Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 178     Entry time: 16 Nov 2020, 13:14
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 16.11.2020 
General Announcement:
-	 

CTRL:
- Further improvements on the SA3 vacuum loop will continue during the shutdown.

DA:
- No issues to report.

EEE:
- 1 OCD call from SCS call related to PLC: hardware issue.
- Fast electronics side: MID timing system problem is still present. Frequency that this issue happens is reduced.
- For the Winter maintenance, EEE will ship some crates to Poland. Due to Covid-19 situation, only crates with non-critical changes for next run will be sent. EEE is in 
closed contacts with instruments.

VAC:
- 1 OCD during the weekend was related to GATT and promptly solved.

XPD:
- Nothing to report.

DET:
- Last Friday problem with offline jobs was solved (it had to be followed by IT).
- SPB activity for AGIPD baseline intervention/correction to start today.

ITDM: 
- Maintenance on the offline storage will happen next Monday 23.11. An e-mail was sent this morning. The system will be OFF and all data will not be accessible that day.
- ITDM will also start the maintenance of online cluster on 23.11. They will not be available until the end of maintenance (about 3 days).

XRO:
- Nothing to report.

LAS:
- OCD calls from SCS: 1. observed crystal degradation in SCS side; 2. laser pattern server could not be changed (LAS forward the message to CTRL).
- All other PP-lasers are fine.

UNSYS:
- BKR tested air coils in the last SA2 undulators cells for performing work on Wednesday for photon beam alignment (there was a problem with Cell37/SA2 not responding).

SPB:
- Instrument and beam delivery were running successfully last week;
- This week SPB starts working with AGIPD: one aim to work as fast as possible to finish before Christmas break.

FXE:
- D3 is currently preparing the tests.

MID:
- Continues to use beam this week for detector tests. 

HED:
- Tested AGIPD during last weekend. Currently HED is changing setup to use High Intensity laser this week.

SCS:
- Not present.

SQS:
- Nothing to report.