Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 537     Entry time: 07 Aug 2024, 09:38
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 07.08.2024 
General Announcement:
- A. Galler informs to SQS that the vertical polarization operation is planned for Thursday starting tuning in the afternoon 15:00. Please SQS inform BKR if tuning can start earlier.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- SA2 and SA3 with normal operating parameters.
- SA1 get extra time to work today from SPB/SFX.

UNSYS:
- Nothing to report.

SPB:
- Nothing to report.

FXE:
- Not present.

MID:
- Nothing to report; HXRSS is planned for this week. 

HED:
- Not present.

SCS:
- Yesterday and Monday problems with Interlocks but were fixed.

SQS:
- Nothing to report.

SXP:
- Nothing to report; it was useful to use the beam on Monday.