Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 103     Entry time: 18 Mar 2020, 09:26
Author: Andreas Galler 
Location: General 
Severity: Information 
Subject: Technical Integration Meeting 18.03.2020 

SPB:

  • interument parked
  • power cut --> someon needs to come in
  • NJ: what'S that status of the VAC
  • KC & RB: safe state, roughing system still running, in the event of a power cut this needs to be looked at

FXE:

  • nothing to report
  • NJ: VAC in safe state? --> MK yes everything is switched off

MID:

  • instrument parked, VAC is running but pumps will be stopped today and partially vented
    • gate valves are closed hopefully the VAC stays

SCS:

  • SCS in safe state, all pumps running
  • valves around KB are permenantly closed
  • in the event of a power cut all other gate valves will close
  • loop update done yesterday

 EEE:

  • preparation for safe state ongoing
    • discussed

CTRL:

  • is master timing going away or not?
  • if master timing goes down, some devices
  • ICI contacts identify what can be remotely done and what not
  • u

ITDM:

  • nothing special

HED:

  • HED is going to sleep within the next two days

DA:

  • focus on long standing tasks

XRO:

  • beam transport is going to be parked today