Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 435     Entry time: 17 Jul 2023, 09:53
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 17.07.2023 
General Announcement:
- SEPS interlock tests are taking place today. An e-mail was sent to xo-info last Friday containing information about the order of the tests.

CTRL:
- Start with bring up days (SCS and SXP today) the whole week.
- Workaround solution for PLC/Karabo was deployed but needs to be redone tomorrow at 8AM tomorrow. An e-mail will be sent to xo-info.

DA:
- Nothing to report.

EEE:
- Bring up days and support of SEPS. 

VAC:
- Nothing to report.
- As PRC, Martin D. says on Saturday morning issues with AIBS blocked beam operation. Solved by DRC and EEE/PLC OCD.

XPD:
- Nothing to report.

DET:
- Nothing to report.

ITDM: 
- Data analysis of experiments (past ones): to be migrated on next week over three days. E-mail to be sent to xo-info.

XRO:
- Involved in the SEPS interlock today.
- ZZ for HED Mono was successful by power cycling device Not yet clear if camera is broken or a Karabo/PLC issue. 

LAS:
- Nothing to report.

UNSYS:
- All fine.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- PP laser work this week and then setting up beamtime for cw31.

SCS:
- Not present.

SQS:
- Nothing to report.

SXP:
- Not present.
ELOG V3.1.4-7c3fd00