Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 104     Entry time: 23 Mar 2020, 08:57
Author: Andreas Galler 
Location: General 
Severity: Information 
Subject: notes Dispatch meeting Mar 23 2020 

Currently EuXFEL enforces a hand-off policy for instrument/tunnel hardware. That includes remote control of motors, pumps, etc.. as well as changing config Files. If and when this policy is lifted will be communicated during Dispatch and Technical Integration Meetings. Please also don't hesitate and contact XO in case of any questions.

SPB:

  • reached safe state
  • rougning pumps still runnning and valves open
  • PLCs need to run for monitoring

FXE:

  • n

MID:

  • absolutely safe
  • cooling water connection
  • PLCs switched off

SCS:

  • S

 EEE:

  • MID switched off completely, all other PLCs are running
  • MID utca also shut down
  • Jörn, plenty of time for additional planning

CTRL:

  • broker logs ok from last weekend
  • ICI contacts are in discussion instruments

ITDM:

  • while instrument schutdown, network and servers are still running

HED:

  • safe state, all motors switched off ( parameters saved) all valves close, ion pumps are stil running.

DA:

  • work to do

XRO:

  • M1s parked on Friday, tunnel seems ok, lenses seem to be fine
  • small problems in the GUI,

XPD:

  • x-ray diagnostics had been secured last week, i.e. power ramped down. XGM vaccum needed.

FXE:

  • Jungfrau chiller switched on, AMPHOS shutter chiller
  • OGT3 no pump cart, ion pumps still running, gate valves closed

VAC:

  • V0 closed, OCD looking at vacuum twice a day, PLCs needed and running