Minutes of the Technical integration meeting 30.01.19 , posted by Adriano Violante on 30 Jan 2019, 11:26
|
SPB/SFX
Planned for the next 2 weeks
AGIPD commissioning and tests. DET group heavily involved.
Screens are being installed
and commisisoned in the hutch.
CSS component commissioning. AE involved and informed.
Loop 14 (Jungfrau) is needed for next week |
Report after dispatch meeting 09.00, posted by Adriano Violante on 01 Feb 2019, 12:49
|
SPB/SFX
Open AGIPD wing. Next 3 days are needed for fixing purposes.
FXE
SQS |
Report after dispatch meeting 09.30, posted by Adriano Violante on 04 Feb 2019, 10:17
|
SPB/SFX
Waiting for the loop 12 to be running to start the commissioning of Jungfrau. Some cables for th fus boxes missing. Also IT cables are
being mesaured.
CSS motion. Discussions ongoing to fix it.
FXE |
Minutes of the Technical integration meeting 06.02.19 , posted by Adriano Violante on 06 Feb 2019, 11:13
|
SPB/SFX
AGIPD commissioning and tests. ==> intervention on the wings is ongoing.
CSS component commissioning. RBean is discussing
with AE. By the end of the week the changes could be implemented.
Loop 14 (Jungfrau) is needed for next week to start the commissioning. AE |
Report after dispatch meeting 09.00, posted by Adriano Violante on 08 Feb 2019, 10:42
|
SPB/SFX
IT cables in D.23 were re-measured yesterday. Waiting for the measurements. PSPO pushes the company.
FXE
SQS |
MInutes of the dispatch meeting 09.30, posted by Adriano Violante on 11 Feb 2019, 09:59
|
SPB/SFX
Beam is back on Wed. night.
IT cables in D.23 were re-measured on friday. Probemessung was OK. Waiting for the complete set
of measurements. PSPO pushes the company.
Updates+testing of the AGIPD with the CFEL experts is ongoing.
interlock definitions |
Minutes of the Technical integration meeting 13.02.19 , posted by Adriano Violante on 13 Feb 2019, 10:59
|
SPB/SFX
CSS component commissioning. RBean is discussing with AE. Concept and implementation being finalized.
Loop 14 (Jungfrau) is
needed for next week to start the commissioning. IT Cables have been accepted after new measurements. Loop can be switched on.
Issue about parallel |
Report after dispatch meeting 09.00, posted by Adriano Violante on 15 Feb 2019, 12:14
|
SPB/SFX
SPB requires the new trigger solution to be implemented for AGIPD. This is urgent and should be done before the next run. SHauf
has to check in the DET group whether this can be pushed also wil Jola coming back only next week. ==> done and seems to work
Commissioning |
Minutes of the dispatch meeting 09.30, posted by Adriano Violante on 18 Feb 2019, 10:09
|
SPB/SFX
Data aggregators were often crashing during the WE and needed to be re initialized.
Puls picker commissiong - Scan tool was
used and worked. Issues concerning motors position and triggers ==> To be worked out with AE.
DET group is helping setting up the Jungfrau |
Minutes of the Technical integration meeting 20.02.19 , posted by Adriano Violante on 20 Feb 2019, 11:16
|
SPB/SFX
CSS component commissioning. Concept and implementation being finalized.==> Final tests have to be performed at SPB, if OK, the CR
will be finalized.
Loop 14 (Jungfrau) commissionig has started. 3 modules are being controlled. The movable stage should have been shipped from |
MInutes of the dispatch meeting 09.00, posted by Adriano Violante on 22 Feb 2019, 12:36
|
SPB/SFX
Pulse picker commissiong - Issues concerning motors position and triggers ==> To be worked out with AE, but beam is needed. Has to
be done.
DET group is helping setting up the Jungfrau detector (w/o PLC).
DAQ performance test performed yesterday.
Trigger |
Minutes of the dispatch meeting 09.30, posted by Adriano Violante on 25 Feb 2019, 09:52
|
SPB/SFX
Change to the triggers for cameras is being discussed/implemented with BF.
Preparation for the AGIPD intervention planned
in the next mini shutdown is being discussed with AE.
On Wednesday the user period start. No more commissioning possible.
FXE |
Minutes of the Technical integration meeting 27.02.19 , posted by Adriano Violante on 27 Feb 2019, 11:27
|
SPB/SFX
CSS component commissioning. Concept and implementation finalized. EPLAN is being modified. PLC modification will follow.
Loop
14 (Jungfrau) commissionig is ongoing. Issues concerning the simultaneous operation of more modules. SPB and DET on it. The detector is needed functional |
Report after dispatch meeting 09.00, posted by Adriano Violante on 01 Mar 2019, 14:18
|
SPB/SFX
Today Loop 8 could be ready (AE)
Agipd - visualization of data shows variable rep rate... correlations to be investigated.
FXE
SQS |
Minutes of the dispatch meeting 09.30, posted by Adriano Violante on 04 Mar 2019, 10:38
|
SPB/SFX
Ongoing discussions with the support groups to organize the shutdown activities.Update of the shutdown task list could eventually be
provided.
X-Ray interlock system had issues in the WE and needed to be re set. Not clear why this happened.
Problem with Karabo freezing. |
Minutes of the Technical integration meeting 06.03.19 , posted by Adriano Violante on 06 Mar 2019, 10:31
|
SPB/SFX
CSS component commissioning. Concept and implementation finalized. EPLAN has been modified. PLC modification has to follow.
Issues
concerning the simultaneous operation of more Jungfrau detector modules has been solved. Additional tests ongoing.
CRL implementation |
Minutes of the dispatch meeting 09.00, posted by Adriano Violante on 08 Mar 2019, 13:01
|
SPB/SFX
Only minor issues being addressed with the support groups.
FXE
SQS |
Status report after dispatch meeting 09.30, posted by Adriano Violante on 11 Mar 2019, 11:58
|
SPB/SFX
Experiments were succesfull
Calibration pipeline has issues - being fixed
Detailed planning of the shutdown works
is being done with AE to see whether some activities can be done before or after the critical week
JGFR calibration pipeline needed. SH will |
Minutes of the Technical integration meeting 13.03.19 , posted by Adriano Violante on 13 Mar 2019, 11:11
|
SPB/SFX
CRL implementation in the hutch will happen in April. AE and EET involved. ==> ZA needs the documentation of the CRL. The point is
SRP to be able to evaluate the focusing properties to give beam permission after installation. TH will ask directly PVagovic. Still pending since PV is |
Minutes after dispatch meeting 09.00, posted by Adriano Violante on 15 Mar 2019, 11:27
|
SPB/SFX
No major issues reported
Motors in Loop 14 have been tested and problems with the motion sign and encoder were found. AE/EET
on it.
FXE |