Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 14
Entry time: 01 Mar 2019, 14:18
|
Author: |
Adriano Violante |
Location: |
General |
Severity: |
Information |
Subject: |
Report after dispatch meeting 09.00 |
|
|
SPB/SFX
- Today Loop 8 could be ready (AE)
- Agipd - visualization of data shows variable rep rate... correlations to be investigated.
FXE
SQS
SCS
MID
- Fast diodes needed on the WE. HW and Software support required and ongoing.
- CY called for a meeting on monday to collect all the requirements for the epix det to work. The det will be then tested in the common lase room. Karabo interface change is required. It will take 3 weeks.
- VAC interlock test in MID OPT to be performed. Marjian can support.
HED
- Si(111) mono commissionig ongoing
- VAC componennt in HED OPT being setup by KS
- Digitizers for diodes being used.
OPT Lasers
XRO
XPD
VAC
AE
- Timing update on monday in SASE2. BF sent an email to readiness with the details.
ITDM
DET
EET
CAS
- Test Karabo 2.4.0. ongoing. List of PLCs AE==>CAS.
- Problem with a solid attenuator valve in XTD1. Not enough air pressure to operate the valve properly. DFM(CAS) will contact XRO.
AoB
CAS and AE point out that there are many activities planned for the next shutdown and as soon as PSPO will issue the shutdown tasklist planning most probably priorities will need to be set by TT/ MGMT |