Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 18 of 33  Not logged in ELOG logo
ID Date Author Location Severity Subjectdown
  260   15 Sep 2021, 10:37 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 15.09.2021
General Announcement:
- Machine stop running yesterday around 21:00 due to problems with the cold compression. A repair was done during the night but there are not yet stable conditions. It is unclear at what time today the 
machine will be back. 
By the other side, gun conditioning was done during the night which may help to have less gun trips.
- Steffen H. on behalf of DRCs reminds the instruments to please attend the jour-fix meeting on Mondays. 

CTRL:
- Beckhoff upgrade is set to take place next Tuesday 21.09 at 09:30 (during ZZ access). It relates to only Karabo devices with Mc2 motor loops; the PLC continues to run. 

DA:
- Nothing to report.

EEE:
- An update of SA2 motion loop to integrate the shutter / Gotthard is to take place next Tuesday 21.09 morning. Nerea J. will coordinate with CTRL (Valerii B.) and Naresh K. on the best time.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Reported last Monday that SA1 PP-laser was down due to air conditioning. In fact, it was a broker chiller that is repaired already Monday was a broker chiller. The PP-laser in SA1 is available since 
yesterday.

UNSYS:
- Nothing to report.

SPB:
- Change of setup happened yesterday. It will be ready for beam at 23:00 if possible.

FXE:
- Nothing to report; not yet clear if program will be affected due to the beam down.

MID:
- All fine at MID.

HED:
- Got beam yesterday morning and made use of it.
- Had issues with Interlocks (see operation-2021 e-log). A DACHS terminal stopped working and could not do hutch search. The Dachs terminal was replaced by Desy colleagues. 

SCS:
- Issue with the GATT mentioned last meeting: Jan-Torben D. has contacted XO (F. Wolff-Fabris). Discussions with further groups will take place.

SQS:
- Not present.
  349   15 Aug 2022, 09:49 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 15.08.2022
General Announcement:
-  On Saturday 4AM there was a very short power glitch. Machine kept running and to our best knowledge only the SA3 GATT had to be reset afterwards. 
If any group find any other affected device, please inform XO or the PRC.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Updates for SA1 PP-laser are coordinated with LAS.
- OCD call yesterday to replace motor on site (HED?).

VAC:
- Issue with GATT on Saturday early morning. It was resolved by SQS and VAC-OCD. Under investigation; it may be related to a drop of cooling water flow.

XPD:
- Nothing to report regarding XPD and PRC duties.

DET:
- Nothing to report.

ITDM: 
- Small issue related to Graphana but fixed on Saturday.

XRO:
- Nothing to report.

LAS:
- Nothing to report.

UNSYS:
- Small issue with PS cell33/SA2: fixed and working by now.

SPB:
- Nothing to report.

FXE:
- No info on the beam usage over the weekend.

MID:
- All fine.

HED:
- Used beam from Friday until Sunday 23:00.

SCS:
- Using TOPAS for laser: some instability was found and shall be checked today together with LAS.

SQS:
- No news from the user program.
  530   15 Jul 2024, 09:39 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 15.07.2024
General Announcement:
- The User Operation Meetings will restart next Friday 19.07.

CTRL:
- Proceeding with bring up days.

DA:
- Busy with bring up days.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Not present.
- As PRC, Raul Villanueva informs that activities in XTD6 are planned to be finished by tomorrow, Tuesday.

DET:
- HIREX / Gotthard-II inSA2: it is fixed and installation is ongoing.

ITDM: 
- Nothing to report; also involved in bring-up days.

XRO:
- An e-mail will be sent as preliminary tests will be done as preparation for SEPS tests next Monday. It is transparent to the machine.

LAS:
- Not present.

UNSYS:
- All good with undulators.

SPB:
- Nothing to report.

FXE:
- Nothing to add.

MID:
- All fine at MID.

HED:
- All fine at HED.

SCS:
- Today bring up days happening.

SQS:
- Nothing to report.

SXP:
- Not present.
  143   17 Jul 2020, 10:19 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 15.07.2020
General Announcement:
- SASE3 tuning will start this afternoon and possibly will last until Thursday afternoon. SCS and SQS will share the closures of their hutches.

CTRL:
- Swap server of one of the two Karabo GUI servers for SA1 (mail to readiness): suggestion is to do Friday 9-10AM. Please let CTRL know in case you have any issue.
- Status on INFLUX roll-out: testing to take place at the end of this week. A coordination with SA1 has to take place due to the running macros. 

DA:
- Not present.

EEE:
- EEE is working in FXE and HED with the open issues.
- EEE gives an update of the discussed points on Monday:
   Communication: From now on EEE will include the contact persons, as well as to the instrument mailing list.
   SA1 motors in OFF state: after a PLC update the safest configuration for re-start is bringing them back in OFF state. EEE will continue with this procedure. 
If instruments want differently, please make a list of devices that has to be changed.
   HED issue: EEE is talking with Konstantin and found it was just a misconfiguration.
   HED pump controller: Konstantin is already working together with VAC;
   XPD turbo pump in SA3: no relation with PLC update. Yesterday's ZZ showed that the pump has to be replaced.
- Nerea and Patrick will provide a write up to ensure the problems are followed up and solved.

VAC:
- ZZ yesterday to install the Neon gas minican to allow the monochromator calibration in SCS/cw31.
- Exchange of PES turbo pump will take one day and break the interlock - North brunch will see no electrons and photons. 
A date has to be found in agreement with involved groups and facility's operation.

XPD:
- Turbo pump in PES: pump itself is the problem. Vacuum beamline is safe but PES does not operate. We need the PES for some user experiments still in 2020. 
- Operation of beam in XTD6 was not possible with multi-bunch due to devices in the beam. We do not know if in reality they were in beam or not. 
Karen Appel confirms the devices were out of beam. This has to be followed up.
- This weekend, together with XRO, XPD will do the further recommissioning of beamlines and diagnostics. 

DET:
- Vacuum issue reported on last Monday was confirmed to be related to the gauge.
- Started with DAQ tests with instruments. All ongoing.

ITDM: 
- Not present.

XRO:
- Not present.

LAS:
- SA2 laser maintenance taking place on Friday.

UNSYS: 
- Nothing to report.

SPB:
- Preparations are going smoothly. All good in the SPB's plan.

FXE:
- DAQ test with LPD deployment - all work fines but for one module need to be fixed in the detector. It is already under care;
- EEE/Bernard is finishing the loops.
- Monochromator commissioning next days (we need a ZZ to align the camera).

MID:
- It is scheduled MID DAQ test for Monday next week.

HED:
- Ulf will investigate with Konstantin on the EEE issues. In XTD6 there were two motors with wrong parameters configurations. HED will communicate directly with Nerea.

SCS:
- EEE is needed to solve issue with the FFT end station.

SQS:
- Not present.
  333   15 Jun 2022, 10:40 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 15.06.2022
General Announcement:
- Currently beam delivery is suffering with gun trips at every 1 hour or so. The RCs and PRC are discussing measures to improve the situation. 
Last Monday gun conditioning did not had the desirable effect in the number of daily gun trips.

CTRL:
- Nothing to report.

DA:
- All fine.

EEE:
- Preparing for the shutdown.

VAC:
- Issue with vacuum signal at SA1 yesterday morning 04:00AM in SPB branch (controller was having faulty settings). The BKR did not call the VAC OCD or the PRC. After a ZZ this mal-function of ion pump was 
fixed.

XPD:
- Nothing to report.

DET:
- Maintenance of AGIPD 1M at SPB: modules were exchanged this week. Unfortunately, one new module is not yet working and needs further investigation.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Nothing to report.

UNSYS:
- Not present.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- All fine at MID; under HXRSS tuning and have observed frequent gun trips.

HED:
- Nothing to report.

SCS:
- Nothing to report.

SQS:
- Nothing to report.
  278   15 Nov 2021, 09:57 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 15.06.2021
General Announcement:
-	 

CTRL:
- Nothing to report.

DA:
- Interruption during the weekend on the automatic data processing: was disrupted on Saturday night (proposal that was finished and treated as same priority). A change of priorities had to take place for 
HED having the data analyzed.

EEE:
- Faulty sensor at ATD broker - EEE will take a look.

VAC:
- No issues to report.

XPD:
- Nothing to report for XPD.
- Jan G. reports the machine overall performance was quite good without major incidents. Several issues were reported on the Operation e-log concerning the calibration pipeline and DAQ.

DET:
- Nothing to report.

ITDM: 
- On the prioritization (refers to DA): major reorganization of priorities took place. This results in the fact jobs that are submitted to the partition, (many jobs for a current beamtime) are killed. 
If instrument has beamtime please request reservations for the proper amount of jobs.

XRO:
- Nothing to report.

LAS:
- Nothing to report.

UNSYS:
- Planned access to exchange motor of PS21/SA3 this morning.

SPB:
- AGIPD data issues were seen and is in contact to DET and DOC. Issue relates to memory modules not sending data from time to time. Jolanta S.-D. says it can happen for 1-2 modules a train may miss and the 
DAQ will discard the data. 
This is not unusual and one has to look at the frequency which happens - there is nothing wrong with Detector; data looks as usual. Further discussions will take place.

FXE:
- Nothing to report. User beamtime seems to have run well.

MID:
- Restriction of priorities: MID jobs went through. Experiment jobs have priority and for this week one has to put back in priorities.
- K. Wrona says a system will prioritize the user beamtimes for each week, getting out of the system automatically.

HED:
- Two user experiments using AGIPD went nicely but a bit stuck due to the priorities list (slow data processing).
- Beam instabilities occasionally: appearing and disappearing from time to time (maybe related to mirrors). It was reported to the stability task force. 
Harald Sinn mentions about a crosstalk between SA2 with SA3. This HED case will be further studied.

SCS:
- Nothing to report.

SQS:
- Nothing to report.
  132   16 Jun 2020, 13:32 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 15.06.2020
General Announcement:
- There will be additional ventilation maintenance on all tunnels, scheduled for next WED/17th and THU/18th between 06:30AM and 08:00AM. 
We request staff to do not enter in tunnels during this period.
- TS has sent information on the hutch crane maintenance starting today up to Wednesday 16th. Please make sure one instrument colleague is present.
- XTD4 will be closed on next FRI/19th as part of Interlock Tests (§88 - TUV Prufung).

CTRL:
- Few minor things were solved on Friday.
- Notification service worked as expected in SPB; VAC also got notification.
- CTRL will follow the uTCA updated after EEE is done today.
- CTRL is working on the PMO projects.

DA:
- Nothing to report.

EEE:
- Activities running well.
- Today afternoon migration plan for tunnel crates and tomorrow SA2.

VAC:
- Nothing to report.

XPD:
- Nothing to report. 
- XPD will check the uTCA crates after its update/restart.

DET:
- Data has been taken at SCS; also performing online tests.

ITDM: 
- Nothing major - Continuing updates with SQS, MID and HED instruments.

XRO:
- Nothing to report.

LAS:
- Scheduled SA2 maintenance on Tuesday. EEE firmware update also takes place. 
- Timing related updates on SA1 and SA3 are under discussion between the groups.

UNSYS:
- Everything is OK - All work in tunnels are done.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- Water leak from last week: TS has contacted the external company and a faulty air humidifier was the cause. It will be changed/fixed.

SCS:
- Not present.

SQS:
- Nothing to report.
  514   15 May 2024, 09:44 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 15.05.2024
General Announcement:
-	 

CTRL:
- Nothing to report.

DA:
- All fine from DA.

EEE:
- Nothing to report.

VAC:
- Not present.

XPD:
- All fine with diagnostics;
- First shift yesterday for studies with beam steering in SA1 and today the continuation.

DET:
- Nothing to report.

ITDM: 
- Reminder for the announcement on the network works on next Tuesday in the lab areas (see also sent e-mail). No strong objections were presented so far. Please contact urgently ITDM in case of questions.
- Room managers have to grant access to the workers during the Network maintenance.

XRO:
- Everything fine.
- Working today with Euler MDL.

LAS:
- On timing jumps and spectrum shifts for SA1 PP-laser reported last Monday: timing jumps under investigations by EEE (not happened since Monday); changes during the shifts under investigation.

UNSYS:
- All fine.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- All fine at MID.

HED:
- Nothing to report.

SCS:
- Not present.

SQS:
- Nothing to report.

SXP:
- Not present.
  418   15 May 2023, 09:51 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 15.05.2023
General Announcement:
- There are different infrastructures among the instruments regarding liquid nitrogen. An idea is to standardize the systems in future to avoid technical issues will be evaluated and put in place.
- There is no UOM on next Friday 19.05 due to the bridge holiday.

CTRL:
- HED Karabo slowness: CTRL is helping HED to better understand it and will be followed up today.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Issue with GATT in SA3: solved by PRC on the weekend and further investigations ongoing.

XPD:
- Today XPD is working at SPB to exchange parts of the calorimeter.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Not present.

LAS:
- SA1 AMPHOS intervention was completed successful.

UNSYS:
- SQS reported that undulator cells got stuck over the weekend for minutes during energy scans. They were reset by the BKR but after restarting servers by Unsys the problem was gone.
	
SPB:
- Difficulties to align mirrors during the weekend.

FXE:
- Preparing next beam time and so far, all under progress.
- FXE requested liquid nitrogen for preparation with user experiment.
- Access to the truck bay during the weekend was not possible for some people; XO informs an e-mail to A. Suleyman shall be send to address this matter.

MID:
- Nothing to report.

HED:
- Run last week was finished successfully.

SCS:
- Nothing to report.

SQS:
- Good commissioning and use of beam last week apart of the GATT issue.

SXP:
- Not present.
  121   15 May 2020, 14:35 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 15.05.2020
General Announcement:
- Judging by feedback and communication to XO both Tunnel and control network works are progressing.
- Friday is a good opportunity to discuss the Karabo tasks to be submitted next week as well as direct questions to SRP.
- The summer shutdown will have tunnels open for two weeks due to the interlock tests that, in turn, need tunnels closed. 
Current plan is photon beam will be available after the interlock tests.
- Due to next week's holiday bridge, the XO Integration meeting will not take place on Friday. 
- XTD1 will be closed next Monday and reopened for the summer shutdown. By its side, the XTD6 will remain open.

CTRL:
- DET confirms task list for this week has possible prolongation for next week on the AGIPB work. CTRL is aware and will prepare support for next week.
- Today a new Karabo version is released but general deployment will be made during summer shutdown (MID will do it earlier).

DA:
- Nothing to report.

EEE:
- A question arises on filling the dates for the summer shutdown task list. It does not need to be necessarily filled, unless if constraints are made. 
If a date is proposed, we shall stick to that day. Entanglement with other groups will be taking into account for a final scheduling. 
- Cabling installation going as planned: SQS cabling may be finished today and the FXE installation will follow. 
- EEE plans to start with change request of modules. For PLC control crates there may be delays. Subject will be communicated to the groups.

VAC:
- Tunnel tasks are progressing: upgrade of SA2 solid attenuator pneumatic system; SA3 pre-shutter is installed; preparing for SA3 re-alignment to start next week.

XPD:
- The planned activities are progressing well.
- Few activities originally planned for the summer shutdown are anticipated to the re-start phase. The summer shutdown task list will be updated accordingly. 
- Preparing for beam delivery in SA2: XPD is prepared for the XTD1 tunnel closure on Monday. The XGM of XTD1 will be available for operation from next Wednesday, 
as well as Imagers. It is expected to receive photon beam by May 23-25 (EEE is informed). 
- The photon delivery is only for XTD1 and beam dump. XTD6 will stay open until the shutdown.
- XPD will regularly use the big clean room from next week with 2 staff members (not continuously, but larger part of the time).

DET:
- Activities on DSSC, Jungfrau, AGIPB are ongoing without major issues.
- DET do not plan to work in the bog clean room, only eventually going there to pick small components. 

ITDM: 
- IT infrastructure is properly running.

XRO:
- Progressing with planned activities, e.g. magnetic limit switch for XTD6 mirror. 
- Preparing for cooling installation in XTD9 together with VAC. Work currently being prepared in the labs.

LAS:
- No problems that require attention: LAS is progressing - all under control.

SPB:
- Jungfrau has been installed and works well besides small issues with data transmission (staff and support are working on it).

FXE:
- Preparing things for cabling installation in hutches; Questions to SRP are clarified.
- In parallel FXE conducts activities with Jungfrau detector.
- Alignment of optical laser is postponed due to staff's sickness.

MID:
- The CRLs check in XTD1 was done and no more tunnel access is need. There were no changes on the CRLs. 
- MID access XTD6 next week and is busy with other re-starting tasks.

HED:
- Progressing with lasers and split delay line.
- Internal staff and Wille company pulled cables in A12.
- Detectors are under tests since yesterday.

SCS:
- Not present.

SQS:
- Activities in hutch proceeding smoothly.
- New spectrometer setup must be finished today.
- SQS plans to start with vacuum and to integrate the locally developed interlock system during next week. 
  605   16 Apr 2025, 09:33 Andreas GallerGeneralInformationNotes XO Integration Meeting 15.04.2025

General Announcement:

  •  

CTRL:

  • nothing 

DA:

  • nothing

EEE:

  • nothing

VAC:

  • everything fine

XPD:

  • nothing to discuss

DET:

  • DSSC2 commissioning hampered, SA3 undulator only manual controls available.

ITDM: 

  • 2 hours maintenance starting at 10:00 maxwell servers

XRO: 

  • nothing

LAS:

  • nothing

UNSYS: 

  • not present, working on recovering SA3 undulator controls

SPB/SFX:

  • nothing to discuss

FXE:

  • mono drift --> issue with encoder?
  • motor config issue, Leandro helped
  • stuch stage in sample stack 

MID:

  • karabo gui servers crashing both on guiservers 1 and guisever 2
    • Wajid: issue is being investigated --> possibly network issue, but no clear identification as of yet

HED:

  •  all on track

SCS:

  •  

SQS:

  •  

SXP:

  • monday issue with beam

DRC

  •  

PRC

  •  

AOB:

 

  506   15 Apr 2024, 09:31 Andreas GallerGeneralInformationNotes XO Integration Meeting 15.04.2024

General Announcement:

  •  

CTRL:

  • SA1 DAQ upgrade

DA:

  • nothing to report

EEE:

  • nothing major

VAC:

  • involved in XTD1 solid attenuator repair
    • inform control once its done for MDL

XPD:

  • nothing major

DET:

  • nothing major

ITDM: 

  • FES switch for SA3 DAQ update will be replaced today --> DAQ won't be available
    tomorrow gpfs pclayer update

XRO:

  •  SA1 Solid Attenuator repair & SA1 21-22 keV beam transport alignment had been done

LAS:

  • not present

UNSYS: 

  • nothign major

SPB/SFX:

  • beam is prealigned for 21- 22 keV this week, lots user prepartion

FXE:

  • mothing major

MID:

  • allfine

HED:

  • not present

SCS:

  • nothing

SQS:

  • not present

SXP:

  • not present

DRC

  •  

PRC

 

AOB:

  •  

 

 

  403   15 Mar 2023, 10:49 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 15.03.2023
General Announcement:
- Tobias Clever informs on electrical works needed to connect XHO to electrical grid:
1. A new transformer will be connected to the new building on 03.April (a small chance of error can produce a minor power glitch as the ones frequently seen by Desy power glitches - usually this events 
have not affected us in the past 2 years. 
2. Second work on 11.04: test of auxiliary conditions that were installed in December; it will be connected for the first time and a chance that a power glitch could happen affecting more XFEL premises 
(only affecting general power supply - all devices connected to secure or redundant power supply will not be affected). 
There is only a small risk and is necessary to run XHO with power. 
This is scheduled in a blue week and last similar event was in 2021 when cryo went down and XFEL systems were not severally affected, so it shall be contained event. An e-mail will be sent to xo-info list. 
P. Gessler raises the concern that this is a blue week.
- Tobias Clever says that for chillers ordered by instruments please make sure a standing maintenance contract has to be done as degradation of coolants happen with time without maintenance. Maintenance 
contracts are usually renewed automatically after the purchase contract is done. XO will forward the comment to DOB (to discuss level of maintenance contracts: individual or facility wide).

CTRL:
- Datalogger problem: fix will be deployed today at 13:00 and shall not take more than 5 mins. Please contact Wajid E. in case of conflicts.

DA:
- Nothing to report.

EEE:
- Call from DOC related to beam shutter from MID (see below): uncertainty in who could help. A ticket was sent via DOOCS; SRP was involved.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- Julabo chiller exchange is ongoing (see below).

ITDM: 
- Nothing to report.

XRO:
- Instruments are fine with mirrors cooling OFF.

LAS:
- Nothing to report.

UNSYS:
- All fine.

SPB:
- Julabo chiller: repaired unit return is delayed and not arrive today. An emergency plan is on place: transfer chiller from SCS to SPB/SFX is ongoing today.
- Tonight SPB/SFX will not use beam. Between today and tomorrow the new chiller has to be put operational.

FXE:
- FXE can use the beam tonight if there is the wish.

MID:
- D3 shutter: BS6.2.3 shutter; root cause unclear if replacement of PC and/or IP address. Michael Dressel showed how to open shutter “manually” using the interlock box until it is finally repaired. 
Root cause shall be identified still.
- Operation with HXRSS started roughly but today it is better than yesterday (stability as well).

HED:
- Nothing to report.

SCS:
- Problem with DAQ (images could not be saved from detector); looks like slowness but DOC is investigating.

SQS:
- Nothing to report.

SXP:
- Nothing to report.
  207   15 Mar 2021, 11:26 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 15.03.2021
General Announcement:
- Following Desy e-mail to all EUXFEL staff, the emergency call system of the elevators will be offline on Thursday March 18th during the morning. Please avoid using the 
elevators in this day. 
- On March 23rd is scheduled the SEPS interlock tests in SA3. On March 25rd is planned for SA2, pending a confirmation with the machine on the impact in SA1 operation.

CTRL:
- Progressing with investigating the train-ID issues, currently it relates to DOOCS/Desy.
- DOC: reports one fix today at 13:00 (following a call). Please respect a sign "we are in", "we are out" at the DOC to help staff focusing on issues. 

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- All working fine in XPD.
DET:
- Detector commissioning in SPB: AGIPD was completed as planned and Jungfrau seems to run properly (data to be analyzed.

ITDM: 
- ITDM will add more space to the storage system (data taking). Initial idea is to make it on March 30th to minimize impact. Acquiring data and data analysis are not 
impacted. 

XRO:
- Beam power increase ongoing.

LAS:
- An issue with SA1 interlock in PP-laser room: the inside doors were reported to be open on Thursday afternoon. 
As SPB was not using the PP-laser, the laser was put in safe mode and Interlock was broken to access and verify the situation. The internal doors were closed. 
Further discussions will follow. This door issue happened for the first time in SA1. 
- LAS is providing beam to SPB and HED as requested.

UNSYS:
- Couple of e-log entries on settings of air coils and phase shifter, all addressed during the weekend.

SPB:
- Detector program is completed. One measurement (which is not critical) is missing from Jungfrau.
- Interacting with DOC worked nicely.

FXE:
- Preparing for this week.

MID:
- Fully in preparation for first April beam. All fine.

HED:
- Nothing to report.

SCS:
- SCS asks for update of missing CPU from EEE. No news from EEE. Contact will be made.

SQS:
- Preparing to have beam in April.
  395   15 Feb 2023, 10:14 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 15.02.2023
General Announcement:
-	 

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Working with SPB with laser power meter / calorimeter.

DET:
- Not present.

ITDM: 
- Announcement: on next Monday at around 8AM the E-log will not be available for a short time.

XRO:
- Working on SCS exit slit. Recommissioning with beam will need to be done. Next action in tunnel will happen on next Monday. Until then the slit is currently detached with cables. None shall move or touch 
the device.
- Regarding parts: they are ordered and shall arrive later this week.

LAS:
- Nothing to report.

UNSYS:
- Nothing to report.

SPB:
- Nothing to report.

FXE:
- Problem with Jungfrau 1M last night. Informed to DET.

MID:
- Motor of rotation for the spectrometer is not yet working to characterize seeding. EEE is investigating and may have to exchange motor.

HED:
- Beam pointing was realigned. It jitters and feedback tries to work. To be see along the day.

SCS:
- Nothing to report.

SQS:
- Nothing to report.

SXP:
- Nothing to report.
  199   17 Feb 2021, 08:52 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 15.02.2021
General Announcement:
- It had been a cooling water issue with SA1 and SA3 PPLs on Saturday. Other groups are encouraged to check their components for eventual damage. Cooling water is back 
again.
- Change on definition of a critical work: everything that leads to operation is from now on considered a critical work (official communication will be send by e-mail).
- Tomasz J. says interlock tests in SA1 tripped the laser interlock due to the Seeder connection to the interlock. 
Andreas G. says there are care been taken to prevent this in future. More discussion will follow.

CTRL:
- Updates were done on the time servers and data loggers.
- GUI servers will be done this week as there was no access to GITLab. Current suggestion is next Wednesday morning before 08:00AM. 
Each topic will take a few minutes only. XPD is fine with the proposed day/time.

DA:
- Nothing to report.

EEE:
- Issue during weekend: signals to the absorber. EEE and PRC (Maurizio V.) will coordinate when it is the best time for applying the final fix. 
EEE needs to mask it for proceeding with the work.

VAC:
- VAC OCD was involved in the absorber EPS issue.
- Today around lunchtime the XTD6 and XTD9 will be closed.

XPD:
- EPS issues: any component driven to the beam was not protected by many bunches operation. The EPS was thinking the PNACT was closing but in reality, it was opened.
PRC/EEE/VAC/XPD OCDs solved by manually telling the system it is closed.
- Wrong bunch number sent to XGM: SA3 toroid was moved to a different position and the old name was not valid anymore. 
Info from this toroid was not received and the consequence XGM was receiving wrong bunch numbers. This makes impossible for the XGM to calculate correctly the number of 
bunches. 
Doocs servers were not updated (these programs would need to be informed of new naming). 
- Andreas K. says that XTD6 is clean. In XTD9 an intervention by EEE will take place. Bruno F. says that it is a simple task and we are accessing tunnels right now.
- Operation E-log 2021 is missing and must be created. 

DET:
- Offline calibration work is ongoing until tomorrow morning.

ITDM: 
- GPFS offline storage maintenance to be done today. 
- ITDM was notified by Desy that is necessary to reboot logins on Maxwell nodes (between 11:00-12:00).

XRO:
- Nothing to add to what was discussed on the EPS.

LAS:
- Affected by water cooling incident. SA1 came up without issues but in SA3 there is problem as AMPHOS did not restart.
- Trigger issue on last week are not the issue anymore. This was not repeated (but SA1 still on local mode).

UNSYS:
- BBA and photon BBA last week: new values to be implemented and minimum gaps will be updated accordingly.
- Frank Brinker tested the ambient field corrections. A ZZ is taking place this morning to fix SA2/cell12. 
Few other coils have different polarities and will be fixed today or in another ZZ.

SPB:
- Preparing for the first two weeks with beam in March.

FXE:
- Aligned the cameras in FXE mono.
- Crates to be installed in the rack room.

MID:
- Joerg H. raises the question on the FFP2 usage recommendation. Sandra Plett says the document containing guidelines will be prepared (hopefully today); 
It is mandatory to use FFP2 masks if you are not alone; it also depends on the room size and at the moment it is 3-5 people in the hutches with mandatory use. 
A. Galler says these are the current regulations and maybe this will change in future.

HED:
- Nothing to report.

SCS:
- Nothing to report.

SQS:
- Trying to get a new DAQ and will talk to ITDM.
  579   15 Jan 2025, 09:40 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 15.01.2025
General Announcement:
- A. Galler announces that yesterday the cooling water of 20C was leaking. The reason is still to be found, as per e-mail from TS sent to the xo-info.

CTRL:
- Proceeding with updates and nothing to report.

DA:
- Ready for bring-up days.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Information: in XTD6 the PLC loop was repaired.
- XGMs are started (upstream ones).
- As PRC, J. Gruenert says a ZZ is ongoing in XTD10.

DET:
- Nothing to report; prepared for bring-up days.

ITDM: 
- Nothing to report.

XRO:
- The XTD10 H-slit access is finished and cable connection is fixed;
- M. Vannoni sent the draft for the ramp-up plan during next week to the instruments.

LAS:
- Continuing with maintenance tasks.

UNSYS:
- Trying to understand why alignment quadrupoles were inserted in cell#24.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- Not present.

SCS:
- Not present due to interlock tests.

SQS:
- Not present.

SXP:
- Not present.
  482   15 Jan 2024, 10:52 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 15.01.2024
General Announcement:
- Interlock tests light: functional tests will happen this Wednesday starting at 09:00 at the instruments. Emergency OFF will not be pressed.

CTRL:
- Updates are working and going well;
- Experiencing issue with DOOCS devices since Friday. Reported to DOOCS team and needs to roll it up.
- Weekend: issue with SA2 topic: MPP broker had one post that lost connectivity to Karabo (LAS2). Middle layer devices successfully connected and easiest solution was to restart these two topics. 
Done between DRC and PRC. Macros or calibration services were not started yet.

DA:
- Nothing to report.

EEE:
- Friday evening OCD call with VAC.
- Bring up day at FXE went fine.

VAC:
- Problems: false alarm that were cleared out on Sunday and is normal now.
- Continuing some maintenance tasks.

XPD:
- Starting Diagnostic devices this week. From weekend SASE tuning is planned.

DET:
- Nothing to report.

ITDM: 
- Investigating broker in SA2.

XRO:
- Not present.

LAS:
- Not present.

UNSYS:
- Small problem in SA1 / cell28: power distribution terminal must be replaced by ZZ.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- All fine at MID.

HED:
- Nothing to report.

SCS:
- Bring up days starting today at SCS.

SQS:
- Not present.

SXP:
- Nothing to report.
  382   14 Dec 2022, 09:55 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 14.12.2022
General Announcement:
- There will not be Xo Int. meeting next Wednesday 21.12. The last meeting for this series will be next Monday 19.12.
- Martin Doering announces that the DACHS system maintenance previously scheduled for next Monday 07:30AM was already done and there will be no access disturbance next Monday; 
Currently around 48% of the winter maintenance tasks are timely done. For Desy groups around 36% are closed.
- Please inform xo-planning for tasks that are not going to happen or are cancelled/delayed. An e-mail will be sent to inform the groups in the coming days and the file to be updated will appear at the 
Sync&Share system.
- XO has been asked regarding gases and cryogenics. The process in place is the Hall Crew only supporting TS and if any group is needing technical gases and cryogenics, please continue to submit a ticket 
to TS. 
- K. Wrona asks for additional info on the 5Hz operation. A. Galler says that if there is a showstopper this has to be communicated and the startup period in January is meant to test this operation mode.
All timing systems will run at 5Hz and some solutions will be put in place e.g. at the lasers. Reason behind is to save electricity. 

CTRL:
- Done with Karabo upgrade in SA1 and SA3 topics. Today goes on with SA3.
- On Thursday ITDM will upgrade the SA1 topic for data loggers' machines. This takes about 1 hour.

DA:
- Nothing to report.

EEE:
- Ongoing with the current schedule for tunnel updates: SA1 motion done yesterday. Please check these systems in the coming days.

VAC:
- Everything is going accordingly to the schedule.

XPD:
- In a group retreat.

DET:
- Testing detectors after the Karabo update.
- Following request from DA to test Detectors calibration pipeline (LPD, AGIPD-1M).
- Operation at 5Hz will be discussed internally.

ITDM: 
- Continuing the calibration work.
- Finalize servers update today (there is one hardware issue to solve).
- Data loggers for SA1 will be changed to the new hardware. An e-mail will be sent.

XRO:
- Not present.

LAS:
- Nothing to report.

UNSYS:
- Small absorber at the end of SA2 was installed in preparation for the SCUs.
- SA3 will have a Marwin installed to measure radiation during operation.
- Beckhoff sent back repaired motors for PSs. A total of 8 spares are now available.
- SA3 undulators had a power cut and is under investigation.

SPB:
- Nothing to report.

FXE:
- Maintenance of the electrical rack today.

MID:
- All fine at MID.

HED:
- Not present.

SCS:
- Nothing to report.

SQS:
- Work happening at the experimental hutch today; Filter change for the air conditioning has to be postponed.
  186   14 Dec 2020, 09:00 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 14.12.2020

General Announcement:

- Please write to xo.planning, if something comes up with intteruption of the maintenance due to new COVID-19 regulations.

CTRL:

- Migration of Beckhoff MC2 motors at SA3.

- Checking operation (e.g. soft mono at SA3).

- Final checks together with EEE.

DA:

- nothing to report

EEE:

- Migration at SA3 MC2 PLC´s.

- Fast ADC: SA2 maintenance starts.

- Cabling to be done in SQS today and tomorrow at HED.

- Crate was sent to Poland and shall arrive this week.

VAC:

- not present.

XPD:

- problem / alarm XGM at SASE1 / XTD2  - Needs to re-cable and install new gauges; requires VAC group.

- PES was re-installed in XTD10 and has been pumped down.

- DAQ test on friday - things are fine.

- XTD6 XGM alignment starts today - used to be confirmed with VAC.

DET:

- AGIPD intervention: need some internal coordination also with DASY groups - it will let XO know, if support needed

ITDM:

- XFEL gateway next Monday

- pre-anouncement: 90% of maxwell cluster update to be done on January 4/5. Communication to be send to Readiness mailing list.

XRO:

- Testing Controls in tunnel devices - needs to fix SA3 expected bugs.

- XTD10 close the vaccuum for M6 mirror chamber this week.

- XTD6 some problems with M3 mirror: to be pumped down this week and checked start of January.

LAS:

- Small delay on works at SA3, but no risk for users.

- Question from LAS: is the SA1 laser interlock update takes place?

- SA2 AMPHOS: external company is coming today

UNSYS:

- not present

SPB:

- nothing to report

FXE:

- nothing to report

MID:

- all fine

HED:

- don´t have anything

SCS:

- nothing to report

SQS:

- nothing to report