Group Selection Page
HELP
Controls Group
ITDM
Vacuum
WP78
SPB
SQS
XO
ToBeMigrated2XWiki
ToBeMigrated2GitlabPages
ToBeMigratedByGroup
Migrated2Zulip
Archived2PDF
not2MigrateOrArchive
SCS
SXP Migrated2Zulip
Photon Commissioning Team
XRO
DOC
HED Migrated2Zulip
WP74
MID
PSPO_XO
XO_Operation
SQS Migrated2Zulip
FXE Migrated2Zulip
DET
Sample Environment
SPB Migrated2Zulip
SASE1 Status and SASE3 Readiness
Technical integration and coordination
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther
Not logged in
List
|
Find
|
Login
|
Help
Message ID:
96
Entry time:
22 Jan 2020, 09:16
Author:
Andreas Galler
Location:
General
Severity:
Information
Subject:
notes Dispatch meeting Jan 20 2020
SPB
:
nothing to report
FXE
:
MC2 library motor commissioning on-going
MID
:
SDL motor parameters defined, however one crate is blocked by Wille and 6 motor connectors (Harting material) are still missing
once fixed, motor paramaters can be uploaded
WCB (wall connection boxes) in otics hutch are partially finished
HED
:
Wille is working on some crates and the respective Beckhoff loops are down for the moment
loop updates from Tuesday on
EEE
:
additional limit switched for XTD6 CRLs (MID) are being installed
HED is asking for limit switches on their XTD6 CRLs as well --> EEE and HED will investigate when and how
cable change in FXE starts this week with exchaging wrongly poled SHV cables
CTRL
:
nothing to report
VAC
:
nothing to report
XRO
:
nothing to report