Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 292     Entry time: 17 Jan 2022, 10:41
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 17.01.2022 
General Announcement:
- SEPS interlock tests are scheduled for this Friday January 21st; Zunaira A. needs XTD6 closed by the SEPS interlock at 09:00. 
Martin D. will evaluate if it is possible to close XTD6 before Friday pending to finish the work (without closed vacuum we won't have beam in future).
- Machine is tuning SA1 and SA3 this week and XTD2/4 tunnels are opening today and tomorrow for finishing Apple-X works.

CTRL:
- Nothing to report.

DA:
- Preparing for start of operation; nothing out of ordinary.

EEE:
- Nothing to report.

VAC:
- Vacuum all is fine.
- Tunnels closures: XTD9 tomorrow afternoon; XTD6 on Friday or Thursday afternoon (see general announcement).

XPD:

- Camera library tests/migration together with CTRL (Aravis library) from today afternoon. Some cameras won't work for the update (5mins or bit more). 
Plan is to do all cameras - please keep in touch with A. Koch if cameras are needed.

DET:
- Nothing major to report: preparing detectors for start of the run.

ITDM: 
- Reminder on the storage system (offline side) update on 19.01: dcache won't be available for the whole day; connection between online and offline won't work also. An e-mail will be sent when activity I 
done.

XRO:
- Next week it starts the photon beamline alignment. Next Friday one needs the SCS or SQS hutch interlocked over the weekend.

LAS:
- Nothing to report.

UNSYS:
- Issue with phase shifter in SA2: BKR forgot to use the right operation mode. 
- Apple-X: waiting to enter tunnel today at 12:00 to install air coils and finalize hardware commissioning.

SPB:
- Controller was affected by power glitch; fix ongoing.

FXE:
- Interlock system problem was detected and under fix.

MID:
- All fine at MID.

HED:
- Nothing to report.

SCS:
- Nothing to report.

SQS:
- Nothing to report.
ELOG V3.1.4-7c3fd00