SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 292
Entry time: 17 Jan 2022, 10:41
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 17.01.2022 |
|
|
General Announcement:
- SEPS interlock tests are scheduled for this Friday January 21st; Zunaira A. needs XTD6 closed by the SEPS interlock at 09:00.
Martin D. will evaluate if it is possible to close XTD6 before Friday pending to finish the work (without closed vacuum we won't have beam in future).
- Machine is tuning SA1 and SA3 this week and XTD2/4 tunnels are opening today and tomorrow for finishing Apple-X works.
CTRL:
- Nothing to report.
DA:
- Preparing for start of operation; nothing out of ordinary.
EEE:
- Nothing to report.
VAC:
- Vacuum all is fine.
- Tunnels closures: XTD9 tomorrow afternoon; XTD6 on Friday or Thursday afternoon (see general announcement).
XPD:
- Camera library tests/migration together with CTRL (Aravis library) from today afternoon. Some cameras won't work for the update (5mins or bit more).
Plan is to do all cameras - please keep in touch with A. Koch if cameras are needed.
DET:
- Nothing major to report: preparing detectors for start of the run.
ITDM:
- Reminder on the storage system (offline side) update on 19.01: dcache won't be available for the whole day; connection between online and offline won't work also. An e-mail will be sent when activity I
done.
XRO:
- Next week it starts the photon beamline alignment. Next Friday one needs the SCS or SQS hutch interlocked over the weekend.
LAS:
- Nothing to report.
UNSYS:
- Issue with phase shifter in SA2: BKR forgot to use the right operation mode.
- Apple-X: waiting to enter tunnel today at 12:00 to install air coils and finalize hardware commissioning.
SPB:
- Controller was affected by power glitch; fix ongoing.
FXE:
- Interlock system problem was detected and under fix.
MID:
- All fine at MID.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Nothing to report. |