Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 77
Entry time: 07 Aug 2019, 11:55
|
Author: |
Adriano Violante |
Location: |
General |
Severity: |
Information |
Subject: |
Minutes of the Technical integration meeting 07.08.2019 |
|
|
XO
The accelerator is now working at 2.25 MHz. Kicker can be used. DET informs that for repetition rates different to the ones been used so far the calibration can be significatively different.
FXE
SPB/SFX
- Hexapods are being integrated.
- Master loop has to be updated. EEE to agree offline with SPB/SFX
SCS
SQS
- Commissioning of smaract stages done. 1 encoder cable is being checked (seems a problem of definition).
MID
- DPS turbo pump issue. A software workaround exists. The problem is that the used controller has not been commissioned firmwarewise before. This is not a showstopper and wil be addressed later.
HED
Optical lasers
VAC
XRO
XPD
DET
- Offline calibration update has been performed in SCS. Tests are foreseen for today.
EEE
- A new karabo device updating the digitizers with the beam parameters in real time has been successfully tested last week.
CAS
ITDM
SRP
TS
AoB
The dispatch/tech. integration meetings will be re organized in the near future. Slides are attached. |
|