Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 61
Entry time: 28 Jun 2019, 11:25
|
Author: |
Adriano Violante |
Location: |
General |
Severity: |
Information |
Subject: |
Status report after dispatch meeting 09.00 |
|
|
XO
FXE
SPB/SFX
- AGIPD: Modules OK. Additional tests with data acquisition planned for next week
- AGIPD: Online preview of the modules position will be implemented next week when AS is back.
SCS
SQS
MID
HED
- Works in the tunnels will resume after the end of the interlock tests.
- Commissioning of the Loop 8 is ongoing.
- It is pointed out that the access to the tunnels is not managed in a transparent way and is difficult to get reliable information. AV will bring the concern to the XO and DOB.
Optical lasers
VAC
XRO
XPD
DET
EEE
- The issues with the encorder of the quadrant motion motors are caused by the fact that the encoder cables are too long (30m until the drag chain + 30 m in the drag chain). Right now a workaround exists (cable ground connected to the general ground). Final solution has to be found.
- MPS Box for timing. Some Cpus have to be reboot. No timing problems are expected. In case, BF will send an e mail to readiness.
CAS
- 2.5.0 will be deployed in the tunnels starting from next week
ITDM
SRP
TS
AoB |