General Announcement:
- Interlock test next 2 weeks starting on monday - from next wednesday the photon tunnels will be closed; Tests are the XHEXP1 take place on 30.06, 01.07 and 02.07 with the last date as reserve; An email is going to be send by FWF to the xo-info@xfel.eu list.
CTRL:
- List of items to be sent to readiness: 1. problems with lima based cameras (Lima library does not work – needs to be updated: instruments contacts shall get in touch); 2. In SA1 there is legacy Undulator Karabo scenes – vector properties have to be adapted; 3. Counter Clocking motor devices upgraded next week.
- A. Koch asks if SA1 was working this morning. Steffen H. says there were updates but must be running now.
DA:
- Next wednesday will be the Offline calibration update deployment
EEE:
- Shutdown activities going well; "Wille" is short in people but scheduling adjustments with FXE and MID is organized.
- If there are short circuits or mal functions in the Beckhoff crates and current is not high enough to trigger the fuse it may be a fire risk. Solution is developed without impact in firmware, just a replacement of fuses. EEE starts today at SPB the changes; Based on this experience a plan will be made for the other systems and EEE will get in touch with groups.
VAC:
- try to get the works finished in the tunnels
- waiting for the Beckhoff crate works
XPD:
- Most of the tunnels works have been done; others are ongoing; No surprises are expected.
- MKK logbook from Desy reporting about electrical issue. XO will check. (XO update at 13:30: automatic mailing system is being commissioned and under testig; no power failure happened at the time).
DET:
- Work with DSSC in SQS going as planned.
ITDM:
- Work currently being done at FXE.
- Reminder of Friday afternoon gateway update.
XRO:
- Not present.
LAS:
- Nothing special to report.
UNSYS:
- Greasing the linear stages for undulators but not in SA2 (missing grease).
- SA1/SA2 after middle plane alignment UNSYS redefined the minimum gap and will be communicated through XO.
- Cell#36/SA2 there is a cable disconnected that need to be fixed.
- SA1/SA2 working with PS tables for extending operating tables for higher photon energies.
SPB:
- Work with EEE changing all the crates (Beckhoff)
FXE:
- Nothing to add
MID:
- Several ongoing infrastructure works are going fine.
- Worried with Beckhoff fuses (reported two years ago by Konstantin). It will be good to hear experience with SPB.
HED:
- Nothing to add
SCS:
- Nothing to add
SQS:
- Nothing to add |