Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 87     Entry time: 27 Nov 2019, 09:25
Author: Andreas Galler 
Location: General 
Severity: Information 
Subject: dispatch meeting Mon Nov 25 2019 

FXE: no issues

SPB: no issues

MID: Split & Delay line arriving on Friday, MID aims for a quick integration into instrument / beamline
         EEE informed to switch Hexapod motors from loop3 to loop 7

HED: changing loop1 (JJ X-ray motors) from open to closed loop operation

 

SQS: KB works, see sometimes spontaneous switching of end switch logics

EEE: MID, SPB, VAC loop updates running this week;
         no triggers for experiments available until end of power off work
         Jörn: cabling for MID is in full swing, for future installations first check phase 1 cabling, for non blocking
                                   HED: cabling
                                   SCS company Witte 30 ccables
                                   FXE: two CRDs not approved yet, no cabling during this shutdown

Controls:
 