Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 460     Entry time: 16 Oct 2023, 09:46
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 16.10.2023 
General Announcement:
- Last X-ray delivery week went normal. 
- Friendly reminder for the submission of the maintenance task list on 20.10, next Friday. In case of questions please do not hesitate in contacting XO.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- ZZ on XTD2 today at 13:00 to exchange XGMD amplifiers.

DET:
- Investigating the settings of detector with FXE.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- SA3 AMPHOS engineer is at XFEL today. Intense work will be made to have PP-laser back by the end of the week - to be seen in coming hours/days.
- In SA1 PP-laser was recovered on Friday.

UNSYS:
- Nothing to report.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Nothing to report.
- Naresh K. will interact with MID to align Hirex for the HXRSS operation this week.

HED:
- Nothing to report.

SCS:
- Needs PP-laser for the beamtime starting on THU.

SQS:
- SQS broke interlock at 6AM and took away beam permission.

SXP:
- Takes beam tomorrow and Wednesday; it will use another laser if SA3 PP-laser is not available.