Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 6     Entry time: 11 Feb 2019, 09:59
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: MInutes of the dispatch meeting 09.30 

SPB/SFX

  • Beam is back on Wed. night.
  • IT cables in D.23 were re-measured on friday. Probemessung was OK. Waiting for the complete set of measurements. PSPO pushes the company.
  • Updates+testing of the AGIPD with the CFEL experts is ongoing.
  • interlock definitions were updated.

FXE

  • Last Thursday an alarm signal was heard from the control room and only entering the hutch it was realized that an additional radiation sensor was triggered, maybe due to a spike. The procedure and actual usefulness of the device should be commented on by SRP.
  • An additional beamstop will be installed otday in the hutch. This requires to OGT3 to be moved.
  • Performance issue with the digitizers when all 3 of them are used in parallel. AE on it.

SQS

SCS

  • Beam is back on Wed. night.
  • Today Loop 7 and 9 will be updated. Loop 7 includes the fast ccd motors and will be tested after update.
  • Smaract stages have to be tested with AE (today/tomorrow)

MID

  • Marjan is supporting the commissioning of components in the hutch.
  • Loop11 is probably already containing all the required components. JH will send a confirmation email to NJ today.

HED

  • Problems with the HV ion pump cables in the HED optics. Many of the cables failed the final test and showed sparks. KS, EET are in contact with Fa. Schulz to solve that. It is not clear whether this is a showstopper or the pumps could be operated locally.==> Fa Schulz will fix the connectors on site.
  • Loop1 is being commissioned (Gauges and gate vales are included)

OPT Lasers

XRO

​​XPD

VAC

AE

  • DESY is restarting the timing serve today at 11am. This will not affect the train ID. 
  • No feedback concerning the additional B4C controls in SASE3. Waiting...
  • Material for the trigger boxes is available at AE

ITDM

  • Issue with the DAQ was discovered (cameras/digitizers): problems occur when more than 1 camera is using the same data aggregator. Investigation and fix is ongoing. DAQ will need to be re deployed only for these aggregators between today and tomorrow. Tunnels and instruments affected. AGIPD is not affected.  

DET

  • Test of the Jungfrau foressen for tomorrow at SPB, for the end of the week for FXE. SCS fast CCD also needed asap.
  • online preview feature was deploted for SPB. FXE next week.

EET

CAS

  • Yesterday OCD was called by JG because of some problems with the data sources. This was found to be a configuration problem. Going to be fixed today.
  • CRL in XTD1 2 lenses are disconnected. They do not nmeed to be included in the Karabo scene.

AoB