SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 85
Entry time: 13 Nov 2019, 10:12
|
Author: |
Adriano Violante |
Location: |
General |
Severity: |
Information |
Subject: |
Status report after tech. Int. Meeting 9.30 |
|
|
FXE
- Radiation tests ongoing.
- EEE informs that the PLC drawings will be exchanged in the WS
SPB/SFX
SCS
SQS
MID
HED
- During the first week of shutdown (KW47) the loop1 devices will be put into closed loop (e.g. for backlash compensation).
- An electrical shutdown seems to be necessary to upgrade the protection against the power glitches, especially to protect the optical lasers. This is now planned for the 17/18.19 for SASE2 and similar dates for SASE1 and 3. AV will try to collect more information and come back to the instruments ans technical groups.
Optical lasers
VAC
XRO
XPD
DET
EEE
- EEE needs the updated interlock definitions from VAC
- The list of requested services during the WS is very long. NJ is trying to plan the works inside EEE and will come back to XO/PMO in case priorities have to be assigned. Also, late requests and changes are making things more difficult.
Controls
- The overnight and weekend OCD service will stop during the shutdown. OCD only available until 18:00
- Karabo 2.7.0 deployment date (now forseen for KW51) is being verified. More info to come.