Status report after dispatch meeting 09.30, posted by Adriano Violante on 29 Aug 2018, 10:01
|
SPB
New users run starting on Thursday. All set.
Discussions on image processors and scan tool with CAS were held. Ongoing.
Smaract
stages issue. After the installation of a wall connection box by SPB only 2 axes out of 10 work. That's not an issue for the next users run but for |
SASE3 loops will restarted at 11:30, posted by Alessandro Silenzi on 28 Aug 2018, 11:19
|
This announcement is to notify you that the intervention planned to configure the interlocks as read-only will be carried out at 11:30.
A following message will notify of the end of the intervention
Alessandro |
Re: SASE3 loops will restarted at 11:30, posted by Alessandro Silenzi on 28 Aug 2018, 11:36
|
Alessandro
Silenzi wrote:
This announcement is to notify you that the intervention planned |
Status report after dispatch meeting 09.30, posted by Adriano Violante on 27 Aug 2018, 09:57
|
SASE3 general
Deployment of the new interlock definitions will be done in the next 2 days. Final test foreseen for Thursday.
SPB
Users collecting data. Problems of clogging of the sample injection, this could result in empty image files. Wil be checked by the users..
AE |
Status report after dispatch meeting 09.30, posted by Adriano Violante on 22 Aug 2018, 10:08
|
SASE3 general
Interlock definitions for the tunnels: today a meeting with AE/HSInn/CAS will take place at 14:00 to continue the discussion.PGessler
pointed out that one has to make sure to implement a concept which is also OK with D3 to avoid wasting time. The common understanding is that HSinn is |
Status report after dispatch meeting 09.30, posted by Adriano Violante on 20 Aug 2018, 11:46
|
SASE3
If the bender of the M2 mirror is used the beam can be focused on the shutter and caouse damaged. This is a safety relevant issue that
prevents SASE3 from getting beam. Interlock definitions related to the gas attenuator are being discussed to overcome the problem.
SQS |
Status report after dispatch meeting 09.30, posted by Adriano Violante on 30 Jul 2018, 10:42
|
SPB
Middle layer for coordinated motion is being reifned.
Request to have the pulse picker ready asap as it is required for user
period. AE working on that,
Scan tool has to be stested. CAS required.
|
Status report after dispatch meeting 09.30, posted by Adriano Violante on 25 Jul 2018, 10:01
|
SPB
Interaction region cabling being reworked. By the end of the week shoud be done.
For the 1st week of operation the Pulse Picker
has to be ready - on a good track.
For the 1st week of operation the coordinated motion and the Peltier system has to be integrated in |
Status report after dispatch meeting 13:00, posted by Adriano Violante on 23 Jul 2018, 13:45
|
SPB
Controls for the pulse picker being prepared. High priority for SPB
Coordinated motion tests ongoing. High priority.
ATT
motors need to be re checked in XTD9. The closing dates for the tunnels are not known excactly. SPB should phone BKR for the last information
SQS |
Status report after dispatch meeting 13:00, posted by Adriano Violante on 18 Jul 2018, 13:51
|
CAS
3 MID CRL motors in XTD6 need to be repaired. The work is being planned and the clean tent is being prepared.
|
Status report after dispatch meeting 13:00, posted by Adriano Violante on 16 Jul 2018, 14:18
|
SPB
Mirrors installed. Lid closed. Las vacuum connection will be closed today. Then the electronics can be connected.
Mock
up pulse picker system ready
Some crates in the tunnels will be switched on today after updates of the interlock definitions to be ready for |
Status report after dispatch meeting 13:00, posted by Adriano Violante on 12 Jul 2018, 08:11
|
SPB
Mirrors being installed. Tests continue. Karabo updated.
AE
Works in the tunnels SASE3 and 2 continue
Works on the SASE3 experiment preparation continue
General |
Karabo 2.2.4 released (mainly for ITDM, AE and DET) + Deployment dates, posted by Hugo Silva Santos on 25 Jun 2018, 09:45
|
Dear All,
I would like to inform that we released last Friday (22.06) the Karabo 2.2.4 version. We got around five days delayed to prioritize issues
regarding Karabo-DAQ integration and MDL devices that were found in the last steps of the test cycle. However, fortunately, those issues are solved. |
Re: Karabo 2.2.4 released (mainly for ITDM, AE and DET) + Deployment dates, posted by Hugo Silva Santos on 10 Jul 2018, 11:23
|
Dear All,
Please, see below the updates regarding Karabo 2.2.4.1 deployment:
SA3: 05.07, Thursday (references: Chris, Wajid, and Valerii) - Done
SA2: |
Status report after dispatch meeting 13:00, posted by Adriano Violante on 09 Jul 2018, 14:32
|
SPB
Mirrors installatiostarting now. Preliminary motion tests conducted last friday were successful. Still closed loop for encoders signal
has to be implemented. AE will work on that.
AGIPD firmware updated. Remaining tests ongoing. New Karabo release will be deployed tomorrow.
Peltiers |
Status report after dispatch meeting 13:00, posted by Adriano Violante on 04 Jul 2018, 14:47
|
SPB
Mirrors installation ongoing. Lid is open. Movements are being locally tested. Test of synch. motion with PLC to happen likely tomorrow.
AGIPD
firmware being updated. On friday all the tests should be finished and on Monday the deployment of Karabo 2.2.4. could happen.
AE |
Status report after dispatch meeting 13:00, posted by Adriano Violante on 02 Jul 2018, 14:03
|
Info about tunnels accessibility
concening the XTD10 + XTD2 situation:
According to my information these two tunnels should be open and will be closed tomorrow at 15:00. |
Status of the power in SASE1 - Update, posted by Adriano Violante on 28 Jun 2018, 15:08
|
Dear colleagues
electrical power to SASE1 rooms, except FXE-experimental hutch OUTLETS, is |
Status report after dispatch meeting 13:00, posted by Adriano Violante on 27 Jun 2018, 14:55
|
SPB
Electronic and instrumentation will remain OFF until the electricity comes back tomorrow (will be announced by TS on the logbook)
MIrrors
installation will start next week
Mirrors movement test to happen, then Loop 4 and 1 to be updated
In order to make the calibration |
Status report after dispatch meeting 13:00, posted by Adriano Violante on 25 Jun 2018, 13:34
|
SPB
The power shutdown has been delayed to tomorrow and power is supposed to come back on Thursday at 12:00. Torsten Schen will send an E-mail
to readiness when the power comes back on Thursday.
Pumps are in a safe state since they currently get external power.
AE |
Status report after dispatch meeting 13:00, posted by Adriano Violante on 20 Jun 2018, 14:12
|
SASE1 Experiments
Due to the interlock PLCs reprogramming, the emergency off circuit will be triggered tomorrow and power cuts will occur. Due to that, the AGIPD
in SPB is being put into a safety state. ITDM and AE are informed. FXE and Optical lasers were also informed. The order is: Experiment in a safe |
Status report after dispatch meeting 09.30, posted by Adriano Violante on 18 Jun 2018, 15:42
|
SCS
Tests continue - List of issues sent to AE. Bernard will take care of that as soon as he's back.
SQS
Issues with KB motors (ELMO) reported and will be addressed by AE. Also the list was sent to BB.
Loop 4 is not up yet. |