Group Selection Page
HELP
DOC
Controls Group
Data Analysis Group
ITDM
WP76
DET
Vacuum
XRO
EEE
WP78
WP74
FXE
SCS
SPB
MID
HED
SQS
SXP
Sample Environment
Photon Commissioning Team
Operation
PSPO
XO
TS
|
Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 66
Entry time: 10 Jul 2019, 16:16
|
Author: |
Adriano Violante |
Location: |
General |
Severity: |
Information |
Subject: |
Minutes of the Technical integration meeting 10.07.19 |
|
|
XO
- In SASE3 the apertures of the GATT have to be realigned. The upstream apertures have been alreadz realigned. The downstream ones will be probablz realigned tomorrow. If not succesfull some restrictions of the operation have to be evaluated. ==> Done.
- Turnstile issue: 2 days ago the hall was not accessible for some hours because of non functioning turnstiles. The problem was a change in the desy firewall configuration that lead to the transponders system not working.
FXE
- Loops update has to be coordinated between EEE and FXE. No feedback received from EEE. AG will remind TKorsh. Still pending.
SPB/SFX
- No major issues
- BB is coordinating the loops update with SPB/SFX
SCS
- No Major issues
- Loop1 has been updated
SQS
- Aerosol will be commissioned next week. EEE waiting for the precise dates.==> Still waiting.
MID
- XRO will agree with MID which functionalities of the attenuators in XTD1 have to be tested. 'to do list' will be issued. XRO will put the results in the operation logbook. If XRO will not make it to test everything, MID will be informed and will help.
- XTD 6 will be closed tomorrow after lunch. CY points out that there is a list of issues to be fixed in XTD6 (e.g. motors not working) and many people in CAS are ill, hence, not available, NJ checks with MS and CY sends the list to EEE.
- By the end of the week MID should send the requirements for the vacuum interlock to EEE.
HED
- The monochromator can be cooled down now. The vacuul is still not optimal but the device is operable,.
- Today loop 3 will be updated.
Optical lasers
VAC
XRO
- M1 in SASE2 and 1 will be commissioned this week end. New positions will be found and written diwn in the logbook. Difference of some mm with respect to the old positions is expected.
XPD
DET
- Tests with Karabo 2.5.0 OK.
EEE
- Electrical safety regulation. From the beginning of July the new electrical safety regulation is supposed to be in place. According to this regulation the work at the back of the racks in the XHEXP1 and in the entire racks in the tunnels can only be done by certified EFK (Elektrofachkraefte) or by EUPs with an additional training. The additional training can only be provided after summer. The nomination of XFEL EFKs is suffering a delay due to the fact that is not clear who should nominate them (TS, UBR, HR?). PG reported the problem and also the fact that no official statements were made in the past concerning the topic. THaas is trying to clarify the status, and come up with a statement and proposal in the Operations meeting. ==> there was no meeting on Friday. Still pending. ==> implementation of the electrical safety regulation has been postponed to the end of the year (mail from SRP).
CAS
- Deployment of Karabo 2.5.0 has been completed
ITDM
SRP
TS
AoB
|