Subject: Notes XO Integration Meeting 03.04.2023 
General Announcement:
-	 

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Small intervention in lasers uTCA today: please save data; this was organized with LAS. 

VAC:
- Not present.

XPD:
- Hirex spectral integral was fine; nevertheless, a threshold setting was changed.

DET:
- MID called for the Epix detector: strong current for the Mpod was observed and further investigation to be done.
- DSSC showed a minor problem (reported on a phone call) that will be investigated.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Nothing to report.

UNSYS:
- Everything fine.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Need to get in touch with XRO as beam was looking like to be blocked by some device.

HED:
- Nothing to report.

SCS:
- Not present.

SQS:
- Nothing to report.

SXP:
- Not present.