SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 602
Entry time: 07 Apr 2025, 09:42
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 07.04.2025 |
|
|
General Announcement:
- Reminder from A. Galler: please use the Operations e-log to report issues or comments instruments may have.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- P. Gessler informs in activity organized by Desy: 10Hz synchronization signal has to be synchronized to the 50Hz of the power work.
A measurement campaign will happen on 17.June without the sync with the 50Hz. There is the possibility to run this day for tests.
A meeting on 06.June will take place; please contact Patrick Gessler to be included in the preparation meeting.
It does not affect normal users and is intended to evaluate possible drifts.
VAC:
- Having a group retreat.
XPD:
- Nothing to report.
DET:
- Nothing to report. Jola S.-D. will discuss with Patrick G. on the 50Hz sync tests.
ITDM:
- Nothing to report.
XRO:
- Nothing major to report.
LAS:
- Various issues with 1. interlock failing; 2. reset timing; 3. water leakage at sub-sync hutch.
UNSYS:
- Everything is fine.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- All fine at MID.
HED:
- Lbsync was down over the weekend.
- Bucket jumps on the PP-laser: needs to be readjusted delay time between PP-laser and FEL. Daniel K. says a call to OCD will help to set it up. Probably due to Lbsync issues.
SCS:
- Not available.
SQS:
- Not present.
SXP:
- Preparing the experiment for this week. |