Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 89     Entry time: 04 Dec 2019, 14:18
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Summary of the technical integration meeting 

FXE

  • No major issues - PLCs update has been started by EEE (BB)

SCS

  • Hrixs and related components will be delivered on 13 and 14.01.2020. SCS is coordinating the works with TS in order to crane the chambers into the hall (collision with the scaffolding required for HED dipole laser)
  • Puls picker update in XTD10. Requires update of loops. EEE is not informed. JTD follows the issue up.

EEE

  • General work is ongoing.
  • Next week the EPS loops will be updated in the framework of the full beam operation project.
  • Issue with a PLC in SPB crashing after update to Win10. Beckhoff is working to a solution. If this does no work the PLC will be replaced.

Controls

  • A mail will be sent out early next week to announce th deployment schedule of the new Karabo release.