Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 1 of 29  Not logged in ELOG logo
ID Date Author Location Severity Subjectdown Text Attachments
  27   01 Apr 2019, 10:29 ITDM AdminGeneralInformationrunning jdd panels in control rooms​​​​​On all
PCs in the control rooms including BKR and
also on the exflgateway there is a new version
  
  104   23 Mar 2020, 08:57 Andreas GallerGeneralInformationnotes Dispatch meeting Mar 23 2020Currently EuXFEL
enforces a hand-off policy for instrument/tunnel
hardware. That includes remote control of
  
  100   04 Mar 2020, 08:49 Andreas GallerGeneralInformationnotes Dispatch meeting Mar 2 2020SPB:


AGIPD improvement campaign
great success
EEE --> 2nd C&C
  
  96   22 Jan 2020, 09:16 Andreas GallerGeneralInformationnotes Dispatch meeting Jan 20 2020

SPB:


nothing to report


FXE:
  
  95   15 Jan 2020, 09:09 Andreas GallerGeneralInformationnotes Dispatch meeting Jan 13 2020

SPB:


Testing coordinated movement
  
  99   26 Feb 2020, 09:06 Andreas GallerGeneralInformationnotes Dispatch meeting Feb 24 2020SPB:


nothing to report


FXE:


not present due to group
  
  101   10 Mar 2020, 12:44 Frederik Wolff-FabrisGeneralInformationnotes Dipatch Meeting March 9th, 2020* Users are scheduled to be here this week
(4 beamlines in user runs). SPB, HED, MID
report several users have cancelled the travel.
  
  98   17 Feb 2020, 12:02 Frederik Wolff-FabrisGeneralInformationnotes Dipatch Meeting Feb. 17th, 2020FXE:
Nothing to report: no issues;
  
  108   06 Apr 2020, 09:50 Frederik Wolff-FabrisGeneralInformationnotes Dipatch Meeting April 6th, 2020CTRL:
- It was remotely observed that some cameras
were consuming too much memory. By remotely
  
  87   27 Nov 2019, 09:25 Andreas GallerGeneralInformationdispatch meeting Mon Nov 25 2019FXE: no issues

SPB: no issues

MID: Split & Delay line arriving
  
  88   28 Nov 2019, 15:42 Andreas GallerGeneralProblemaffected ITDM Systems after power cut tonight


XHQ.E1.092

SW-HH-AL-271
was available
  
  145   22 Jul 2020, 09:22 Andreas GallerGeneralInformationXO integration meeting 22.07.2020General Announcement:


Default beam positions
are being implemented for each SASE at the
  
  105   25 Mar 2020, 09:32 Andreas GallerGeneralInformationTechnical Integration Meeting 25.03.2020Currently EuXFEL
enforces a hand-off policy for instrument/tunnel
hardware. That includes remote control of
  
  103   18 Mar 2020, 09:26 Andreas GallerGeneralInformationTechnical Integration Meeting 18.03.2020

SPB:


interument parked
power
  
  110   15 Apr 2020, 09:03 Andreas GallerGeneralInformationTechnical Integration Meeting 15.04.2020

CTRL:


notificagion service device
  
  109   08 Apr 2020, 08:45 Andreas GallerGeneralInformationTechnical Integration Meeting 08.04.2020

CTRL:


no bigger issues
announcement:
  
  107   01 Apr 2020, 09:19 Andreas GallerGeneralInformationTechnical Integration Meeting 01.04.2020

CTRL:


productive meeting with
  
  89   04 Dec 2019, 14:18 Adriano ViolanteGeneralInformationSummary of the technical integration meetingFXE


No major issues - PLCs
update has been started by EEE (BB)


SCS
  
  85   13 Nov 2019, 10:12 Adriano ViolanteGeneralInformationStatus report after tech. Int. Meeting 9.30​FXE


Radiation tests ongoing.
EEE
informs that the PLC drawings will be exchanged
  
  48   27 May 2019, 10:35 Gerd WellenreutherGeneralInformationStatus report after dispatch meeting Monday 27.5. 09.30 SPB/SFX


Digitizers are ready, have
been tested by CAS ==> to be be installed
  