Group Selection Page HELP Controls Group ITDM Vacuum WP78 SPB SQS XO ToBeMigrated2XWiki ToBeMigrated2GitlabPages ToBeMigratedByGroup Migrated2Zulip Archived2PDF not2MigrateOrArchive
SCS SXP Migrated2Zulip Photon Commissioning Team XRO DOC HED Migrated2Zulip WP74 MID PSPO_XO XO_Operation SQS Migrated2Zulip FXE Migrated2Zulip DET Sample Environment SPB Migrated2Zulip
SASE1 Status and SASE3 Readiness Technical integration and coordination
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 77     Entry time: 07 Aug 2019, 11:55
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Minutes of the Technical integration meeting 07.08.2019 

XO

The accelerator is now working at 2.25 MHz. Kicker can be used. DET informs that for repetition rates different to the ones been used so far the calibration can be significatively different.

FXE

SPB/SFX

  • Hexapods are being integrated. 
  • Master loop has to be updated. EEE to agree offline with SPB/SFX

SCS

SQS

  • Commissioning of smaract stages done. 1 encoder cable is being checked (seems a problem of definition).

MID

  • DPS turbo pump issue. A software workaround exists. The problem is that the used controller has not been commissioned firmwarewise before. This is not a showstopper and wil be addressed later. 

HED

Optical lasers

VAC

XRO

XPD

DET

  • Offline calibration update has been performed in SCS. Tests are foreseen for today.

EEE

  • A new karabo device updating the digitizers with the beam parameters in real time has been successfully tested last week.

CAS

  • 2.6.0. being prepared.

ITDM

SRP

TS

AoB

The dispatch/tech. integration meetings will be re organized in the near future. Slides are attached.

Attachment 1: Technical_Integration_Meeting_07.08.2019_-_Copy_(4).pptx  44 kB  Uploaded 07 Aug 2019, 14:08
ELOG V3.1.4-7c3fd00