SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 191
Entry time: 18 Jan 2021, 09:44
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 18.01.2021 |
|
|
General Announcement:
- Clarification on the definition of a critical work will be made this afternoon during a discussion with group leaders and will be communicated to the staff.
It includes also tasks carried out by two different groups.
- On Thursday there is going to be a switch of MPS components in the balcony room.
This affects the timing signal distributed to XFEL, e.g. Lasers will not be able to follow timing.
- Test of automatic switch of power bridge is shifted to Feb.2: this affects all devices connected to orange or green power sockets (no power for few seconds/minute).
General e-mail will be sent. Instruments will need to care for equipment which is connected to these sockets.
This also affects the E0 level as well as office space in XHQ. Pease plug devices out or re-plug in other sockets.
CTRL:
- CTRL enquires ITDM on the issue with DOC (disk space full error). ITDM will take a look into it.
DA:
- Getting prepared for involvements such as the data operation center.
EEE:
- Update of SA1 loop motion to take place by Wednesday. Affected staff is already informed.
- Firma Wille work on cabling is ongoing.
VAC:
- Continuing with works in the tunnels.
XPD:
- Tunnels works in XTD6 and XTD9 are ongoing. No incidents to report.
DET:
- Working on data analysis calibrations and installing the DOC.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Regarding the Timing signal interruption mentioned in general announcements: it is not a problem as usually LAS keep the laser systems in the local timing during
shutdown periods.
- Upgrading hardware that should be updated accordingly to the plans for the shutdown.
UNSYS:
- Works in tunnel are proceeding.
- Issues with SA2 cell 26 and cell27 were found and experts are going to the tunnel to solve it.
SPB:
- Working on making experimental plans for the Covid-19 beamtime.
FXE:
- Detectors: software upgrade taking place from today.
MID:
- All fine.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Nothing to report. |