563
|
06 Nov 2024, 09:38 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 06.11.2024 |
General Announcement:
- Invitation for scheduling meeting was distributed to some groups. The Winter maintenance period is relatively short.
- UOM next Friday takes place with presentations from FD studies and jitter reports from the instruments.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Nothing to report; all fine.
XPD:
- Nothing to report; no news on PES.
DET:
- Nothing to report.
- Successful tests with high Z yesterday.
ITDM:
- Nothing to report.
XRO:
- Nothing major to report; prepared for the 30keV studies.
LAS:
- Nothing to report.
UNSYS:
- Yesterday problem with PS motor in cell 25/SA1: solved by ZZ;
- Apple-X and PS cell 26/SA3: tomorrow 7AM a ZZ to try to fix problems.
SPB:
- All fine.
FXE:
- Not present.
MID:
- Not present.
HED:
- Not present.
SCS:
- Nothing to report.
SQS:
- Nothing to report.
SXP:
- Not present. |
466
|
06 Nov 2023, 09:53 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 06.11.2023 |
General Announcement:
- As PRC, Jan G. reports that on Saturday morning no beam permission at the North branch happened. An issue with XTD2 solid attenuator vacuum happened and together with VAC-OCD the threshold was changed
to allow continuation of beam delivery. A ZZ will be needed today to fix the vacuum leak;
On Sunday around 09:20 an issue with accelerator quadrupole magnet in A21 caused downtime initially until noon (SA2) and around 16:00 (North branch); also D3 had to come onsite to reset burn through
monitors in the aftermath.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- MID had couple of uTCA cards offline that needs to be rebooted. This will be discussed with MID offline.
VAC:
- Preparing for the needed ZZs in XTD2.
XPD:
- Nothing to report.
DET:
- Couple of tasks for the DSSC (SQS) to reconfigure the detector;
- DAQ of DSSC was affected by failure of GPFS servers.
ITDM:
- GPFS issue happened last Friday and was fine over the weekend.
- An update of the clients will happen today in all SASEs. This was agreed with instruments.
XRO:
- Nothing to add to what was reported by the PRC.
LAS:
- SA2 issue with pulse on demand will be discussed with MID.
UNSYS:
- Nothing to report.
SPB:
- User beamtime went OK even with downtimes during weekend.
FXE:
- Nothing to report; last night shift (Sunday night) cancelled as program was finished on Saturday.
MID:
- Supporting today the short pulses activities; from tomorrow interventions at MID can be scheduled.
- Regarding laser issue: when changing sequence for using Laser showed trains with pulses and trains with missing pulses. Running macro was changed for working to 1 pulse per second.
- Users were happy and the program was accomplished in full.
HED:
- Not present.
SCS:
- Detector tests to be done by end of the week.
SQS:
- Affected by beam losses but overall a lot of useful data was acquired.
SXP:
- Nothing to report. |
266
|
06 Oct 2021, 09:28 |
Andreas Galler | General | Information | Notes XO Integration Meeting 06.10.2021 |
General Announcement:
CTRL:
DA:
EEE:
VAC:
XPD:
DET:
- nothing to report (SPB reports JF1M issue --> suspected readout board issue)
ITDM:
- issues with Nagios
- misconfig by puppet mangement (DESY)
XRO:
LAS:
UNSYS:
- Phaseshifter tables for higher energies in blue week had been uploaded
- two quad movers from SA2 moved to 0
- triggered by doocs --> quad movers moved back but it is unclear if they actually returned the BBA optimized position
- clarification with M. Scholz confirms that quad movers did not move.
SPB/SFX:
FXE:
- User Experiment starts
- C&C update requested until next week for LPD (uTCA)
MID:
HED:
SCS:
SQS:
AOB:
|
449
|
06 Sep 2023, 10:03 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 06.09.2023 |
General Announcement:
-
CTRL:
- Issues with cameras are being addressed.
DA:
- Nothing to report.
EEE:
- Yesterday issue with SEPS/HED being investigated/addressed.
VAC:
- Not present.
XPD:
- Nothing to report.
- As PRC, Naresh K. reports 1: new SEPS interlock at HED not properly working; 2. FXE reported crosstalk from SA3 pulses being lasing at SA1; also when switching 0 pulses in SA1 the SA3 went to zero also.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Mikako M. is aware of HED SEPS issue and is helping EEE.
LAS:
- Nothing to report.
UNSYS:
- SA2/cell25 fixed (terminal replaced) and is functioning.
SPB:
- Nothing to report.
FXE:
- Crosstalk SA1/SA3.
MID:
- Not present.
HED:
- Issues with ADC fixed by EEE (rear module) - seems a recurring feature with a 1 week frequency.
SCS:
- Motors at ending station solved by DOC;
- Issue with bunch/crosstalk.
SQS:
- Nothing to report.
SXP:
- Not present. |
257
|
06 Sep 2021, 11:00 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 06.09.2021 |
General Announcement:
- XO thanks the instruments for posting in the Operations e-log.
- Jan G. says calorimeter measurements last Friday on HED hutch took place in order to measure transmission of pulse energy in the hutch and compare with tunnel HED-XGM.
It is found a factor 2 loss - half beam intensity arriving at the end of the hutch.
- Lorenz K. says that the Barista machine triggered a fire alarm. TN did a check and may be caused by the self-cleaning program of the machine by producing enough steam.
- Call for tasks to be carried on next Winter maintenance period were sent out to the are sent out via e-mail last Friday. Groups shall submit one group list by 30.09.2021.
CTRL:
- From tomorrow morning all the mails sent to the "controls integration" ticketing service will be offline due to an update. Please contact DOC instead. An e-mail will be sent as soon as the service is
back.
DA:
- Nothing to report.
EEE:
- OCD calls from SQS last week were solved.
- Nerea J. and F. Wolff-Fabris say the issue with SQS EPS is temporarily solved by now (masked signal at the Big Brother). SQS has to plan when it wants the EPS running.
VAC:
- Quiet week in terms of OCD.
- Today in the morning: please refrain to use this morning any SA3 device like GATT.
XPD:
- Nothing to report.
DET:
- Follow up of the pnCCD detector: upper part of the detector has scratches after Thursday accident. SQS will replace parts this week. The lower part of the detector has also some issues (noisy).
It is unclear if the detector can be used.
ITDM:
- Today and tomorrow ITDM carries the integration of the offline storage into the new system (new storage blocks; it shall be unnoticed by the users). The old one goes out by replacement.
XRO:
- Apart of the beam point instability @ HED (stochastic instabilities that appear from time to time) there is nothing else to report.
LAS:
- Change repetition rate at SA2 PP-laser this week.
- SA1 has a higher jitter than normal that has to be investigated on-site.
UNSYS:
- All fine at Undulators.
SPB:
- Running night shifts: on SAT night some X-ray trains not arriving; It did not disturb operation but a bit disturbing.
FXE:
- Lost of pulses and many issues on Saturday such as instability and tuning without prior communication. To FXE team.
- F. Wolff-Fabris says the beam became more stable on Sunday afternoon after the restart of a server and the feedback for the compression.
MID:
- All fine at MID.
HED:
- Suffered from beam jitter: measurements were done with different mirrors settings, CRL configs; MID branch. Analysis ongoing this week (Sebastian Goede).
SCS:
- Nothing to report.
SQS:
- Nothing to report. |
339
|
06 Jul 2022, 10:22 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 06.07.2022 |
General Announcement:
- Interlock tests in tunnels start today so there is no tunnel access today. Tests are finishing tomorrow and then tunnel search is taking place.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Deployment of new version of new ADC is taking place. Tutorials for new features are offered for interested groups. Please contact Bruno Fernandes for information.
- SA3 work is done (Nerea J. / Maurizio V.)
VAC:
- Not present.
XPD:
- Everything is fine.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Maurizio V. reports that vacuum level in M6 chamber in XTD10 is not progressing well and it is under investigation; some measures and discussions may take place in 1-2 weeks if things do not go well;
Apart of this, tests were successfully done together with EEE and CTRL.
LAS:
- Back on track and PP-lasers are going up.
UNSYS:
- All good.
SPB:
- Preparing for tests and configurations for the start of next user run.
FXE:
- Today there will be Mono heater tests in XTD9 MONO.
MID:
- All fine at MID.
HED:
- Nothing to report.
SCS:
- Shutdown activities are ongoing; it will discuss with EEE and CTRL on updates.
SQS:
- Not present. |
140
|
07 Jul 2020, 13:23 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 06.07.2020 |
General Announcement:
- Since the end of the shutdown last Friday, the current Program is "Access/Tuning/Setup";
- DESY/MXL has started ramping up the Gun, powering and testing the Magnets and phasing the RF stations.
- Currently it has electron beam transmission up to the TLD and is ahead of the planned schedule for these days.
CTRL:
- Data logger issue: Friday CTRL has rolled back to the old data login system. Meeting today at 11:00 with involved groups to define next steps.
Information will follow via readiness mailing list.
DA:
- No issues to report.
EEE:
- Issue with HED PLCs: a fuse has been tripped and it has been replaced. A CPU was broken and is believed to have caused the fuse tripping.
This is the first time this happens in the facility.
- Cabling activities in SCS is scheduled to take place this week.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- ITDM has made a request to DESY-IT for a routers restart. This will cause the network to be interrupted and restarted. Also Karabo will restart.
A meeting today will define the proper time for this action, currently schedule for tomorrow morning. Information will be send to the readiness mailing list.
XRO:
- Not present.
LAS:
- All lasers are up and running again.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- Few problems with motors were already solved last Friday by EEE.
HED:
- All going fine.
SCS:
- Not present.
SQS:
- Nothing to report. |
511
|
06 May 2024, 09:21 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 06.05.2024 |
General Announcement:
- Summer maintenance task list was sent to the groups. Please contact XO in case of questions or if your group did not receive the list.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Discussion ongoing for the summer maintenance tasks.
VAC:
- No OCD calls for VAC and systems seemed to be not affected by this morning's power glitch at 05:47AM.
XPD:
- Everything fine with diagnostics.
DET:
- Nothing major to be reported.
- 500k AGIPD over the weekend was helped by DOC and DATA OCDs solved.
ITDM:
- Nothing to report.
XRO:
- Event of misalignment of M6 on Friday for SA3/SXP under investigation. It will be discussed with SXP.
LAS:
- Not present.
UNSYS:
- All fine with undulators.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- Nothing to be reported.
HED:
- Running and thanks to DOC and OCDs for AGIPD help.
SCS:
- Not present.
SQS:
- Nothing to report.
SXP:
- Not present. |
117
|
06 May 2020, 14:45 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 06.05.2020 |
General Announcement:
- SRP is invited and urged to participate in this series of meetings.
- Several groups have questions to the SRP regarding:
1. Rules on access, training and work performed by external companies;
2. Clarification in how to conduct work in the clean room among several groups;
3. Distribution of PPE/Masks;
4. Usage and disposal of masks;
5. Procedure to work in the rack rooms;
6. Hygienic rules in experimental hutches: disinfecting tools, computers, disposal of PPE.
- Friday we will discuss next week plans and also CTRL activities for next week.
CTRL:
- No issues to report;
- Announcement: to reach OCD please use 6541 and 6542.
DA:
- Planning with instruments the support for coming weeks.
EEE:
- Ongoing with planned works;
- Cabling: SQS cabling will start on next Monday (EEE and SQS will organize the task). Afterwards the cabling installation takes place at FXE.
The installation is done with external contractors - EEE needs clear information from SRP on the Covid-19 trainings and rules for external companies.
VAC:
- Working on the tunnels accordingly to this week's plan:
1. small issues at XTD10: chamber does not fit and needs some re-work at external company;
2. Preparations in XTD9 for IMG screen change.
- No issues with distancing regulations;
XPD:
- No issues to report - working as planned: XTD6 installation of Hirex filter; XTD9 exchange of Imager screen.
- Unpacking and mounting the hard-Xray PES chamber.
- XPD needs clarification from SRP on work procedures in the clean room;
- After exchange of IMG screen, XPD needs to check functionality by moving motors. EEE and CTRL are aware and shall not be a problem.
DET:
- Going back on-site to work in the prep Lab.
- Usage of labs has to be coordinated among the groups.
ITDM:
- Nothing to report.
XRO:
- Not present.
LAS:
- SA1 pump-probe laser re-stared; SA2 PP-laser is progressing;
- LAS needs answers from SRP on the regulations for external company which is coming this week.
SPB:
- Nothing to report: working as planned on re-start;
FXE:
- Started working in the control and main hutches. Group has plans for next two weeks and is organizing tasks together with DET and LAS.
- E-mail to health@xfel.eu is not answered. FXE will not allow external companies coming in unless if trained.
- FXE has set own rules in how to use tools, disinfect tools and computers. FXE waits clarifications from SRP.
MID:
- General progress accordingly to the plan: updates have been made; tests of motors are ongoing.
HED:
- Nothing to report;
SCS:
- Not present;
SQS:
- Started with checking vacuum systems. |
496
|
06 Mar 2024, 10:12 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 06.03.2024 |
General Announcement:
- This is a facility development week and on Friday's UOM we will get reports on recent weeks' jitter observations from the instruments.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Clean tent is moved from XTD10 to XTD2 for XFELO activities on the summer maintenance period.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- E-mail was sent to xo-info on the intervention of migration THU morning for about an hour.
XRO:
- SA1 ATT watchdog presenting typos and acting with the wrong bunch number: Mikako M. reports the same (copied) watchdogs in other SASEs do not show this error and the SA1 is now fixed.
Origin for the error in SA1 is not understood and difficult to find.
- All Attenuators in SA1 were moved 1mm up to help reaching an area without damage.
LAS:
- AMPHOS shutter issue over the weekend: the ad-hoc procedure is no longer in place and the issue is fixed.
UNSYS:
- Motor and electronics in PS SA3/cell12 were exchanged yesterday.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- Not present.
HED:
- Nothing to report.
SCS:
- Girder system showed an electronic problem that requires hardware change; discussed with Sylvia and E-planners.
SQS:
- Not present.
SXP:
- Not present. |
400
|
06 Mar 2023, 10:06 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 06.03.2023 |
General Announcement:
- Operation this week consists in a Facility Development week. Many FDs are scheduled and if you plan any activity that may interfere in tunnels please contact either XO or the PRC.
- As DRC Patrick Gessler informs there is no DOC this week and all calls will be handled by him who then coordinate with respective DATA OCDs and groups.
CTRL:
- Nothing to report.
DA:
- Uncovered a situation last week: old data saved by DAQ (HED) is now understood and DA will apply a fix.
EEE:
- Remind the deployment of ADQ in all setups apart of SQS today before lunch time.
VAC:
- All fine with VAC; a short interruption on Friday in SA1 happened due to some tests with electronics. To be redone possible today.
- As PRC Martin D. reports a 5-6 hours downtime on night to Saturday due to issues with interlocks at the Injectors. It was fixed by Desy colleagues.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Nothing to report.
UNSYS:
- Nothing to report.
SPB:
- All fine and data were collected for last week's user.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Fight with beam jitter last week; For the weekend a change in focusing configuration helped to get acceptable situation and beamtime seemed to be successful.
SCS:
- Experiment arrived at the point of data collection. Further analysis needed to evaluate if successful or not.
SQS:
- Nothing to report.
SXP:
- Not present. |
392
|
06 Feb 2023, 12:48 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 06.02.2022 |
General Announcement:
- A. Galler shows at the TTFinfo schedule where to find information for operation calendars.
- A. Silenzi inform that the Jour-Fixe takes place and instruments shall be present to inform on needed requests to DRC/DOC.
- As PRC, Harald Sinn informs the agreed RF window that was set on Friday was reversed on Saturday. Do not hesitate in contacting the PRC in such situations.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Two OCD calls on weekend:
1. Issue with PP-laser setup at FXE/Mono in tunnels - to be followed by PLC team;
2. Issue with SA3/SCS Exit SLIT in the tunnel to be followed up by ZZ. Couple of hours are needed in tunnel to try to fix it without guarantee of success.
VAC:
- Performing ZZ and breaking interlock in XTD10.
XPD:
- Jan G. says chamber for calorimeter and laser power meter are being installed in SPB hutch today.
- Tests of the IMG watchdog can take place only after lunch due to ongoing ZZ access.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Not present.
LAS:
- Laser timing in SA1 is 3ns off.
UNSYS:
- Tunnel access ongoing in SA2.
- Replacement of the HXRSS crystal to take place today.
SPB:
- Wednesday morning Karabo server was down for 90min; it was fixed by the DOC.
- Chan Kim says that SPB/SFX had a wrong RF window set on Wednesday.
- Camera devices were showing issues (had to break interlock to reset camera) and needs a long term fix.
Wajid E. says CTRL investigates with high priority and it seems not to be a Karabo issue. Investigation continues at CTRL hands.
FXE:
- Nothing to report.
MID:
- Problem with FSSS that is needed for the user experiment: CTRL and SEC are looking into it.
HED:
- Setup instrument; Karabo connections solved by DOC.
- Due to RF window AGIPD tests were delayed.
- A ZZ for checking a motor can be done still this morning.
SCS:
- Troubles with motors were addressed.
- Exit slit issue still pending.
SQS:
- Nothing to report. |
576
|
06 Jan 2025, 09:42 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 06.01.2025 |
General Announcement:
- Interlock tests shall start tomorrow 07.01. In case of questions please do not hesitate in contacting XO.
- Eric Boyd says on Wednesday 10AM two hutches shall be interlocked for the tests (FXE exp. Hutch and MID optical hutch) for ~15 minutes. It shall work for both instruments.
- A. Silenzi reminds that a tentative schedule for the bring-up days was sent to the instruments and a feedback is expected to be returned by the end of today.
CTRL:
- Present but with technical difficulties; it shall be all fine for CTRL.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- No incoming calls last weeks for the XPD OCD.
DET:
- Nothing to report.
ITDM:
- Reminder that tomorrow Desy computer center will perform central maintenance; it shall not affect XFEL.
XRO:
- Nothing to report.
LAS:
- Not present.
UNSYS:
- Nothing to be reported.
SPB:
- All quiet.
FXE:
- Nothing to report.
MID:
- All fine at MID.
HED:
- All fine at HED.
SCS:
- Nothing to report.
SQS:
- Not present.
SXP:
- Not present. |
188
|
06 Jan 2021, 09:05 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 06.01.2021 |
General Announcement:
- Due to work restrictions, some of shutdown activities will not end as planned in time. This leads to a prolongation of the start-up phase starting next week. It means re-start of Accelerator and South branch will be delayed by 2-4 days while the North branch by about 1 week.
- The first 2 weeks of X-Ray delivery (2.2-15.2) will most likely be affected and photon delivery cannot be guaranteed into all beam-lines at all days. Some flexibility in planning for the commissioning tasks is expected. A detailed schedule for an upcoming week will be available on the week before, latest on Friday.
- Sara C. asks if tunnel access is allowed during this week. F. Wolff-Fabris understands tunnels still can be accessed this week apart of Covid regulations (in the context of tunnel maintenance tasks that have to be performed while tunnels are open). T. Tschentscher says the understanding is from Robert F. guidelines e-mail are still valid for this week and really important tasks may be conducted – an e-mail to Robert and Nicole pointing the task with the need of access could be sent. Steve A. reported from today’s Covid taskforce meeting that the regulations of last corona email are still valid - if there are any question send an email to health@xfel.eu.
CTRL:
- Due to incompatibility discovered after last update on Dec. 23rd, CTRL would like to update files on all microTCAs before user operation (Karabo devices) mostly likely next Friday.
- A network maintenance was performed by Desy. Please inform CTRL if issues are encountered.
DA:
- nothing to report
EEE:
- Preparing to finish the cabling in HED and MID.
- Nothing to report from PLC side.
VAC:
- nothing to report - tunnel update tomorrow
XPD:
- XPD OCD put in place during Christmas break had no emergencies calls.
- XPD expect earliest work to take place on next week.
DET:
- nothing to report
ITDM:
- Desy network team would like to do a update of the control network routers tomorrow at 1300 -> email comes to readiness
XRO:
- Proceeding with activities from last days of last year.
- No major updates. Testing the SA3 MC2 library update.
LAS:
- Lasers are down.
- SA2 seeder that took longer than expected time to be back in December after the OFF request by LSO. Probably on next OFF mode LAS has to exchange it.
UNSYS:
- Minimum gaps for SASE3 Undulator system is 10mm. Other SASEs shall be defined after the middle plan scans.
- Apple-X major work from Unsys is done.
- Quad movers are working remotely.
- Remaining task: connecting fire extinguisher system in one rack.
SPB:
- nothing to report
FXE:
- nothing to add
MID:
- nothing to report
HED:
- nothing to report
SCS:
- not present
SQS:
- A High voltage power supply with double-polarity was installed. It is the first time this is installed at SQS. |
379
|
05 Dec 2022, 09:59 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 05.12.2022 |
General Announcement:
- Dec.3rd power an drinking water maintenance: many thanks to TS and MKK groups for their efforts - tasks accomplished without any harm by lunch time (4 hs earlier than originally planned).
- Unfortunately an action by another Desy group triggered radiation protection in instrument areas. This action was not announced to XO.
Please inform XO if you encounter any damaged device. An 8D report will be prepared on this incident.
- PLCs and Karabo will be ramped up; Office network was available all time; Drinking water is already available.
- Zunaira A. says that an e-mail is usually sent to a list of persons. A. Galler says that this time we do not know if someone was informed.
- J. Szuba says only in SA1 rack rooms were out of power.
- Tobias Clever inform that every device can be switched on again.
CTRL:
- Start bringing up Karabo topics as soon as control machines are available.
DA:
- Nothing to report.
EEE:
- Tunnel loops are already properly working.
- Switching ON instruments loops as agreed with them from today on.
- uTCAs are in process to be brought back.
VAC:
- Lost some controllers and power suppliers as expected but no major issues on Saturday.
XPD:
- Survived electrical shutdown quiet well: PES and XGMs are fine.
- Second outage due to Desy group was detected first at SCS XGM which was the first device to be brought back.
- Re-starting more devices after Karabo is back.
DET:
- Nothing to report.
ITDM:
- Started to bring up the control servers and other systems.
- Comment to update done on office network switches Friday afternoon: one distribution layer is not working. Currently one runs office network in a single layer - to be investigated by NOC.
XRO:
- All systems are reconnected and will be checked when Karabo is available.
- One computer did not come back (failure of power supply).
LAS:
- Nothing to report. Seeders were unaffected to the best of LAS knowledge.
UNSYS:
- Replacement of undulator: new one in SA2/cell33 is in place and connected to control system; Needs alignment by MEA.
- Control cabinets in balcony room to be brought back.
SPB:
- Ion pump system is back online Saturday evening. Continue today with other devices.
FXE:
- To be checked today for effects from the weekend.
MID:
- All fine at MID. Most devices were OFF.
- Work on power line at the balcony room today. Wait for TS finish the work before start major switches. ITDM will wait before re-starting machines there.
- High temperature in control room and hutches is seen this morning.
HED:
- High temperature in the control room and hutches as of now.
SCS:
- Components were OFF and today switches ON again and search for damage.
SQS:
- Not present. |
363
|
05 Oct 2022, 10:11 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 05.10.2022 |
General Announcement:
- XFEL got 12 bottles of He gas (50 l; 200 bar) which are connected to the central supply. Only SA1 will receive He gas from central gas supply in order to guarantee the run until the end of 2022.
The pressure in the line will be monitored and the valve will close if unexpected drop happens. If one needs He gas please get in touch with XO.
- Winter maintenance task list: XO has received almost all lists apart of two of them. Groups missing shall submit the maintenance task list as soon as possible.
- Zunaira A. informs that if SEPS/AIBS is triggered (like last Saturday event) the procedure is to send an e-mail to rpo@xfel.eu.
CTRL:
- Follow-up of MID mirror feedback: problem is hard to replicate; yesterday happened again and recovered itself. MID reports it is stuck at exactly this moment. CTRL will investigate.
- Zunaira A. says on the aftermath of the Saturday AIBS alarm many automatic e-mails are kept to be sent and only today an e-mail saying problem is solved was sent.
Steffen H. comments that it was informed that a test of the system has to be done due to an occurring bug and currently it has to be manually reset. The test is to take place in winter maintenance time.
DA:
- Nothing to report.
EEE:
- Nothing to be reported besides the Saturday issue with SXP losing power which affected the AIBS. Zunaira A. says devices are in the UPS system (Pandora, which did not give alarm).
Oleg E. which will exchange components during winter maintenance time.
VAC:
- Not present.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- No news from LAS.
UNSYS:
- Not present.
- XO reports an issue with Phase shifter in SA3 (cells 20 and 21) which are stuck and need motor replacement. This is likely to happen next Monday as users at SCS do not plan to change photon energy.
SPB:
- Nothing to report.
FXE:
- Problem with BAM “S” not properly working.
- As PRC, F. Wolff-Fabris says a work around is in place and shall use the BAM “M” instead. FXE shall get in touch with BKR for more details.
MID:
- AGIPD preview crashing and has to be restarted.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Not present. |
166
|
06 Oct 2020, 10:36 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 05.10.2020 |
General Announcement:
- XO has sent to the support groups and instruments the call for the winter maintenance tasks. Deadline for submission is Oct. 16th.
CTRL:
- Friday night incident with signals of SA3 vacuum loop. It took hours to recover the system.
- A deployment/restart of online cluster nodes will be done today meaning 10 minutes downtime. Devices / clone devices shortly unavailable during the
deployment.
- CTRL reminds that tickets that may require Doocs bridge are better worked if sent during the week time.
DA:
- No major issues to report.
- DA will carry an offline discussion with CTRL on the cluster nodes deployment. CTRL says this is for the CPU nodes.
EEE:
- Nothing major to report. No incidents during the weekend.
- Looking into PL/fast ADC mTCA issue with SA1 PP-laser. To be discussed separately with LAS, XO after the meeting: next solution is to exchange CPU -
needing coordination with ITDM and CTRL.
VAC:
- No major issues. Karabo SA3 VAC loops look fine now.
XPD:
- PES: ZZ on Friday to fix issue with a broken gauge, mostly likely related to the power failure. Cables had to be switched. PES works again.
- Tests next week using PES: Joakim L. will set the system.
- Change of SA3 XGM settings during this week: Theo M. will change setup during weekdays.
DET:
- Nothing major to report.
ITDM:
- No OCD calls during the weekend.
XRO:
- Nothing to report.
LAS:
- Shutdown AMPHOS in SA3 PP-laser (SCS/SQS): LAS asks for one single point of communication with the instruments; This laser needs work today morning to do
not compromise the week.
- E-mail for communication can be scs@xfel.eu and sqs@xfel.eu where all group members receive the message.
- SA2 PP-laser is ready for next week.
- SA1 PP-laser still show problems with ADC cards. CPU will be exchanged - to be discussed after this meeting.
UNSYS:
- ZZ intervention last week.
- Couple of hiccups remotely fixed.
SPB:
- Nothing to report, besides issues with PP-laser.
FXE:
- ADQ with different sampling rates issue was solved by EEE.
- Plan is to work on the Jungfrau commissioning.
MID:
- MID requests if there is planned a meeting to discuss the train-ID issue. Steve A. comments that yes, a meeting will be organized next week.
HED:
- Asks on the request for a pulse on demand test during today. F. Wolff-Fabris says this has been sent to the machine RCs and will be discussed during the
RC meeting at 10:00.
As soon as a decision is done this will be communicated.
SCS:
- Nothing to report.
SQS:
- Nothing to add apart of PP-laser issue. |
355
|
05 Sep 2022, 10:07 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 05.09.2022 |
General Announcement:
- If an instrument experiences a feature of machine that does not work, please do not hesitate in contacting the PRC, who is there to support you.
CTRL:
- Nothing to report.
DA:
- On Wednesday an update with minor interruption is due to happen.
EEE:
- DOC announcement: there will be no DOC but DRC is in place (Patrick Gessler).
- Jour-fixe meeting is happening today at 13:00.
VAC:
- Nothing to report.
XPD:
- SA3 FEL Imager: under investigation.
DET:
- Nothing major to report.
ITDM:
- Maintenance of GPFS system on Tuesday (user system for offline storage will not be available tomorrow).
XRO:
- Ticket for follow up of the SRA XTD1 interlock (motor positions do not correspond to actual location - to be investigated by EEE).
- Maurizio V. will be in OCD for XRO this week (blue week).
LAS:
- Issues with timing and triggers: work around by switching OFF the pattern. Further discussion to take place.
- Laser-2 change caused a damage to SPB laser. No optical damage, only electronics.
- SCS reported laser “disappeared”. Meeting and work shall involve DESY group. XO will reinforce with Desy.
UNSYS:
- Nothing to report.
SPB:
- Issue with Laser;
- Issue with XGM: loose single shot. It was reported to the PRC.
Laurent M. says they tried to setup XGM when it went down. He proposes to setup a specific Karabo device that works only with the one in use. XPD will discuss offline.
FXE:
- Work with new cryo system this week.
MID:
- Info for DRC: MID expects to use beam on Sunday during the day.
HED:
- All fine at HED.
SCS:
- Issue with BAM stabilization. It was requested but due to issues it was turned OFF during the weekend. It took time to realize it was OFF and to find experts to bring up again.
- Power outage in some devices at the experimental hutch. TS was called and came to fix it.
- Liubov S. says problem relates to the laser interlock occurred: it searched few times before one could eventually set it.
SQS:
- Issue with ADQ digitizer of Spie devices: more than one in one crate and in interleaved mode it gives a random artefact.
It was discussed with EEE: vendor says there is nothing what can be done. If someone else has issues please join forces with SQS. |
536
|
05 Aug 2024, 09:41 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 05.08.2024 |
General Announcement:
-
CTRL:
- Nothing to report.
DA:
- Announcement: tomorrow afternoon a maintenance on online and offline calibration will take place causing a 20min downtime.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Nothing to report.
UNSYS:
- Nothing to report.
- Suren K. questions SA3 instruments on the vertical polarization setup done last Saturday.
Laurent M. and Manuel I. say that beam condition with polarized light was fine but they did not yet performed scans. Shifts in beam positions were seen but not understood.
SPB:
- Nothing to report.
FXE:
- Tuning for SA2 and SA3 influenced FXE data collection, as it was not aware of tuning activities.
MID:
- All fine at MID.
HED:
- All good at HED.
SCS:
- Not using the shift today - done with X-ray commissioning and prioritizing the laser work.
- Changing number of pulses seemed to affect FXE for a second or so. Agreed to inform FXE when wanted to change pulses.
- XGM position was behaving weirdly. Drifts of the beam in the horizontal was seem by order of 1mm.
SQS:
- Nothing to report.
SXP:
- Will use the beam today instead of SCS. |
149
|
05 Aug 2020, 09:02 |
Andreas Galler | General | Information | Notes XO Integration Meeting 05.08.2020 |
General Announcement:
CTRL:
- SA3 vac loop
- devices lose connection to the PLCs every now and then (every few days)
- karabo fix for small movement error on MC2 motors
- for the tunnel topics CTRL suggests to do that Thursday morning
- InfluxDB
DA:
- no issues
- upcoming commissioning
- da infrastructure up and ready
EEE:
- cw36, cable installations require
VAC:
- no issues, normal activities
XPD:
DET:
ITDM:
- continuing with Monday tasks
XRO:
LAS:
- increas priotity on karabo integration for lasermet interlock
- SH: for SA1 and SA2 much of the interlock data is
UNSYS:
- today ZZ --> cell 33 should be fixed today as well as cell1
SPB:
- nothing outstanding
- DAQ testing
- VAC intervention
FXE:
- FXE and XRO is switching off M3 cooling
- no update on the digitizer issue
MID:
HED:
- MC2 motor timeout problem, karabo fix seems to work
- there are other time out errors that ar not addressed by this
- SH: suggests a zoom session for demonstration of these
- TP: e.g. stop button gives time
SCS:
- no issues
- installation of girder
- bestec is working on hRIXS
- recommissioning of Mono
SQS:
- laser interlock issue
- Lasermet is visiting today
|