Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 221     Entry time: 03 May 2021, 10:06
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 03.05.2021 
General Announcement:
- The deadline for submitting the summer maintenance tasks is ended. In case you have not done so, please submit it as soon as possible.
- Monica T. as DRC invites people to attend the DRC jour-fixe meeting.

CTRL:
- Bug fix for the device clone is prepared and will be deployed today. The clone devices will go down for a couple of minutes only.
- ADC 412 bug: there is a fix and instruments shall get in touch with their contacts for the deployment.

DA:
- One OCD call related to Karabo bridge and usage of online monitoring: the problem was not related to Karabo but with an environment conflict.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- All PP-lasers are up and running.

UNSYS:
- Waiting for the ZZ in SA1 and SA3.

SPB:
- User experiments last week went well again.

FXE:
- Nothing to report.

MID:
- All fine at MID.

HED:
- HED run last week went well - quite successful with tests with Laser.
- Missing Train-ID issue was reported to expert groups; All the devices are not correctly seen (arriving some trains later); 
Steffen Hauf says CTRL are working and will be ready to test. There is a chance for tests in the coming week or still this week. 
An offline discussion will take place between CTRL and HED.

SCS:
- Nothing to report.

SQS:
- Nothing to report.