Group Selection Page HELP Controls Group ITDM WP76 DET Vacuum EEE WP78 FXE SPB HED SQS SXP Sample Environment Operation PSPO XO TS Migrated2Zulip MigratedByGroup
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 14 of 30  Not logged in ELOG logo
Entry   Status and plans after SASE1 Readiness Meeting, posted by Tobias Haas on 28 Apr 2017, 13:08 
 Tunnel Status (T. Haas):

    Tunnels XTD2/4/10 were interlocked yesterday afternoon
    Beam is already going through the T2 and T4 beam lines to T4D

   XTD9 remains open until approximately 15 May

Vacuum (J. Eidam, R. Villanueva):
Entry   Status and plans after SASE1 Readiness Meeting, posted by Tobias Haas on 12 May 2017, 13:33 AttendanceS1R120517.pdf
Focus of meeting is on SASE1 Instruments, Laser and Detectors
SPB (B. Weinhausen)

    All motors in the SPB tunnel loop have been commissioned except for one TECHNOSOFT motor where the updated driver was not yet available
Entry   Status and plans after SASE1 Readiness Meeting, posted by Tobias Haas on 19 May 2017, 11:30 
General (T. Haas)

    Due to problems with interlock cabling the approval date with the TÜV on 1 June has been cancelled
    The MB, SASE1
Instruments, AE, CAS  and PSPO met yesterday and agreed that in view of the schedule risks with technical commissioning the focus of the next weeks
Entry   Status and plans after SASE1 Readiness Meeting, posted by Tobias Haas on 02 Jun 2017, 13:01 
General

    Due to the water incident in the hall commissioning activities are somewhat delayed
    Next week 2 technicians from Actemium/Jovo
arrive and shall fix damaged connectors, disassemble a subset of connectors and test all cables
    Detailed planning for the repair and testing
Entry   Status and plans after SASE1 Readiness Meeting, posted by Tobias Haas on 07 Jun 2017, 11:43 
 General

    Technicians from Actemium/JOWO arrived and
found that a lot more connectors than originally estimated need to be replaced
    Tests are finished in SPB Optics (40 connectors to be replaced)
Entry   Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 09 Jun 2017, 12:41 







Normal
0


21


false
false
false
Entry   Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 12 Jun 2017, 10:55 
Tunnel's schedule:


    Monday 12th June:  XTD10 closed, XTD9 open
Entry   Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 14 Jun 2017, 10:57 




General:




Entry   Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 16 Jun 2017, 10:18 Radiation_Measurments_for_Commissioning.pptx20170615-Components-Detectors.xlsx

 
  
 

 
  Normal
  0
  
  
  21

 
  
  false
  false
Entry   Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 19 Jun 2017, 10:17 
XTDs:


There are no major issues, commissioning works smoothly
this weekend.


Entry   Status and plans after SASE1 Readiness Meeting, posted by Tobias Haas on 23 Jun 2017, 11:11 




General


A low intensity beam is being put into the SASE1 intrument hutches in this order: SPB Optics, FXE Instrument, SPB Instrument
No
special precautions outside the hutches are needed due to the low intensity. 
The work will most likely not finish today. If necessary
Entry   Status and plans after SASE1 Readiness Meeting, posted by Tobias Haas on 30 Jun 2017, 11:33 
Data Acquisition and Data Archiving


K. Wrona summarised the basic ingredients of the system.
All components are ready and tested individually
Integration
in the instrument environment is needed and will be done first in the context of commissioning LPD in FXE starting from 5 July
DAQ and archiving
Entry   Status and plans after SASE 1/3 Readiness Meeting, posted by Frederike Wittmaack on 24 Jul 2017, 10:07 
General (T. Tschentscher/G. Wellenreuther)


Further tuning of the machine might require some time which was initially dedicated to photon/experiment commissioning.
Since
Harald Sinn will be on vacation: If you need any kind of access please address T. Tschentscher or M. Dommach. TT will organize coordination of groups requiring
Entry   Status and plans after SASE 1/3 Readiness Meeting, posted by Frederike Wittmaack on 28 Jul 2017, 11:50 
General



The radiation test in SASE1 could not take place yesterday since the machine was not able to deliver proper light intensity with
30 bunches. Another tentative is happening now.
Entry   Status and plans after Readiness meeting, posted by Monica Aresté on 10 Jan 2018, 13:22 
PSPO:

- G.Wellenreuther inform that MKK is planning to test the Umschaltautomatik, this will affect XHE1, XHE3, XHPSC, XHEXP, XHVAC. Oleg Engelmann
will send a mail with detailed information.
Entry   Status and plans after Readiness Meeting 23.02. , posted by Gerd Wellenreuther on 23 Feb 2018, 15:54 
Photon Run Coordinator (L. Samoylova):


SASE1 tuning is ongoing (350 microJ)
SASE3 3000microJ
SASE1 interlocks enabled, SASE3 only vacuum interlock enabled
Soft
monochromator is being commissioned
K-mono studies were carried out
HiRex was being commissioned
SASE1 and SASE3 DAQ was
Entry   Status and plans after Readiness Meeting, posted by Gerd Wellenreuther on 29 Sep 2017, 10:43 
SPB (A. Mancuso): 

 

​Users are in good shape
Beam operation with ca. 600 microJ, but beam seems to be ring-shaped
after M2?
Preparing for first pump&probe experiments in November.
Start of the focussing mirror controls should start after the
Entry   Status and plans after Readiness Meeting, posted by Monica Aresté on 04 Oct 2017, 12:10 Shut_down_task_list.xlsx
General:

Reminder to all the groups to provide the shutdown task list today afternoon to PSPO. Find template attached.

SPB:
Entry   Status and plans after Readiness Meeting, posted by Gerd Wellenreuther on 06 Oct 2017, 11:15 
SPB (B. Weinhausen): 


​Users took good data
Problems occured with the DAQ / control system
Working on diamond
@ beamstop
Preparation for several updates / activities regarding AGIPD


FXE (A. Galler):
Entry   Status and plans after Readiness Meeting, posted by Gerd Wellenreuther on 18 Dec 2017, 10:48 
PSPO:


M. Areste presented a report about the progress so far achieved in the shutdown (see Indico for details).
Most tasks are ongoing,
on schedule.
Few still have to be scheduled, mostly because support groups wait for feedback.
C. Youngman does detailed coordination
ELOG V3.1.4-7c3fd00