointments are being clarified (UB, TH, WUS)
AoB |
4
|
06 Feb 2019, 11:13 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 06.02.19 | SPB/SFX
- AGIPD commissioning and tests. ==> intervention on the wings is ongoing.
- CSS component commissioning. RBean is discussing with AE. By the end of the week the changes could be implemented.
- Loop 14 (Jungfrau) is needed for next week to start the commissioning. AE infrastructure is ready. The CAT cables measurements not compliant with XFEL standard, have to be re-measured. It was supposed to happen on Monday, but Fa. Bohn had problems with the measuring device. PSPO tries to apply pressure and get it done asap. In parallel AE will communicate to ITDM the number of ports required to prepare a temporary connection between D.22/D.23.
- CRL implementation in the hutch will happen in April. AE and EET involved.
FXE
SQS
- REMI chamber was installed. Final modifications to the DPS were done. Now the system is pumping down. Bake will be turned off during the WE.
- CYoungmann is commissioning the Mpods.==> Working now.
- The chain digitizers-triggers-software is being commissioned to allow online analysis. AE, CAS required and involved.==> Ongoing
- New requirement document will be submitted today for a new slit system component (not for this SD). ==> Ongoing.
- exhaust line for explosive gases has not been tested so far and no information is available to SQS. Urgent. SRP should comment.==> MMeyer is following up the issue.
SCS
- PLCs have been all installed. Firmware deployment has to be pushed. AE is on it.==> Ongoing and high priority.
- 1 Terminal needs to be exchanged. It is needed for next week. Eplan has been updated. AE has to implement the change now.
- Concerning the smaract stages a technician is today here. If anybody is interested, please contact JTDelitz.==> The component has 17 motors but only 15 were included in the CRD and therefore controlled.
- Detector group is working on the fastCCD. ==> Today the cooling rod will be installed.
MID
- Issue with the remote control of the ion pumps. It is not possible to switch on and off the pumps remotely due to the fact that a wrong terminal was used . It seems this was also the same issue in SASE1 and 3. AE and EET are on it to fix it and update the doucumentation. ==> MS is doing some test today to see whether the tunnel solution could be implemented in a provisional way.
- Fa. Schulz did not manage to pull all the MID EXP cables by Tue afternoon as requested. Fine tuning of whoch cables are needed to start the loop commissioning and whoch ones can be postponed has to be done and driven by EET/MID (M. Flade/JHallman) ==> Being finalized.
- On Monday afternoon (17:00) a power cut caused by works on the SASE emergency power off caused the PLC to be switched off and additioanl efforts to bring them on again. This intervention was not known to MID and not planned in the winter schutdown list of activities. Technical Services is/will be reminded that proper communication is needed.==> Other unexpected power cuts due to MPS works both on Monday and today. The communication has to be improved (via SRP). In addition, also an automatic chain of communicaton has to be set up (TS?) to notify relevant peopole when the power is down.
HED
- Loop 2 needed for commissioning. ==> Commissioning starts tomorrow.
- Tomorrow the commisisoning of the monochromator in the tunnel and CRL in the optics hutch will start. ==> Mono 1 and 2 commissiong is ongoing.
- hires mono water connections will be reworked in March.
OPT Lasers
- In SASE3 commisioning isd ongoing and there are no concerns about having the laser ready in July
- In SASE2 commissioning of the seeder started.
- Issue with the door is being discussed with TS. ==> Door being fixed. Then the commissioning can start.
XRO
- In SASE3 additional safety shutters issue: Hardware will be ready by middle of Feb. On the 24 and 25. the installation and the modification of the EPS loop should take place if D3, SRP agree on the change request proposed by HS and MD. AE is involved and has allocated resources. It is not clear to whoch extent CAS is involved. This should be clarified, also for proper CAS resourced allocation. ==> No feedback received but CAS is not involved a lot (mainly AE).
- For this friday SRP schedule a test of the GATT. SQS/SCS informed and part of the activity. ==> Successful.
- During the installation of mirrors for SASE3 with InGa an issue occured. While pumping down (slowly) foam was generated and it required baking of the system to be able to pump it and bring it to ion pumps vacuum level. Tests are needed to finalize the proper procedure. In general, all the instruments dealing with mirrors should contact XRO (M.Vannoni) for proper venting and pumping down of the system to avoid surprises.
XPD
VAC
- Mono in XTD6 commissioning. AE and XRO involved.
DET
- AGIPD calibration is being prepared
AE
- DESY will reboot the timing system next monday. BF circulated a mail about that. ==> Has been postponed. No new date yet.
- Instruments have been already informed about the new timing feature.
ITDM
- Switch of the storage in SASE1 was succesful. Testing ios ongoing. OK so far. In the next days other tests with detectors will be done. (IBM technician also at XFEL today) ==> Done. Test to check the possibility for the users to read directly the raw data is being done.
EET
CAS
- Gateway has been updated.
- Karabo roadmap will be sent by mail in the next hours
AoB
Next technical integration meeting (Wed 13.02) will be anticipated at 9 due to the General assembly called for 10:00. |
|