Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 107     Entry time: 01 Apr 2020, 09:19
Author: Andreas Galler 
Location: General 
Severity: Information 
Subject: Technical Integration Meeting 01.04.2020 

CTRL:

  • productive meeting with HED
    • CTRL will ask the other instruments if a similar concept could be agreed upon
  • discussion with LAS this afternoon with respect to the current hardware policy

EEE:

  • HED provided tasks that EEE shall do
  • uTCA development ongoing
    • review how digitizers are being used (fastADC, SPdevices, clock & Control)

VAC:

  • power glitch

XPD:

  • nothing to report

DET:

  •  

ITDM:

  • nothing to report, no indication of power glitch

XRO:

  • no indication of power glitch

SPB:

  • nothing to report

FXE:

  • nothing to report, problem to read out pressure values
    • Bernd Baranasic: no ion pressure readings on OGT1
      • in PLC it looks ok, but karabo shows 0
    •  

MID:

  • meeting with DESY safety colleagues wrt PUMA, going to be bundled with LDM safety
  • discussing with Bruno about digitizers
  •  

HED:

  • see CTRL

SCS

  • only valves in loop1 were closed
  • every few days a pump is failing, new behaviour
    • JG: comments it is a known behaviour that one of the gauges showed an erratic behaviour (wrongly set epsilon in karabo)
    • GM: answers, what happened on Saturday was slighty different

DA:

  •  