SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 82
Entry time: 26 Aug 2019, 09:52
|
Author: |
Adriano Violante |
Location: |
General |
Severity: |
Information |
Subject: |
Report after dispatch meeting 09.30 |
|
|
XO
- Today a test of the fire alarm system will take place. Mail has been circulated by SRP.
- From next monday the dispatch meeting time slot will change to 8.30. Chair will be with XO.
FXE
- Leak in the LPD cooling system has been found. DET on it.
- Laser went out of synch several time during the last weeks. Being addressed with CAS.
- Mono middle layer is not working properly. Calibration parameters are not reloaded correctly after restart. CAS on it.
SPB/SFX
- CSLITS - discrepancies between the behavior of normal motors vs MC2 motors. CAS on it.
SCS
SQS
MID
- During last WE big issues with the AGIPD were experienced. Probably calibration pipeline related. DET on it.
HED
- Hirex 2 commissionig ongoing.
- Mono commissioning - cameras were found not to work. CAS/EEE to check.
- Access to the experiment hutches will be restricted this week due to laser shots tests.
Optical lasers
VAC
XRO
- SASE1 FEL imager was damaged following the last power cuts and EPS/MPS issues. Will be replaced by Thursday.
XPD
DET
EEE
CAS
- 2.6.1. ready to be deployed. Deployment schedule has been agreed with individual groups.
ITDM
SRP
TS