ID Date Authordown Location Severity Subject
  27   01 Apr 2019, 10:29 ITDM AdminGeneralInformationrunning jdd panels in control rooms

​​​​​On all PCs in the control rooms including BKR and also on the exflgateway there is a new version of jddd installed which is working with openjdk-11.
It is worth to mention that the old javaws from old oracle java 8 is deprecated and it is not recommended running jddd panels using old way, like
javaws jddd-run.jnlp

The recommended way, is to run it on the control PC (if you are in the control room), you don't need to login to exflgateway and start it there anymore, although this is also possible.

To start a svn repository selection window just run
jddd-run

To start a panel of a given name from http repository just type for instance
jddd-run -http XFELMainTaskbar.xml

To start a panel from svn repository just type for instance
jddd-run -file XFELMainTaskbar.xml
 

In case of question contact it-support@xfel.eu

Best

Janusz

  57   19 Jun 2019, 16:33 ITDM AdminGeneralInformationRe: running jdd panels in control rooms

Regarding the recent announcements from doocs/jddd people about running jddd application I post here a short summary:
- running jddd with oracle java 8 via java webstart will be no longer possible as of 10.07.19
- on all control PCs in the instruments control rooms, BKR and exflgateway the new jddd was already in use since March, as described in the previous entry
- today the jddd was updated to version 2.12.10-2, which includes openjdk-12 (control PCs will be automatically updated during night)

On Windows 10 you can install Jddd using Software Shop (Netinstall).

Best, 

Janusz
 

ITDM Admin wrote:

​​​​​On all PCs in the control rooms including BKR and also on the exflgateway there is a new version of jddd installed which is working with openjdk-11.
It is worth to mention that the old javaws from old oracle java 8 is deprecated and it is not recommended running jddd panels using old way, like
javaws jddd-run.jnlp

The recommended way, is to run it on the control PC (if you are in the control room), you don't need to login to exflgateway and start it there anymore, although this is also possible.

To start a svn repository selection window just run
jddd-run

To start a panel of a given name from http repository just type for instance
jddd-run -http XFELMainTaskbar.xml

To start a panel from svn repository just type for instance
jddd-run -file XFELMainTaskbar.xml
 

In case of question contact it-support@xfel.eu

Best

Janusz

 

  35   24 Apr 2019, 10:05 Gerd WellenreutherGeneralInformationMinutes of the Technical integration meeting 24.04.19

SPB/SFX

  • SPB/SFX is preparing for the upcoming beamtime.
  • CRL motors being tested. --> Still ongoing.
  • CSS interlock tests being planned for tomorrow. --> Still ongoing.
  • AE needs to know when Loop 9 and 10 are expected to run. SPB to check.

FXE

  • AE needs to get information on PLCs loop splitting. FXE to comment. 
  • Loop 6 is required to drive 2 servo motors. BB will try to bring this into operation this week. NC checked the setup.

SQS

  • AE still needs priorities for the next loops. SQS to comment.

SCS

  • Discussion with EET ongoing concerning the installation of cables for end stations. Space problem. --> This is a long term issue, to be discussed in the other meetings, ongoing.
  • Commissioning of the motion is ongoing. JT is fixing particular motors / issues.
  • Further testing is including interlocks, vacuum and chiller.
  • Loop 12 is supposed to be up & running by the end of next week

 MID

  • For Loop 9 CY is preparing a change request. AE involved. --> still pending
  • Loop 12 will be operable this week --> an 100V input is needed, but not readily available. To be checked by AE.
  • Priorities for next loops needed by AE to plan the work. --> Still required.

HED

  • Loop 7 being commissioned --> still being commissioned, encoders are misbehaving / behaving strange.
  • Loop9 (Smaract stages) has to be brough up.  --> will be done this week
  • Next loops are 8 followed by the priority-items from loop 6.
  • Loop10 and 11 regarding PPL will be needed in June. HED to confirm. --> Feedback from MN required.

OPT Lasers

  • AE support is needed in order to bring the SCS laser up by the end of may. Mail has been sent. NJardon checks. --> Loop extended and running by the end of next week.

XRO

  • Motion loop for Hirex 2 has been delayed until June

XPD

  • Issue repoeted from CAS: Fast ADC for MCP in SASE3 duplicates data in the 3 % of cases. DAQ is not responsible. Tests have to be made and for that the ADC servers have to undergo to short interruptions. Will be coordinated with XPD. Should not be e problem. CAS to follow the issue up. --> Unclear, CAS not attending.

VAC

​​DET

AE

​​ITDM

  • New DACHS-area "Balcony rooms" will be setup. Requires local training by ITDM, which is currently being organized.

EET

  • Working on MID SDL and SCS day 2 components.

CAS

SRP

  • Schedule changes for the Summer shutdown due to modification of the interlock systems. Additional meetings needed. No info is expected before the beginning of May. --> an uncoordinated email was sent around by MDressel (MPS). SRP will take care of clarifying with MPS what has to be done, when, and will communicate this.

TS

AoB

  45   20 May 2019, 10:02 Gerd WellenreutherGeneralInformationStatus report after dispatch meeting Monday 20.5. 09.30

SPB/SFX

  • are working on achieving a good focus @ 6 keV, which currently is not as good as expected.
  • Digitizers are ready, have been tested by CAS ==> to be be installed / integrated probably next week
  • Different GUIs were reporting varying values for STATUS on different clients / machines ==> ARound will make sure a proper description of the issue (which machines, which clients, when, ...) will be brought to the attention of the proper people @ CAS.

FXE

  • The Karabo FAI went well, FXE thanks explicitly for the support received.

SQS

  • The pnCCD is being set up. AE will be required to help for axes commisisoning next week. ==> this should happen today.

SCS

  • MTeichmann attended, fresh from vacation, nothing to report, everything is "awesome".

 MID

  • Commissioning the cryomanipulator. Had to use a couple of work arounds in order to align it with the beam (travel range issues it appears).
  • The AGIPD Julabo chiller failed on Saturday, it has to be sent in. Meetings this mornings should clarify what other options remain to support the user experiments as planned.

HED

  • User experiment went very well.
  • Currently commissioning ion pumps in the optics hutch
  • Starting on Wednesday loop 6 is to be commisioned (exp. hutch components) together with AE

OPT Lasers

​​XRO

XPD

VAC

DET

  • Question to ITDM: Did the crash of git on Saturday affect the calibration database (there were apparently issues @ FXE for 2 hours) ==> No. If there would have been problems, they would not have resolved with nobody doing anything, the system requires manual intervention. So most probably the problem was somewhere else...

​​AE

  • SCS had a problem with the fast ADC, was fixed Friday. Did this gave further problems during the weekend ==> MTeichmann to check.

ITDM

EET

CAS

SRP

TS

AoB

  46   22 May 2019, 09:58 Gerd WellenreutherGeneralInformationMinutes of the Technical integration meeting 22.05.19

FXE

SPB/SFX

  • XTD2 attenuator appears to be damaged.
  • Beam at lower energies look disturbed, SPB/SFX will contact XRO.
  • Digitizers have been requested. HW needs to be installed and set up and the timeline has to be clarified betweek BF and SPB. ==> next week

SQS

  • pnCCD: testing the 5 axis of motion. 3 are working, but there are problems, the wiring of the cables is now being checked.

SCS

  • Some issues are noticed regarding the triggering of the detector, but BF is on it

 MID

  • Due to the failed chiller, the user experiment had to be cancelled.
  • As a consequence, time is available to commision other hardware. ==> to be clarified with AE which activities can be supported.
  • Integration of the LDM: Safety document is needed.

HED

  • Loop 6 being commissioned.
  • Loop 1 was updated, parameters got lost. :-(
  • Detector issues regarding Epix 100: First some HW + assistance from MID was provided to get the detector running. By now, the HED-owned HW for the Epix 10K is being used.

XRO

XPD

VAC

DET

AE

  • Loop priorities for HED and MID are needed.
  • AE reminds everybody to contact TSchoen if power is required during the middle of June, e.g. in order to keep the vacuum running.

ITDM

EET

CAS

SRP

  • A safety walkthrough for SASE2 was done. Several installations are in conflict with the safety regulations regarding e.g. electrical installations. Detailed minutes will be provided. SRP will also involve TS / Süleyman Arslan.

TS

AoB

  47   24 May 2019, 11:01 Gerd WellenreutherGeneralInformationStatus report after dispatch meeting Friday 24.5. 09.00

SPB/SFX

  • are working on achieving a good focus @ 6 keV, which currently is not as good as expected. ==> This is understood now, those were higher harmonics, too many absorbers in the beam. Absorber still shows some structure, though
  • Digitizers are ready, have been tested by CAS ==> to be be installed / integrated probably next week ==> according to Adrian probably Monday, to be confirmed with AE (Bruno + Hamed)
  • Different GUIs were reporting varying values for STATUS on different clients / machines ==> ARound will make sure a proper description of the issue (which machines, which clients, when, ...) will be brought to the attention of the proper people @ CAS. ==> CAS is aware.
  • Data from motor + camera was taken to correlate motion data. ==> still has to be understood with help of DET and ITDM.
  • AGIPD quadrant motion is needed in summer in order to align the detector in order to record data at low scattering angles / closely around the beam center. ==> is scheduled for summer shutdown

FXE

SQS

SCS

  • First light was seen on the DSSC!

MID

  • AGIPD control server is dead ==> to be replaced by a spare by ITDM / Janusz

HED

OPT Lasers

​​XRO

XPD

VAC

DET

  • pnCCD integration is progressing at SQS, testing taking data with the DAQ.
  • MID-chiller issue: chiller will return in next week.
  • Increasing amount of problems and sufferings due to unreliability of gitlab

​​AE

ITDM

EET

CAS

  • OCD-call regarding device communication: The polling-intervall epsilon was set too small, such that the client became flooded and turned unresponsive.

SRP

TS

AoB

  • Shutdown planning now includes MKK, which includes some activities concerning cooling water. Please check, email was sent to readiness.

  48   27 May 2019, 10:35 Gerd WellenreutherGeneralInformationStatus report after dispatch meeting Monday 27.5. 09.30

SPB/SFX

  • Digitizers are ready, have been tested by CAS ==> to be be installed / integrated probably next week ==> according to Adrian probably Monday, to be confirmed with AE (Bruno + Hamed) ==> is confirmed to be today
  • Different GUIs were reporting varying values for STATUS on different clients / machines ==> ARound will make sure a proper description of the issue (which machines, which clients, when, ...) will be brought to the attention of the proper people @ CAS. ==> CAS is aware. ==> CAS has a suspect.
  • There appears to be an issue with recorded / stored values vs. values shown in the client of motors moving. CAS shall receive a proper + detailed description of the issue.

FXE

  • Tool to save motor positions is not working reliably. ==> CAS + AE have different tools on different levels. There is not automatic / global restoring of for example motor positions from the CAS-side available. BUT in the shutdown motor position should not be lost, unless there is a true power outage also affecting the CPUs.
  • Problems with the PP-laser have been reported.

SQS

SCS

MID

  • Request to have the same kind of feedback as implemented at FXE ==> will require HW changes, to be done during the summer shutdown, and work by CAS in order to adapt the procedure from FXE.

HED

  • According to KS the Smaract-stages are to be checked with AE
  • Interlock definitions would be needed by Wednesday ==> MS is on it.
  • Last weeks issues regarding the epix were probably caused by the DAQ.

OPT Lasers

​​XRO

XPD

VAC

DET

  • The DSSC underwent successful readout test, more DAQ-test to come.
  • The pnCCD saw first visible light, working now on the delay / timing.

​​AE

ITDM

EET

CAS

  • A Hotfix 2.4.2 is provided by CAS, which should fix some issues related to the XGM.

SRP

TS

AoB

  49   29 May 2019, 10:30 Gerd WellenreutherGeneralInformationMinutes of the Technical integration meeting 29.05.19

FXE

SPB/SFX

  • XTD2 attenuator appears to be damaged. ==> Request to VAC: is it possible to exchange the attenuators in the summer shutdown? LBatchelor might have spares.
  • Digitizers have been installed
  • Bunch number is reported to have jumped from 1 --> 150, report to be provided by SPB/SFX so CAS can investigate.
  • Top priority: Testing new camera + DAQ interface along with motor positions recording @ 10Hz

SCS

  • Currently running + supporting the user experiment

SQS

 MID

  • Integration of the LDM: Safety document is needed. ==> This is needed ASAP!!!
  • Further commissioning is ongoing

HED

  • Loop 6 being commissioned. ==> done

VAC

  • Preparing for Shutdown

XRO

  • Preparing for Shutdown

XPD

DET

EEE

  • Loop priorities for HED and MID are needed.
  • AE reminds everybody to contact TSchoen if power is required during the middle of June, e.g. in order to keep the vacuum running.

CAS

  • Supported / tested measurements of gain curves in SASE1
  • Next week: Testing of correlator
  • Karabo Hotfix 2.4.2 was released, new week testing of 2.5. commences
  • Progress regarding InfluxDB etc. was achieved and reported, e.g. to readiness mailing list

ITDM

SRP

TS

AoB

  • No Dispatch on Friday due to the bridge day!
  51   05 Jun 2019, 09:59 Gerd WellenreutherGeneralInformationMinutes of the Technical integration meeting 05.06.2019

FXE

SPB/SFX

  • few days of beamtime remaining, no particular issues
  • preparing for emergency power off
  • preparing shutdown activities with EEE

SCS

  • beamtime, no particular issues.
  • preparing for shutdown
  • XGM is supposed to run even despite the emergency power off ==> M. Teichmann is in contact with T. Schoen (TS)

SQS

  • beamtime, first scattering images taken using the pnCCD!
  • preparing for shutdown, in particular some cabling together with EEE

 MID

  • Integration of the LDM: Safety document is needed. ==> This is needed ASAP!!! ==> THIS IS STILL NEEDED!!!

HED

  • CAS was able to follow up regarding the request for test of triggering / pulse on demand from this Monday. HED was kind of lucky, CAS would appreciate some further notice next time...
  • Due to missing endswitches / interlock conditions, some YAG-screens have been burnt. HED would like to try to get this fixed in the tunnels and the hutches still in this shutdown by installing endswitches etc., to be negotiated with EEE
  • The bias teeth(???) used by HED are not being supplied any more, new ones are not performing ==> to be checked with other instruments / EEE, Sato-san was suggested as another expert to ask.

Optical lasers

  • everything fine, thanks for the support!

VAC

  • Requested to see the first pump + valve of SPB/SFX ==> to be clarified by VAC, SPB/SFX + EEE

XRO

XPD

DET

EEE

CAS

ITDM

SRP

  • From SBP/SFX: Currently, it is not clear what to do if one of the Pandoras goes off. This apparently happened @ FXE on the night from Sat.-Sunday, and it took 12 hours to fix it.

TS

  • From CAS: TS should not rely on email alerts to monitor the cooling of the servers running for example the email services...

AoB

  78   12 Aug 2019, 09:50 Gerd WellenreutherGeneralInformationStatus report after dispatch meeting 12.8.

XO

FXE

  • XTD1 CRLs: There is an issue regarding a limit switch, to be repaired in the shutdown by MKnoll + EEE.

SPB/SFX

  • Master loop has to be updated. EEE to agree offline with SPB/SFX ==> has been fixed
  • Hexapods are being integrated. ==> was supposed to be tackled today. But since both HED and MID experienced different issues with their hexapods, the commissioning at SPB/SFX has to rescheduled (Tuesday?)
  • Micro KB encoders + beam are drifting away, so closed loop operation would stabilize things... has to be commissioned, foreseen for Wednesday. Users start at Thursday...
  • A microscope got stuck on a limit switch. Probably the limit switches have to be rewired.
  • An encoder in loop 11 seems to be missing. EEE is on it...

SCS

  • Since Sunday there appears to be an issue with the in-vacuum sample stage. Is kind of urgent...

SQS

  • Last week: Commisioned the laser
  • This week: Users & night shift

MID

  • There is an issue with the hexapod, EEE is on it.
  • Chris is testing some cooling / heating using peltier elements.

HED

  • Train IDs are missing in loop 5 and 10. EEE is on it, too.

Optical lasers

VAC

XRO

XPD

  • There is probably an intervention in XTD1 to repair a camera for the self-seeding setup. Others might want to jump on the train. Time is not yet decided.

DET

EEE

CAS

  • Test for 2.6. are ongoing.

ITDM

SRP

TS

AoB

  79   14 Aug 2019, 10:01 Gerd WellenreutherGeneralInformationMinutes of the Technical integration meeting 14.08.2019

XO

  • On Monday at around 12:20 there was a power glitch at least in Hamburg, affecting the machine.
  • In this cause, the startup was delayed due to a missing signal from the Vacuum EPS-MPS-interface. The signal had to be manually enabled again.
  • Tuning is estimated to take until 14:00 today.
  • In the wake of such events a lot of communication about the machine status is happening. In the future, XO will ensure the readiness mailing list will be updated, too. In this respect, P. Gessler suggested to rethink / rename the multitude of mailing lists inherited from the construction phase.

FXE

  • There are concerns about the replacement of the simple motor with the MC2 library, in particular about whether all functionalities will still be available (e.g. step-up/down). According to EEE this should be okay. CAS has already release the new library for testing.

SPB/SFX

  • Hexapods are being integrated. ==> This was rescheduled due to the issues with hexapods at HED and MID. Currently, there is no dire need to integrate the SPB/SFX hexapod, it can be run from TwinCAT.

SCS

  • There is an issue with the main sample stage. SCS and SEC are working on it, will continue with commissioning the instrument.

SQS

  • Loop 14 will be updated today.

MID

  • DPS turbo pump issue. A software workaround exists. The problem is that the used controller has not been commissioned firmwarewise before. This is not a showstopper and wil be addressed later. ==> The cabling is done differently. EEE is testing the device + firmware.

HED

  • Loop 13 has been commissioned.

Optical lasers

VAC

XRO

  • There was an issue with a drift of the HED mirror. As a consequence, VAC and XRO have switched of the mirror cooling. HED and MID should report about the change of the situation.

XPD

  • During an intervention in XTD1 the LED for the Self-Seeding setup was replaced.

DET

EEE

CAS

  • 2.6.0. being prepared. ==> Sneak peak was deployed in SPB/SFX. Actual deployment datas can be found in the Shutdown planing, will be discussed in the chapters and with the SASE responsibles.

ITDM

SRP

  • The primary door of the HED experiment is currently not guarded with a magnet against incidential opening of the door leading to a trip of the machine. KWitt has to redo some cabling, until then, users can set the laser interlock, which will engage the magnet.

TS

  • Controller for the hexapod is currently in the MID control room. UBrueggmann should check the installation.

AoB

  • Please check the shutdown planning
  • No dispatch meeting on Friday.

  97   10 Feb 2020, 10:12 Frederik Wolff-FabrisGeneralInformationNotes Dispatch meeting Feb 10th, 2020
SPB:	Nothing to report;

FXE: 	Everything ongoing; nothing special to be reported;

MID:    Finalize motors of split and delay line; MID has to test interlock for vacuum loop update.

HED:	Commissioning of laser heat table. It may need assistance from EEE and CTRL during the week.

SCS:	Nothing to report - Last week's mounted setup will be disassembled in order to mount the standard setup for users;

EEE: 	OCD was called from XRO during beamline alignment of SA2: 1 BMPI motor had a problem and is under investigation - EEE reminds on the new homing position for 
negative direction motion.

CTRL: 	Following reset of train-ID and timing system for today.

XPD: 	Shifted Beam Pointing Studies from A. Koch to Tuesday. 

DET: 	Nothing to report

*machine is currently not running due to filter clean in the cold compressor. Shall be re-started this afternoon and by tomorrow must be lasing.
*Master time reset and train-ID reset this morning. Then EEE (check systems), followed by CTRL (karabo servers re-start) and ITDM (check DAQ operation). LAS and DET are 
informed.
*Wednesday: Network stress test with Cameras by CTRL on Wednesday 12:00-14:30.
  98   17 Feb 2020, 12:02 Frederik Wolff-FabrisGeneralInformationnotes Dipatch Meeting Feb. 17th, 2020
FXE:
Nothing to report: no issues;

MID:
Delay line pumping down; Connecting all devices in preparation to be ready for Friday;

EEE:
Finishing SQS interlock scenes and SPB loops;
ELMO parameters lost themselves (in connection to XRO/Maurizio request). Parameters to be checked this week and next shutdown;
XPD ticket to be checked;
Cabling shall be started for SQS/SCS: waiting for open hutch;

CTRL:
Ticket from XPD (shared EEE/CTRL): dry run did not work at BKR: missing pieces. 
Please instruments check the systems during the day prior Friday when the Test Run starts;
Request from CTRL/Chris: Define guidelines for the users/support on the ticketing and e-log (who has responsibilities to check devices?).

ITDM: 
Ticked from XPD/Liuba: it is a ticket with link (?) to E-log.


* Mc2 motors: XRO needs a list of all motors in order to check configurations. Example: SA3 MONO pre-mirrors with torque set to zero; SA3 exit 
slits with wrong settings.

* CTRL reminds the instruments to check devices during working hours prior Friday when the Test Run starts with beam delivery.
  101   10 Mar 2020, 12:44 Frederik Wolff-FabrisGeneralInformationnotes Dipatch Meeting March 9th, 2020
* Users are scheduled to be here this week (4 beamlines in user runs). SPB, HED, MID report several users have cancelled the travel. Beamlines are making mitigation plans 
to run experiments.

FXE:
- Setting up and working with detectors; Working with 4-bounds MONO; Von-Amos detector working;
- Jumps of beam position have been observed and have to be evaluated;
- Jungfrau detector crashed and DET was contacted;

SPB:
- Smooth run after new tuned up on Tuesday;
- Jump on beam position comes from mirrors;
- It was observed a change of number of bunches on Tuesday night: from 2 to 30 for example; XO comment: This time should be not considered as regular beam delivery and 
only parasitic use. Nevertheless, better information on what kind of changes the machine may perform during the shift can help for the future use of parasitic beam.
- AGIPB was successful; also preparation for users; Mitigated troubles with missing user;

SCS:
- Not present

SQS:
- Not present

HED:
- Solving issues with motors together with EEE last week;
- Hexapod vacuum feedthrough: missing flange has to be borrowed from another group  - still to be found;

MID:
- The Pump-probe laser test last week was very successful;
- Re-start of some devices was needed;
- For this week: reduction of user group from 11 to only 3 visitors. Beamtime is a continuation from last year's interrupted time due to the power outage. Local staff is 
mitigating missing users;

EEE:
- Nothing to report

CTRL:
- Nothing to report

ITDM: 
- Not present

VAC:
- Gas attenuator in SQS: not above 10.2 mbar - in investigation. A stress test has to be made and shall be agreed with BKR;

DET:
- Not present

LAS:
- Not present

XPD:
- Not present
  102   16 Mar 2020, 09:36 Frederik Wolff-FabrisGeneralInformationNotes Dipatch Meeting March 16th, 2020
FXE:
- Beamline is in safe state;
- Minor Jungfrau calibration issues over last week. In touch with DET and EEE;

SPB:
- Good exercise: experiment run with only 2 users. Successful beamtime with data taken: to be analysed by users;

MID:
- Successful beamtime with good beam conditions and data has been taken;
- Beamline is in safe state and most of staff is in telecommuting;

EEE:
- Start collecting a list of broad activities to take place in case of a long shutdown;
- No major issues to be fixed;

CTRL:
- Few cameras and detectors hiccups – e.g. DAQ re-start bring system back;
- Most of people will run from home office / telecommuting;
- Tests together with EEE/FXE still to be performed this week - to be scheduled;

DET:
- DET is placing a plan to warmed up detectors and be ready for shutdown;
- AGIPD, DSSC are already in safe mode;
  108   06 Apr 2020, 09:50 Frederik Wolff-FabrisGeneralInformationnotes Dipatch Meeting April 6th, 2020
CTRL:
- It was remotely observed that some cameras were consuming too much memory. By remotely re-starting these devices the issue was solved.  
- No calls to the OCD during the weekend.

EEE:
- No issues to report;
- Planning a meeting with Instruments/CTRL/DA to discuss long term tasks that have been working on during this reduced operation period.

VAC:
- Nothing to report; All running in good state.

XPD:
- Nothing to report.

DET:
- Nothing to report.

ITDM:
- Nothing to report.

XRO:
- After the recent power glitch: XRO has checked the basic parameters of special motors which presented problems in the past associated to power glitches;
- At this time, the main basic parameters remain OK (note that only few devices were checked - the ones which presented problems in the past);
- During the EuXFEL restart a deeper look on all devices has to be taken together with the instruments. 

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- Nothing to report.

	 
  111   20 Apr 2020, 10:59 Frederik Wolff-FabrisGeneralInformationNotes Dispatch Meeting 20.04.2020
General:
- Desy informed a power glitch occurred on Thursday 16th at 04:55AM. TS has not seen any traces of it in the EuXFEL internal GLT.
- From next week the Dispatch meeting will start at 09:30AM.
- An additional Friday's Integration Meeting will happen at 11:30AM. Proper information and invitation will be send soon.

CTRL:
- The notification service for the reduced operation mode is ready for start-up and an e-mail will be send around with instructions. 
- Groups/staff will be requested to subscribe to the lists.
- Training will be conducted on next Wednesday at 15:00 and/or next week. One member of each group is required to attend it.

DA:
- Nothing to report. Working busily from home.

EEE:
- No issues to report

VAC:
- Two pumps located in a gas attenuator were OFF due to the power glitch of last Thursday 16/04 at 04:55AM.

XPD
- No issues related to the power glitch were observed.
- XPD has received devices and they were successfully stored in vacuum / clean rooms. Another devices shall arrive this week.

DET:
- Nothing to report.

ITDM:
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Not present.

SPB:
- Nothing to report.

FXE:
- Not present.

MID:
- Everything is fine.

HED:
- All is fine, all is running.

SCS:
- Not present.

SQS:
- Not present.
  112   23 Apr 2020, 10:04 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 22.04.2020
General Announcement:
- An e-mail was sent yesterday about the relaxation of restrictions on the control network.
- From now on, the XO integration meeting series will happen on Monday and Wednesday at 09:30 and Friday at 11:30.
- These meetings serve two purposes: 1.exchange of information for the re-start phase, and 2. Controls issues. 
- This procedure is set to help the re-start of activities coming from the super-restricted operation mode.
- Groups are asked to send by every Friday to controls-integration@xfel.eu a summary of activities to be carried out during the following week regarding the Control 
Network. 
This helps CTRL and XO to prepare and coordinate the full scope of activities while having an overview on actions that require large scale resources.
- For example, groups and staff who move motors have to be cautious, once reduced number of people will have access to debug devices in case they get stuck.
- This process could be reviewed in the course of next weeks. 

CTRL:
- Training for the Notification service: half of the groups have delegate people to attend it. Other groups please do so at the distributed Doodle link.

DA:
- Request that groups should inform DATA if people on site are required from next week.

EEE:
- Nothing major to report on micro-TCA and technical side.
- Cablings are ready to be installed when allowed to.

VAC:
- Preparing for the start-up.

XPD:
- Preparing for start-up.

DET:
- Same as VAC and XPD.

ITDM: 
- Preparing for start-up.

XRO:
- Nothing to report.

LAS:
- Work together with Desy last week.
- It is planned to test the laser pattern synchronization on next week if possible. 
An e-mail has to be send to controls-integration@xfel.eu with this request prior Friday 11:30AM XO Integration meeting.

SPB:
- Nothing to report.

FXE:
- Not present.

MID:
- Planning the re-start steps for May 4th.
- MID reminds that at least one person from the Safety groups shall attend this series of meetings.

HED:
- Not present.

SCS:
- Nothing to report.

SQS:
- Not present.
  113   24 Apr 2020, 13:48 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 24.04.2020
Relaxation control network: 
- CTRL and XO remind the groups to submit the planned activities on e.g. scenes, projects, until Fridays. 
- For next week case: please limit any hardware change. Reason is the current limitation on the physical presence of staff. 
Groups will support only emergency and priority tasks. From May 4th the situation will be different. 
- However, we do not want to stop any progress on activities. This also includes work on Karabo that affects critical work like VAC in tunnels.

Tunnel access for the coming weeks:
- A scheduling plan will be made due to the restrictions of allowed people working on tunnel at the same time. 
Plan will be made in order to respect safety rules and minimize number of people working in tunnels. 
- Tunnel access will be a first agenda point from next week.

General:
- For next meetings, we will continue with the small report from the support and instrument groups.
- Tasks to happen in the hutches are decided by the groups. XO/PMO plan tasks in tunnels.
- We encourage groups to start as earlier as May 4th the tasks which were originally planned to be conducted during the summer shutdown. 
If it needs tunnel access, then one must respect the coming schedule.
- XO is looking together with Desy on all tunnel activities. A schedule is being prepared and will be communicated to the groups as soon as possible. 
- In case of delay of activities due to e.g. excess of people in tunnel, prioritization will be made together with XO and Desy.
  114   28 Apr 2020, 16:19 Frederik Wolff-FabrisGeneralInformationNotes XO Integration meeting 27.04.2020
General Announcement:
- The CTRL group has received 3 Control Network tasks that can be carried out this week;
- Requests from the groups to Tunnel activities from May 4th are being treated and an answer will come in the next couple of days. 
- With respect to Re-start activities XO/XML has 17 group submissions. We thank the groups to submit them. We have not spotted conflicts so far.
- In case of need to contact staff, please use the working mobiles, emergency phone list or group's mailing lists to address any issue.

CTRL:
- First training on the notification service with 5-6 people. Next training is scheduled for today.

DA:
- All good, doing progress without conflicts.

EEE:
- Nothing special; Group is working on the submission of tasks, to prioritize and make schedule for next week. 
- The group is requested to inform XO in case you have re-start tasks needed to be performed in tunnel.
- An electrical safety person will be provided on site by EEE to serve the instruments from next week. EEE is clarifying and shall respect the safety rules. 

VAC:
- Nothing special. Assembling for the tasks that can be done in tunnel. Also CTRL is involved. Progressing normally.

XPD:
- We have submitted the tasks and looking forward to coordinate with VAC, XRO, EEE to plan the tunnels tasks. 

DET:
- Same as XPD.

ITDM: 
- Nothing to report.

XRO:
- We sent re-start task list. The main problem is to evaluate what work can be done due to safety regulations in the case of complex installations.

LAS:
- We are preparing to switch SA1 on beginning of next week and other lasers will follow during the next week (PP and lab lasers). 
- SA2 may delay due to the needed presence of external company.

SPB:
- Nothing special to report; The group believes it has no activities in the tunnel;

FXE:
- Similar when compared to SPB;

MID:
- Preparing the start-up;

HED:
- Preparing for the start-up.
- HED will need people to switch on electric components on the racks.

SCS:
- Nothing special to report.

SQS:
- Nothing special to report. We are ramping up the vacuum system.