Message ID: 507     Entry time: 17 Apr 2024, 09:47
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 17.04.2024 
General Announcement:
- A. Galler inform on the transponder/access issues at XHEXP1 last two days: when turnstiles are not working, people shall not get though and enter experimental Hall. 
This is a safety break that will be taken by SRP. Please do not enter Hall if turnstiles are not working. 
- As DRC, A. Silenzi informs there is nothing to report so far.

CTRL:
- Together with XPD and XRO a new version of DAQ in tunnels was installed and tested. All went fine.

DA:
- Nothing to report.

EEE:
- Nothing to be reported.

VAC:
- Nothing to report. Repair on Monday went successful.

XPD:
- Nothing to report.

DET:
- Nothing to report.

ITDM: 
- DAQ Switch in SA3 was exchanged and work fine.
- GPFS update is postponed to a later date (tbd).

XRO:
- SA2 ATT #5 (1.2mm CVD) is replaced and working.
- SA1 mirror is calibrated to work with Euler motions.
- SPB/SFX is aligned with 22keV beam.

LAS:
- Nothing to report.

UNSYS:
- PS motor in SA1/cell23 was replaced yesterday by a ZZ.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- All fine at MID.

HED:
- Not present.

SCS:
- Nothing to report.

SQS:
- Nothing to report.

SXP:
- Not present.