Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 6 of 29  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 21 Mar 2018, 10:02 
SPB

On monday there was an issue with a detector related PLC due to misconnection of one EtherCAT cable. The issue has been solved and it "just"
resulted in 3 of hours delay in  the AGIPD calibration activity.
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 19 Mar 2018, 10:24 
No new issues to be discussed where reported by any groups.

The status and issues reported on friday are still valid. 
Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting 16.03.., posted by Adriano Violante on 19 Mar 2018, 08:42 
Photon Run Coordinator (H. Sinn):

1.) SASE1: User experiment SPB could be finished sucussfully after several problems on the weekend (thank to FXE for providing night shift). Big
progress in improving throughput of FXE insrument. Next D3 material test with 300 bunches on April 3, 9am. 
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 14 Mar 2018, 10:06 
SPB (Weinhausen/Round/Mancuso):


Again on the fast valve was triggering the MPS interlock system. For XRO was not completely clear what happened. for AE everything
is clear and it depends on the wrong MPS configuration with respect to missingl cables. The will discuss this offline and eventually bring back the issue.
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 12 Mar 2018, 13:18 
SPB (Weinhausen):


During the night there was an interlock issue. The fast shutter was triggering the MPS interlock system. After several calls and request
of support from SPB to the photon run coordinator and the machine run coordinator the problem was found and the interlock signal bypassed. This was due
Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting 09.03, posted by Adriano Violante on 12 Mar 2018, 08:18 
Photon Run Coordinator (L. Samoylova):


Commissioning during machine studies Tue and Wed and parasitically
during SA1 user operation at 
 SASE3 on Thursday and Friday 

SASE1

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 07 Mar 2018, 11:14 
SPB:


Monday morning Karabo failed. It was not possible to operate anything. Aftrer restart it took 2 hrs. to have the tunnel loop and Lopp
5 again operable . Other issues connected to that. CAS is on it.
AGIPD can be operated with some workaroung concerning the control system. No
Entry   Details on SPB issues reported in the dispatch meetings, posted by Adriano Violante on 05 Mar 2018, 16:37 
Below some clarifications from R. Bean on the issues reported in today's dispatch meeting:

 

- AGIPD suffered many problems which affected the operability (not really a problem of the scene). It was just operable, although not at all
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 05 Mar 2018, 11:07 
 

SPB


Last night the beam disappeared between 4 and 8. 
AGIPD scene showed many problems, both concerning Karabo and Data preview.
Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting 02.03., posted by Adriano Violante on 02 Mar 2018, 14:36 
Photon Run Coordinator (N. G. Kujala):


SASE1


Machine
delivery 300 pulses upto XTD2 without M1 mirror in beam on Wednesday evening.
On
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 28 Feb 2018, 10:55 
SPB:


Ion pumps running in the Mirror chamber. Vacuum level OK to run.
D.02 is now interlocked and is a clean area.
Mahadi
and Alessandro are setting up a test system for the coupled movement. The test will probably be done between the 2 users periods.
2 hours of
Entry   Status report after dispatch meeting 26.02, posted by Monica Aresté on 26 Feb 2018, 12:09 
SPB:


Ion pumps running in the Mirror chamber.
Starting test with mirrors together with CAS this week.
In general everything
in good position to receive beam.
Primary limits for coupled motion not included in E-plan, safety switches are implemented but SPB prefers to
Entry   Status and plans after Readiness Meeting 23.02. , posted by Gerd Wellenreuther on 23 Feb 2018, 15:54 
Photon Run Coordinator (L. Samoylova):


SASE1 tuning is ongoing (350 microJ)
SASE3 3000microJ
SASE1 interlocks enabled, SASE3 only vacuum interlock enabled
Soft
monochromator is being commissioned
K-mono studies were carried out
HiRex was being commissioned
SASE1 and SASE3 DAQ was
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 21 Feb 2018, 10:55 
SPB


KB chamber being pumped down
Smaract commissioning ongoing
Coordinate motion for VAC ready to be tested (probably
tomorrow). It has to be agreed with Richard Bean
Clean-up slits Karabo middle layer deployed and working. - The same hase to be done for
    Reply   Re: Status report after dispatch meeting 09.30, posted by Alessandro Silenzi on 21 Feb 2018, 13:49 
Small correction:

The coordinated motion is the KB-mirror's, not the Vacuum.

The postfix is 2.2.2.1 and includes features that were not included in 2.2.2
Entry   FXE Beam Shutter Key, posted by Eric Boyd on 20 Feb 2018, 12:29 
The FXE beamshutter key has been installed into the interlock system after satisfactory completion of the FXE Chicane and Radiation Protection Sticker
Checklist. The FXE Experiment hutch is now ready to receive xfel beam as required by the FXE instrument group.

However, the bunch mode MUST be limited to 1 or 2 bunches until the new user chicane is tested with thirty bunches using the copper target. This
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 19 Feb 2018, 09:56 
SPB




KB chamber being pumped down


interaction with AE is ognoing concerning update pf Loop 5 and AGIPD cooling
procedure ongoing
Smaract commissioning ongoing
The goal is to be ready to start commissioning with beam on 01.03.
Slit
Entry   CAS OCD, posted by Jan Grünert on 18 Feb 2018, 17:20 
Here is a information from Sandor on CAS OCD Numbers
(this info is copied from the SASE1 commissioning logbook): 

during the day: 98053   (8:00 - 16:00)
Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting 16.02., posted by Adriano Violante on 16 Feb 2018, 15:44 
Photon Run Coordinator Report to Readiness Meeting

The maintainance on Wednesday was very successful and all goals were reached (and some extras). 

Thanks to everybody involved in planning and execution! 
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 14 Feb 2018, 14:21 
SPB


MIddle layer karabo devices are responsible for the det. Karabo problems. Issue being addressed.
2 mirrors in D.02 installed.
Test
of the mirrors movements is done.
Mirrors cooling bars being installed


Vacuum
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 12 Feb 2018, 10:03 
SPB


During operation Karabo crashed. As soon as detector is being operated the problem appears. Fixing is still ongoing.
2 mirrors
in D.02 are being installed.
Test of the mirrors movements has been performed.


FXE