Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 96
Entry time: 22 Jan 2020, 09:16
|
Author: |
Andreas Galler |
Location: |
General |
Severity: |
Information |
Subject: |
notes Dispatch meeting Jan 20 2020 |
|
|
SPB:
FXE:
- MC2 library motor commissioning on-going
MID:
- SDL motor parameters defined, however one crate is blocked by Wille and 6 motor connectors (Harting material) are still missing
once fixed, motor paramaters can be uploaded
- WCB (wall connection boxes) in otics hutch are partially finished
HED:
- Wille is working on some crates and the respective Beckhoff loops are down for the moment
- loop updates from Tuesday on
EEE:
- additional limit switched for XTD6 CRLs (MID) are being installed
- HED is asking for limit switches on their XTD6 CRLs as well --> EEE and HED will investigate when and how
- cable change in FXE starts this week with exchaging wrongly poled SHV cables
CTRL:
VAC:
XRO:
|