17 Jan 2022, 10:41 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 17.01.2022 |
General Announcement:
- SEPS interlock tests are scheduled for this Friday January 21st; Zunaira A. needs XTD6 closed by the SEPS interlock at 09:00.
Martin D. will evaluate if it is possible to close XTD6 before Friday pending to finish the work (without closed vacuum we won't have beam in future).
- Machine is tuning SA1 and SA3 this week and XTD2/4 tunnels are opening today and tomorrow for finishing Apple-X works.
CTRL:
- Nothing to report.
DA:
- Preparing for start of operation; nothing out of ordinary.
EEE:
- Nothing to report.
VAC:
- Vacuum all is fine.
- Tunnels closures: XTD9 tomorrow afternoon; XTD6 on Friday or Thursday afternoon (see general announcement).
XPD:
- Camera library tests/migration together with CTRL (Aravis library) from today afternoon. Some cameras won't work for the update (5mins or bit more).
Plan is to do all cameras - please keep in touch with A. Koch if cameras are needed.
DET:
- Nothing major to report: preparing detectors for start of the run.
ITDM:
- Reminder on the storage system (offline side) update on 19.01: dcache won't be available for the whole day; connection between online and offline won't work also. An e-mail will be sent when activity I
done.
XRO:
- Next week it starts the photon beamline alignment. Next Friday one needs the SCS or SQS hutch interlocked over the weekend.
LAS:
- Nothing to report.
UNSYS:
- Issue with phase shifter in SA2: BKR forgot to use the right operation mode.
- Apple-X: waiting to enter tunnel today at 12:00 to install air coils and finalize hardware commissioning.
SPB:
- Controller was affected by power glitch; fix ongoing.
FXE:
- Interlock system problem was detected and under fix.
MID:
- All fine at MID.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Nothing to report. |
574
|
16 Dec 2024, 09:44 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 16.12.2024 |
General Announcement:
- Next Wednesday it is the last XO Integration Meeting.
CTRL:
- Proceeding with Karabo update accordingly to the schedule.
DA:
- Nothing to report.
EEE:
- Issue with PLCs: on Friday the SA3 GATT Loop had issue; not fixed until now and loop will be brought back as soon as possible. Working is ongoing.
VAC:
- Nothing to report.
XPD:
- Proceeding with:
PES repair (today afternoon goes back to tunnel);
SA1 XFELO photon diode and grating was installed (electronics ADC card in the uTCA crate was not found in the crate and EEE was contacted – P. Gessler says a normal card will be installed in the coming
days).
DET:
- Nothing to report; tests to be performed after Karabo updates.
ITDM:
- SA1 control network switches updates were done (two switches not yet operational but Desy experts are working on it).
XRO:
- Progressing well with maintenance activities.
- Note to CTRL: today Karabo update in SA1, tomorrow in SA2 and Wednesday in SA3; Also EEE makes an update today in SA3.
LAS:
- Not present.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
- LPD burned cable and plugs: new connectors were ordered and will be replaced.
MID:
- All fine.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Not present.
SXP:
- Not present. |
187
|
16 Dec 2020, 09:11 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 16.12.2020 |
General Announcement:
- Today is the last xo-integration meeting for this year. Xo wants to thank everyone for the participating in this meeting series while sharing information and giving updates.
- The next XO Int. Meeting will happen on 04 January.
CTRL:
- Beckhoff MC2 motor upgrades at SA3 is ongoing.
DA:
- no updates
EEE:
- all SA2 fast ADC tasks have been concluded.
- Cabling in HED is ongoing; On MID will happen next year.
- AIBS control at SA1 balcony room installation starts today.
- Testing Mc2 motor configurations in tunnel devices.
VAC:
- Trying to finish main shutdown tasks: GATT, new mirror chamber in SA3/SXP, SA2 M3 mirror chamber.
- M3 chamber InGa is clean and ready to be pumped down.
- XGM/SA1: broken gate will be replaced this week or next.
- Some members of VAC group are working on site next week.
XPD:
- XGM SA2/XTD6 was moved 4mm and is still in alignment (no damage found) -> Jan G and Harald S. will have a look today onsite. M. Dommach says the differential pump could not move that far away due to bellows.
- Installing of switches for HRIX will be most likely finished this month and some maybe in January.
DET:
- nothing to report.
ITDM:
- nothing today.
XRO:
- Not present.
LAS:
- Laser Hutches are locked (no access allowed) by Safety and LAS members can not continue the work in laser rooms. LAS maintenance tasks can not be finished and may be delayed over the end of shutdown.
- Emission of SASE2 Seeder laser was put in OFF yesterday due to inspection by SLSO. This means laser was OFF and there is no guarantee the PP-laser will be available in February, as they will not start mode-locking again after an Emission OFF.
- Typically the Seeder lifetime is 3-4 years. Each time it is switched OFF it shortens the lifetime by half. If Seeder is included in the Interlock system, and taking into account the interlock trips 1 time per week or month (case of SASE3), the availability of PP-lasers is in risk and consequently the whole operation for instruments.
- Alignment lasers will be no longer provided. This also relates to the safety decision - such lasers are not allowed to be operated.
UNSYS:
- not present.
SPB:
- nothing to report: quiet days.
FXE:
- Craning activities over the hutches due to SXP construction still ongoing: not always a notice from construction workers.
MID:
- all fine.
HED:
- nothing to report.
SCS:
- not present.
SQS:
- nothing to report |
374
|
16 Nov 2022, 10:58 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 16.11.2022 |
General Announcement:
- With the winter maintenance period coming in two weeks, XO kindly reminds you to check the access rights for tunnels at the DACHS/DARF system. Please also remind your respective groups' colleagues.
- Steffen H. presents a summary for the ramp down plan of PLCs and Karabo relative to the Saturday's Electrical activity of Dec. 3rd.
Please note that Karabo or PLCs based controls will not be available from Friday 11:00 up to Monday mid-day. XO will prepare an e-mail clarifying this information.
CTRL:
- Nothing to report.
DA:
- Concerning skipping of calibration: an e-mail with procedures was sent and is available at Alfresco. Instruments can look at it.
EEE:
- Nothing to report.
VAC:
- All running fine.
XPD:
- Nothing to report.
DET:
- On last weekend: SPB/SFX documented at the e-log an incident of AGIPD detectors with modules replaced last Summer Maintenance. Three out of 4 modules are compromised.
Steve A. said he was charged to propose a solution to be discussed with R. Bean.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- AMPHOS SA1 switched OFF this morning and investigation is ongoing to find reason. Beam is back on the table and will be available to FXE in few hours.
UNSYS:
- Nothing to report.
SPB:
- Nothing major to report.
FXE:
- Problems with beam with lower intensity than expected: XO informs that tuning for the North Branch happened yesterday late afternoon and performance was improved.
- Problem with PP-laser.
MID:
- All fine.
HED:
- Problems with uTCA crates with cards that do not show signal. Being addressed.
SCS:
- Nothing to report.
SQS:
- Nothing to report. |
178
|
16 Nov 2020, 13:14 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 16.11.2020 |
General Announcement:
-
CTRL:
- Further improvements on the SA3 vacuum loop will continue during the shutdown.
DA:
- No issues to report.
EEE:
- 1 OCD call from SCS call related to PLC: hardware issue.
- Fast electronics side: MID timing system problem is still present. Frequency that this issue happens is reduced.
- For the Winter maintenance, EEE will ship some crates to Poland. Due to Covid-19 situation, only crates with non-critical changes for next run will be sent. EEE is in
closed contacts with instruments.
VAC:
- 1 OCD during the weekend was related to GATT and promptly solved.
XPD:
- Nothing to report.
DET:
- Last Friday problem with offline jobs was solved (it had to be followed by IT).
- SPB activity for AGIPD baseline intervention/correction to start today.
ITDM:
- Maintenance on the offline storage will happen next Monday 23.11. An e-mail was sent this morning. The system will be OFF and all data will not be accessible that day.
- ITDM will also start the maintenance of online cluster on 23.11. They will not be available until the end of maintenance (about 3 days).
XRO:
- Nothing to report.
LAS:
- OCD calls from SCS: 1. observed crystal degradation in SCS side; 2. laser pattern server could not be changed (LAS forward the message to CTRL).
- All other PP-lasers are fine.
UNSYS:
- BKR tested air coils in the last SA2 undulators cells for performing work on Wednesday for photon beam alignment (there was a problem with Cell37/SA2 not responding).
SPB:
- Instrument and beam delivery were running successfully last week;
- This week SPB starts working with AGIPD: one aim to work as fast as possible to finish before Christmas break.
FXE:
- D3 is currently preparing the tests.
MID:
- Continues to use beam this week for detector tests.
HED:
- Tested AGIPD during last weekend. Currently HED is changing setup to use High Intensity laser this week.
SCS:
- Not present.
SQS:
- Nothing to report. |
557
|
16 Oct 2024, 09:57 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 16.10.2024 |
General Announcement:
- Reminder that Nov. 1st is the deadline for submitting the Winter Maintenance task list to XO.
- As PRC, Maurizio Vannoni says no issues are currently happening.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- VAC OCD got a call from SQS related to the GATT: interlock is on the limit of reaction at higher operational pressure. Under adjustment.
XPD:
- Yesterday problem with HIREX SA2 Gotthard shutter which did not closed completely: HIREX can still be operated and issue is under investigation.
DET:
- Issue with AGIPD at MID seems to have a hardware problem that will require intervention during the winter maintenance. Still under investigation to make a final plan for repair.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Nothing to report.
UNSYS:
- Apple-X studies during the blue week: problem with PS in cell26 showing strange behavior with limit switches always activated. A ZZ access is needed.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- Nothing to report in addition to the detector.
HED:
- Nothing to report.
SCS:
- Not present.
SQS:
- Not present.
SXP:
- KB commissioning last days: it had a hardware problem and machine was at times not stable but good process was achieved. |
460
|
16 Oct 2023, 09:46 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 16.10.2023 |
General Announcement:
- Last X-ray delivery week went normal.
- Friendly reminder for the submission of the maintenance task list on 20.10, next Friday. In case of questions please do not hesitate in contacting XO.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- ZZ on XTD2 today at 13:00 to exchange XGMD amplifiers.
DET:
- Investigating the settings of detector with FXE.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- SA3 AMPHOS engineer is at XFEL today. Intense work will be made to have PP-laser back by the end of the week - to be seen in coming hours/days.
- In SA1 PP-laser was recovered on Friday.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- Nothing to report.
- Naresh K. will interact with MID to align Hirex for the HXRSS operation this week.
HED:
- Nothing to report.
SCS:
- Needs PP-laser for the beamtime starting on THU.
SQS:
- SQS broke interlock at 6AM and took away beam permission.
SXP:
- Takes beam tomorrow and Wednesday; it will use another laser if SA3 PP-laser is not available. |
548
|
16 Sep 2024, 10:03 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 16.09.2024 |
General Announcement:
- As PRC, Maurizio V. reports some calls over the weekend mostly for exchange of info on minor issues that were addressed
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Reported issue with PP-laser: P. Gessler talked to Desy and LAS, and together with Bruno found the delayed train and is under investigation.
No guarantee it can't happen again, but it may be a one-time event. Under investigation for reason behind.
VAC:
- Nothing to report.
XPD:
- Nothing to report;
DET:
- Nothing to report.
- Marcin S. asks on a problem with MID problem getting correct gain previous; data disappeared then recovered;
- It is not a detector it self issue; Philip S. looked this morning; DAQ being loaded and could be the cause with this particular aggregator. Ticket has been issued; aggregator was working at 8AM.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Not present.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Not present.
SXP:
- Not present. |
161
|
16 Sep 2020, 10:20 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 16.09.2020 |
General Announcement:
- Yesterday evening a ZZ in XTD10 was planned but it turned unsuccessful due to no access in the turnstiles. D3 solve the problem in the middle of the night and since
then ZZ is possible again.
- Eric Boyd mention on the SQS shutter: a XTD10 ZZ was planned for 8:30AM. He has currently no news so far.
CTRL:
- XGM Pulse pattern decoder issue is under investigation.
- Vacuum issues (giving unknown state in Karabo): also under investigation.
- Next Monday CTRL plans to update Karabo login system. Groups shall inform CTRL if there is any issue against this.
- Last Influx training will be next Friday An e-mail to participants will be sent.
DA:
- No issues to be reported.
EEE:
- SA1/ Solid Attenuator Interlock problems: EEE is investigating and news will follow. FXE found an issue within the motion loop last night and XRO also helps.
It is the Interlock on the attenuator itself and not in the EPS.
VAC:
- Nothing to report.
XPD:
- XGM signals were monitored when SA1 went to 5keV for a short time yesterday night. No issues were observed.
DET:
- SCS made an OCD call on the DSSC which has been fixed.
- Agipd issue: under investigation together with ITDM (a ticket was opened to ITDM). This is not a calibration issue.
ITDM:
- ITDM will follow on the Maxwell issue with Agipd.
- CTRL and ITDM working and progressing on the bunch patter issue.
XRO:
- Issue with SA1 solid attenuator: same behavior can be expected also in SA2.
- Mirror inspection in XTD2: it shows no big damage on it. A full service will be made later. Next Monday inspection on XTD10 mirror to understand situation.
- Meeting to investigate possible upgrades to drive motors faster will take place. Participation of CTRL, DA and instruments.
LAS:
- Nothing to report.
UNSYS:
- Suren K. informs Beckhoff Hardware for cell#31/SA2 was received and is under test. As soon UNSYS is ready for a ZZ it will inform PRCs for scheduling a date.
Mostly likely ZZs will occur on Tuesday and not Monday due to continuation of 11.5 GeV studies.
- Communication problem with one undulator on Monday was quickly fixed.
SPB:
- Working on nano KB mirrors.
- 5 keV last night: gives right trajectory. It looks like the beam performance was sufficient for SPB alignment. Fine tuning has to come.
FXE:
- Affected by the shutter problem during the tentative ZZ access yesterday.
- Solid Attenuator issue in discussion with EEE.
- Sampling rate of ADC has changed. Peter Z. contacted EEE and it has been accessed.
MID:
- Not present.
HED:
- User experiment ongoing.
- Some stages worked intermittently and has to be investigated (related to crystal alignments).
- Pulse picker is not behaving correctly. It may be a Hardware issue and has to be investigated. Then HED will communicate to EEE.
SCS:
- PP laser was down last night and the OCD was contacted. There is the suspicion the crystal is damaged and the OCD informed it will be fixed this morning.
Daniel Kane will try to get some info inside LAS and report back t SCS.
SQS:
- It has users this week and shutter becomes a serious issue. In Karabo the shutter state changed but it is disconnected. It is not clear if the ZZ team is progressing
right now.
- Problem is that when trying to close the shutter via JDDD interface it went to an intermediate state but shutter did not close.
This cause interlock not opening the hutch and the beam could not be sent to the hutch. No beam since 5PM yesterday. Also locally operated in the panel it does not work.
The JDDD interface worked nicely the whole last week. Eric Boyd asks if problem appeared at the first operation. Tommaso M. says they did a lot of times prior having this
issue.
- Waiting for updates from CTRL mentioned. |
444
|
16 Aug 2023, 09:24 |
Andreas Galler | General | Information | Notes XO Integration Meeting 16.08.2023 |
General Announcement:
CTRL:
DA:
EEE:
VAC:
XPD:
DET:
ITDM:
XRO:
LAS:
UNSYS:
SPB/SFX:
- Issue with Hexapod of sample changer.
FXE:
- not present;
- frequent error with PPODL, locked station --> investigated by CTRL (wajid)
MID:
- Julabo chiller
- switching off recurrenlty
HED:
SCS:
SQS:
SXP:
DRC
PRC
|
251
|
16 Aug 2021, 10:07 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 16.08.2021 |
General Announcement:
- On frequent power glitches: it happened twice over the weekend. Machine was not affected and maybe this time the PP-lasers also. The origin is on the electrical power grid of Vatenfall and it is unclear
how long it takes to fix it.
- TS requires location knowledge of all office chairs. In case you have taken yours to home, please let TS know.
CTRL:
- Reports from DOC with delayed train of DOOCS XGM for HED. It will be investigated.
- Reminder that it is a blue week and the DOC does not run. The DRC is available via phone.
DA:
- Issues with the offline calibration system: changes of data migration (how it works). Hot fixes are ready to be deployed (probably today); please check the migration and the auto-run; DA will update
after the deployment.
EEE:
- Nothing to report.
VAC:
- No problems with power glitches.
XPD:
- XPD side: all fine.
- As PRC, Jan G. says that pump-probe laser at FXE was affected on Friday morning (Laser unavailable until the night). On Saturday and Sunday the lasers were not affected due to the power glitches.
DET:
- Nothing to report.
ITDM:
- Gitlab update taking place this week.
XRO:
- Not present.
LAS:
- None of the PP-lasers went down this weekend in relation to the power glitches.
UNSYS:
- Nothing to report.
SPB:
- Adrian M. asks that, in case supply problems continue to happen, would that mean EuXFEL makes proactive action for operations?
A. Galler comments that DOB will discuss the issue with lasers (exchange of pumps that are vulnerable to the power glitches is planned for the winter shutdown). From machine side, as it is largely
unaffected, the operations calendar won't change.
FXE:
- Nothing to add, no news on clock and control upgrade.
MID:
- All fine at MID.
HED:
- Not present.
SCS:
- Nothing to report.
SQS:
- Dismount the DSSC and give back to SCS this week.
- SQS expect beam for the safety tests on Wednesday and Thursday. |
629
|
16 Jul 2025, 09:51 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 16.07.2025 |
General Announcement:
- Martin Doering informs on the LIMP-25 on cw30:
1. On PLCs only the GATT will have an update next week;
2. Ramp-up phase will start next week with tunnel racks, balcony rooms and Lasers;
3. XHQ rack room doors will remain open next week - please do not enter rooms;
4. SA2 HXS electrical work will finish this week;
5. XHEXP1 UPS extension work is postponed and will not happen on 22-23.07. Once new date is available it will be communicated;
6. Electrical work in XHQ: lab areas (level 0) being affected until 21.07;
7. Electrical work on the XHQ offices of level 1 starts on 22.07 until 25.07;
8. XHQ level 2 office areas are affected with electrical work from 29.07 to 01.08.
- Martin Doering updates on the cw29 (current week):
1. Today from 10AM to 11:30 craning activities are planned for HXS area; Electrical maintenance in E0/lab area are also affected on Thursday in the same way as today.
- Michael Prollius informs on the fire safety for SA2 experimental area: the smoke detection system is currently OFF due to the electrical work being done.
CTRL:
- Nothing to report; Karabo to be ramped up next week from 22.07 to 25.07.
DA:
- Nothing to report.
EEE:
- Nothing major; temperatures of SA1 balcony rooms raised more than other areas - to be monitored to see if PLCs shall also be switched off.
VAC:
- Not present.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- Balcony rooms being monitoring temperatures.
- Doors to the rooms are opened and there is a trend of slow raise of temperature ongoing and flow of air from the Hall to be improved with fans.
XRO:
- Nothing to report; activities are progressing as planned;
LAS:
- Progressing with tasks.
UNSYS:
- Nothing to be reported.
SPB:
- Nothing to report, all good.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Ongoing work depends on the return of electricity.
SCS:
- Emergency OFF tests were delayed and Tobias C. informed it will happen today.
SQS:
- Nothing to report.
SXP:
- Not present. |
620
|
16 Jun 2025, 09:41 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 16.06.2025 |
General Announcement:
- A. Galler says a second Cryo issue happened on Saturday but it was possible to recovered by 18:00.
- LIMP-25 is about to start in one week. In case of questions please do not hesitate in contacting Martin Doering and XO.
CTRL:
- New broker version is ready to be installed to cure issues saw in SA2 recently.
DA:
- Nothing major to report from DA.
EEE:
- Issues on Saturday morning (during beam downtime) with PLCs in SCS to be restarted, affecting local vacuum interlocks.
- Camera issue also appeared at SCS but CTRL was working on it.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Everything is fine.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Quiet week but SA3 PP-laser had not enough triggers. Tests with EEE were done and will be discussed with Desy.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
FXE:
- Nothing to report; beam stability seems to be fine by now.
MID:
- All fine at MID.
HED:
- Not present.
SCS:
- Vacuum loop problem seems to be resolved.
SQS:
- Nothing to report.
SXP:
- Not present. |
234
|
16 Jun 2021, 08:37 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 16.06.2021 |
General Announcement:
- Interlock test next 2 weeks starting on monday - from next wednesday the photon tunnels will be closed; Tests are the XHEXP1 take place on 30.06, 01.07 and 02.07 with the last date as reserve; An email is going to be send by FWF to the xo-info@xfel.eu list.
CTRL:
- List of items to be sent to readiness: 1. problems with lima based cameras (Lima library does not work – needs to be updated: instruments contacts shall get in touch); 2. In SA1 there is legacy Undulator Karabo scenes – vector properties have to be adapted; 3. Counter Clocking motor devices upgraded next week.
- A. Koch asks if SA1 was working this morning. Steffen H. says there were updates but must be running now.
DA:
- Next wednesday will be the Offline calibration update deployment
EEE:
- Shutdown activities going well; "Wille" is short in people but scheduling adjustments with FXE and MID is organized.
- If there are short circuits or mal functions in the Beckhoff crates and current is not high enough to trigger the fuse it may be a fire risk. Solution is developed without impact in firmware, just a replacement of fuses. EEE starts today at SPB the changes; Based on this experience a plan will be made for the other systems and EEE will get in touch with groups.
VAC:
- try to get the works finished in the tunnels
- waiting for the Beckhoff crate works
XPD:
- Most of the tunnels works have been done; others are ongoing; No surprises are expected.
- MKK logbook from Desy reporting about electrical issue. XO will check. (XO update at 13:30: automatic mailing system is being commissioned and under testig; no power failure happened at the time).
DET:
- Work with DSSC in SQS going as planned.
ITDM:
- Work currently being done at FXE.
- Reminder of Friday afternoon gateway update.
XRO:
- Not present.
LAS:
- Nothing special to report.
UNSYS:
- Greasing the linear stages for undulators but not in SA2 (missing grease).
- SA1/SA2 after middle plane alignment UNSYS redefined the minimum gap and will be communicated through XO.
- Cell#36/SA2 there is a cable disconnected that need to be fixed.
- SA1/SA2 working with PS tables for extending operating tables for higher photon energies.
SPB:
- Work with EEE changing all the crates (Beckhoff)
FXE:
- Nothing to add
MID:
- Several ongoing infrastructure works are going fine.
- Worried with Beckhoff fuses (reported two years ago by Konstantin). It will be good to hear experience with SPB.
HED:
- Nothing to add
SCS:
- Nothing to add
SQS:
- Nothing to add |
325
|
16 May 2022, 09:53 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 16.05.2022 |
General Announcement:
- Another cryo failure happened yesterday night due to an overpressure. Expected cryo OK shall be around 10AM. Plan to tune today holds.
- Steffen H. reminds that instruments shall participate in the Jour-fixe today at 13:00.
CTRL:
- Nothing to report.
DA:
- Announcement from the calibration team: offline calibration will have a deploy today – minor intervention – to correct e.g. bug fixes
EEE:
- SA3 PPL has a card that behaves not normally. Needs an access and is been repaired right now.
- Pouhneh S. says that Saturday reason maybe be related to laser interlock. The whole SA3 went down. Lasermet was onsite and a wire was shorted circuit. Needs to look closely if it was interlock .
It acted as if the emergency OFF was pressed. Zunaira A. says that this happened also in SA2 time ago: AMPHOS shutter has a sub-D connector and when this connects the fuse blows and power went down; LAS
and Klaus Witt solved at the time and reason shall be related to the AMPHOS shutter.
K. Wrona says as DRC he has got a call informing the power glitch. This morning the network switches in the room are still not functioning. Please call DRC using DOC number when power goes down.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
- On the power glitch of SA3: only SQS and SCS hutch devices were affected by the power glitch due to the short circuit on the interlock/PPL.
- Switch to the 18keV in SA2 went smooth on Saturday.
DET:
- AGIPD in SPB showed radiation damage. On May 7th the detector was exposed to high radiation and investigation still ongoing.
About 10% of pixels are damaged and need full characterization to find if still usable for users.
ITDM:
- Nothing to report.
XRO:
- Last week on Friday: moved Mirrors M1 and M2 of SA2. Mirror positions seem to be in the right positions.
When beam is handled over to MID the XRO group has to check alignment and it is already agreed with MID. Currently beam is in the Platinum stripe.
LAS:
- Power outage in SA3: seeder is back but interlock does not allow seeder shutter open (card to be changed). Many troubles with devices in the network.
UNSYS:
- ZZ for SA2/cell#2 to fix a problem.
SPB:
- Interesting program last week with stability investigation and beam usage on the weekend.
FXE:
- Got support from Data calibration: thanks!
MID:
- All fine at MID.
- Ulrike B. comments on the Karabo broker pile up over Easter: noticed now that there is a mismatch between what is written and triggered.
Wajid E. says that will contact offline to MID to further understand. It is corrected as of now. Bruno F. says that there is a ticket ongoing (wrong timer connection affecting the configuration location).
HED:
- Nothing to report.
- Long pulse train tests were successful and shall be used on cw22 - a meeting takes place with BKR today.
SCS:
- No full power outage in SCS hutch (beamline was checked and seem to be fine). XGM did not get interrupted.
SQS:
- Suffer from laser interlock during the weekend – could not take PP laser. Got a damaged scroll pump. |
301
|
16 Feb 2022, 10:42 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 16.02.2022 |
General Announcement:
- XO launched a new XO Alfresco presence. Please check there for information related to operations and do not hesitate in giving suggestions or raising questions.
Adam R. asks for the schedule for the PRCs and DRCs. A. Galler says that the PRCs are included in the photon delivery tables. A discussion with Olivier M. on the DRC will take place.
Naresh K. asks on the status display: it is current a screenshot for the moment the page is loaded. It is not yet a live display.
- A. Galler reminds instruments to make entries to the Operations-2022 E-log to help the PRCs to track down and spot problems.
CTRL:
- Intervention on Monday GATT update: action to be done again next Monday to increase performance.
DA:
- Nothing to report.
EEE:
- Intervention on HED to replace a fast ADC card that lost communication to CPU. Replacement to take place today.
VAC:
- Nothing to report.
XPD:
- A. Koch reports that yesterday the Karabo fast-X was slow.
DET:
- Nothing to report.
- Olivier M. also observed slow fast-X connection to gateway.
ITDM:
- Janusz S. says the fast-X issues can be related to an overload yesterday.
- Login to Influx had intermittent connection for a half day yesterday n the afternoon. Investigation being taking place of it relates to fastX.
XRO:
- Nothing to report.
LAS:
- Issues with SA1 PP-laser: overshooting in the CM station. Maintenance this morning is taking place. Current timing is not as good as it could be.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- All fine at MID.
HED:
- Nothing to report apart of the ADC issue.
SCS:
- All fine at SCS.
SQS:
- SQS shutter issue from yesterday 15.02: problem was solved and it was due to a card misbehaving.
Zunaira A. says that the problem was with the Lasermet interlocks. Work done in the maintenance affected signals going to radiation protection interlocks. The particular signal was missing and after a fix
it worked again. |
386
|
16 Jan 2023, 09:54 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 16.01.2023 |
General Announcement:
- Tomorrow and Wednesday the 5Hz test take place; Wednesday as the pure 5Hz operation and on Wednesday there is the hybrid test. Every second pulse will not see any train.
CTRL:
- New version of Beckhoff Karabo device will be deployed today at 14:00; it shall take 5-10 mins.
DA:
- Nothing to report.
EEE:
- Continuing with remaining maintenance tasks and preparing the bring-up days with instruments.
VAC:
- Nothing to report. Tunnels XTD6 and XTD9 remain open until Wednesday.
XPD:
- Preparing for tunnel closure, stat-up and 5Hz tests.
DET:
- Gotthard1 detectors: need a firmware upgrade and will be coordinated with instruments.
ITDM:
- Announcement: on Friday exchange of SA1 devices.
XRO:
- All fine from XRO.
LAS:
- Working on the Lasers back-up; Lasers will be shut down for the 5Hz tests.
- Issue with Smaract stages being worked.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Nothing to report. |
287
|
15 Dec 2021, 10:26 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 15.12.2021 |
General Announcement:
- Severe power cut affected Schenefeld campus yesterday: it seems to be associated to human error but investigations are still ongoing. As soon as information will be available, it will be distributed via
e-mail either from TS or from XO.
- Regarding access regulations coming into effect Thursday evening (16.12): those who shared vaccination status with SRP will be able to enter via side gates or without showing vaccination certificates to
the gate keepers.
Without showing to SRP one can enter only via the main gate.
CTRL:
- Due to power cut some devices went to error state; a bunch reset helped to bring them up. If errors appear again please write tickets to CTRL.
DA:
- Nothing to report.
EEE:
- Issues with power cut: lost electronics in instruments; lost parts in tunnels (but recovered). Please check systems if they need to be reset.
- XGM in SA1 and SA3 were also affected.
- uTCAs are back and running after power cut.
- Work with cabling is ongoing accordingly to the maintenance planning.
VAC:
- PLC in rack room were affected and recovered with help from CTRL and EEE. So far nothing severe seems to be appeared but investigations still ongoing.
XPD:
- XGM is under investigation by Theo M.
- HIREX in SA1 has a motor not moving. Today on-site investigation will be done together with Bernard B,
DET:
- Nothing to report.
ITDM:
- Power cut: problems with office switches had to be rebooted/recovered. It got stuck during the reboot process causing problems that switches had to be manually power cycled (maybe due to a second short
power failure).
XRO:
- Nothing to report.
LAS:
- Affected by power cut; PLCs were off but running again after help from EEE.
- Seeder seems to do not suffer major issues.
UNSYS:
- Problems with electricity at XHU due to power outage were recovered later in the afternoon.
- Two Apple-X undulators were installed in SA3 yesterday.
SPB:
- Could recover the essential systems quickly enough; no big damages so far.
FXE:
- Working in tunnel this morning. Investigations related to the power outage ongoing.
MID:
- Issues were recovered with EEE.
HED:
- Could recover vacuum systems; Laser systems were turned OFF.
- SA2 gas alarm controller was damaged due to the power outage. So there is no operation with liquid nitrogen and other gases from now. TS need to discuss with HED as tasks must be performed by latest mid-
January (lasers and/or cryo activities).
SCS:
- Not present.
SQS:
- Damage in the air conditioning (electronic and physical) in room 509 due to the power outage. To be discussed between SQS and TS. |
469
|
15 Nov 2023, 09:48 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 15.11.2023 |
General Announcement:
- As PRC, A. Galler informs the machine runs without major issues but kicker adaptation has difficulties with 4.5MHz. For the next 20 mins machine colleagues will introduce stronger kickers and during
this time beam will be jittery at SA1/SA3. SA2 shall be unaffected.
During the meeting PRC received a call from BKR informing the intervention was done at 09:45 and stable beam is currently available.
- Martin Doering announces on the Winter Maintenance period:
1. The release of Maintenance Task List will happen tomorrow 16.11 and maintenance starts on 30.11;
2. Major topics:
Karabo (4-7.12 and 13.12),
DAQ and CTRL network interruptions (4-8.12),
Cooling water has no big interruptions planned apart of the regular maintenance with fluctuations in flow and temperature,
Electrical maintenance in XHQ (4-22.12) with rooms affected in different days,
electrical maintenance at XHEXP1 in 27.11-22.12,
Timing missing, smoke detector tests, laser interlock upgrades,
interlock test "light" (17.01);
3. Please check for precise dates on above at the Maintenance Task List.
CTRL:
- No announcements for CTRL.
DA:
- Nothing to report.
EEE:
- Nothing to mention.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Nothing for DET and for DRC (Monica T.).
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Nothing to report.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report apart of the Kicker issues.
FXE:
- Issues with Kicker as mentioned by the PRC.
MID:
- Nothing to report.
HED:
- Nothing to report. Tomorrow the switch to 24keV will take place and time has to be allocated for tuning.
SCS:
- Nothing to report.
SQS:
- Nothing to report.
SXP:
- Not present. |
648
|
15 Sep 2025, 09:45 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 15.09.2025 |
General Announcement:
- On the LIMP25, no news apart of what was mentioned last week by Martin Doering (see 10.09 minutes)
- Inaki de Diego informs that AIBS and airboxes installation is completed, with the exception of HED, where there is a problem with a cable (or connector) that needs to be
fixed by MPS during the next days.
It will be confirmed when fixed/done.
CTRL:
- Today proceed with test deployment at MID.
DA:
- Nothing to report.
EEE:
- PLC team starting to replace the PLC CPUs with SA1 after agreement with instruments.
VAC:
- Not present.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Not present.
UNSYS:
- All proceeding and the hardware is prepared; only waiting for construction/MEA work.
SPB:
- Nothing to report.
FXE:
- Thanks to Hall crew who helped with craning.
MID:
- All fine; Temperature in the control hutch to be addressed today.
HED:
- Not present.
SCS:
- Not present.
SQS:
- Nothing to report.
SXP:
- Nothing to report. |