Group Selection Page HELP Controls Group ITDM Vacuum WP78 SPB SQS XO ToBeMigrated2XWiki ToBeMigrated2GitlabPages ToBeMigratedByGroup Migrated2Zulip Archived2PDF not2MigrateOrArchive
SCS SXP Migrated2Zulip Photon Commissioning Team XRO DOC HED Migrated2Zulip WP74 MID PSPO_XO XO_Operation SQS Migrated2Zulip FXE Migrated2Zulip DET Sample Environment SPB Migrated2Zulip
SASE1 Status and SASE3 Readiness Technical integration and coordination
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 537     Entry time: 07 Aug 2024, 09:38
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 07.08.2024 
General Announcement:
- A. Galler informs to SQS that the vertical polarization operation is planned for Thursday starting tuning in the afternoon 15:00. Please SQS inform BKR if tuning can start earlier.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- SA2 and SA3 with normal operating parameters.
- SA1 get extra time to work today from SPB/SFX.

UNSYS:
- Nothing to report.

SPB:
- Nothing to report.

FXE:
- Not present.

MID:
- Nothing to report; HXRSS is planned for this week. 

HED:
- Not present.

SCS:
- Yesterday and Monday problems with Interlocks but were fixed.

SQS:
- Nothing to report.

SXP:
- Nothing to report; it was useful to use the beam on Monday.
ELOG V3.1.4-7c3fd00