SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 103
Entry time: 18 Mar 2020, 09:26
|
Author: |
Andreas Galler |
Location: |
General |
Severity: |
Information |
Subject: |
Technical Integration Meeting 18.03.2020 |
|
|
SPB:
- interument parked
- power cut --> someon needs to come in
- NJ: what'S that status of the VAC
- KC & RB: safe state, roughing system still running, in the event of a power cut this needs to be looked at
FXE:
- nothing to report
- NJ: VAC in safe state? --> MK yes everything is switched off
MID:
- instrument parked, VAC is running but pumps will be stopped today and partially vented
- gate valves are closed hopefully the VAC stays
SCS:
- SCS in safe state, all pumps running
- valves around KB are permenantly closed
- in the event of a power cut all other gate valves will close
- loop update done yesterday
EEE:
- preparation for safe state ongoing
CTRL:
- is master timing going away or not?
- if master timing goes down, some devices
- ICI contacts identify what can be remotely done and what not
ITDM:
HED:
- HED is going to sleep within the next two days
DA:
- focus on long standing tasks
XRO:
- beam transport is going to be parked today
|