Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 61     Entry time: 28 Jun 2019, 11:25
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Status report after dispatch meeting 09.00 

XO

FXE

SPB/SFX

  • AGIPD: Modules OK. Additional tests with data acquisition planned for next week
  • AGIPD: Online preview of the modules position will be implemented next week when AS is back.

SCS

SQS

MID

HED

  • Works in the tunnels will resume after the end of the interlock tests. 
  • Commissioning of the Loop 8 is ongoing.
  • It is pointed out that the access to the tunnels is not managed in a transparent way and is difficult to get reliable information. AV will bring the concern to the XO and  DOB.

Optical lasers

VAC

XRO

XPD

DET

EEE

  • The issues with the encorder of the quadrant motion motors are caused by the fact that the encoder cables are too long (30m until the drag chain + 30 m in the drag chain). Right now a workaround exists (cable ground connected to the general ground). Final solution has to be found.
  • MPS Box  for timing. Some Cpus have to be reboot. No timing problems are expected. In case, BF will send an e mail to readiness.

CAS

  • 2.5.0 will be deployed in the tunnels starting from next week

ITDM

SRP

TS

AoB