FXE: no issues
SPB: no issues
MID: Split & Delay line arriving on Friday, MID aims for a quick integration into instrument / beamline
EEE informed to switch Hexapod motors from loop3 to loop 7
HED: changing loop1 (JJ X-ray motors) from open to closed loop operation
SQS: KB works, see sometimes spontaneous switching of end switch logics
EEE: MID, SPB, VAC loop updates running this week;
no triggers for experiments available until end of power off work
Jörn: cabling for MID is in full swing, for future installations first check phase 1 cabling, for non blocking
HED: cabling
SCS company Witte 30 ccables
FXE: two CRDs not approved yet, no cabling during this shutdown
Controls:
|