SASE1 Status and SASE3 Readiness Technical integration and coordination
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 592     Entry time: 03 Mar 2025, 09:48
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 03.03.2025 
General Announcement:
- For next Friday 07.03 UOM a jitter report from instruments is expected together with presentations from groups using beam during this FD week.

CTRL:
- Nothing to report.

DA:
- Not present.
 
EEE:
- Nothing to report.

VAC:
- Issue with vacuum at HED Mono on Sunday morning 06:40AM: spike on vacuum happened (needs investigation with HED and EEE to further understand it). Recovered half way by HED colleagues. 
Please do not hesitate in calling VAC-OCD in such situations. The V0 closed and was masked at MPS - now it is back unmasked (Desy-MXL will investigate).

XPD:
- Nothing to report.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Not present.

UNSYS:
- Nothing to be reported.

SPB:
- Energy drop on Saturday 02:20AM (bunches not lasing) was seen (fixed); vacuum spike in the chamber being investigated by SPB/SFX.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- Apart of the VAC, all fine.

SCS:
- Discussion with BKR will be done.

SQS:
- Nothing to report.

SXP:
- Nothing to report.