Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 574     Entry time: 16 Dec 2024, 09:44
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 16.12.2024 
General Announcement:
- Next Wednesday it is the last XO Integration Meeting.

CTRL:
- Proceeding with Karabo update accordingly to the schedule.

DA:
- Nothing to report.

EEE:
- Issue with PLCs: on Friday the SA3 GATT Loop had issue; not fixed until now and loop will be brought back as soon as possible. Working is ongoing.

VAC:
- Nothing to report.

XPD:
- Proceeding with: 
PES repair (today afternoon goes back to tunnel); 
SA1 XFELO photon diode and grating was installed (electronics ADC card in the uTCA crate was not found in the crate and EEE was contacted – P. Gessler says a normal card will be installed in the coming 
days).

DET:
- Nothing to report; tests to be performed after Karabo updates.

ITDM: 
- SA1 control network switches updates were done (two switches not yet operational but Desy experts are working on it).

XRO:
- Progressing well with maintenance activities.
- Note to CTRL: today Karabo update in SA1, tomorrow in SA2 and Wednesday in SA3; Also EEE makes an update today in SA3.

LAS:
- Not present.

UNSYS:
- Nothing to report.

SPB:
- Nothing to report.

FXE:
- Nothing to report.
- LPD burned cable and plugs: new connectors were ordered and will be replaced.

MID:
- All fine.

HED:
- Nothing to report.

SCS:
- Nothing to report.

SQS:
- Not present.

SXP:
- Not present.