Entry   Notes XO Integration Meeting 02.07.2025, posted by Frederik Wolff-Fabris on 02 Jul 2025, 10:03 
General Announcement:
- M. Doering announces on the LIMP-25: 
1. Old's AIBS removal is starting already this week (today), after agreement between Inaki de Diego and instruments; 
Entry   Notes XO Integration Meeting 30.06.2025, posted by Frederik Wolff-Fabris on 30 Jun 2025, 09:58 
General Announcement:
- M. Doering announces one schedule change on the test of mobile electrical equipment during the LIMP-25: 
Company doing it finished Desy premises earlier and from this week they start at EuXFEL in offices and then on the labs. If you have equipment to be tested
Entry   Notes XO Integration Meeting 25.06.2025, posted by Frederik Wolff-Fabris on 25 Jun 2025, 10:27 
General Announcement:
- Martin Doering informs on the LIMP-25: 
1. Friday the summer party takes place; please deliveries with big trucks shall be re-scheduled; 
Entry   Notes XO Integration Meeting 23.06.2025, posted by Frederik Wolff-Fabris on 23 Jun 2025, 10:19 
General Announcement:
- Martin Doering informs on the LIMP-2025: 
1. Tunnels were opened from 7AM today; 
Entry   Notes XO Integration Meeting 18.06.2025, posted by Frederik Wolff-Fabris on 18 Jun 2025, 09:47 
General Announcement:
-  LIMP-25 information: Martin Doering informs: 
1. Monday 7AM the tunnels are open but smoke extraction system tests is planned from 8AM to 10AM so that tunnels will be noisy and doors difficult to open;
Entry   Notes XO Integration Meeting 16.06.2025, posted by Frederik Wolff-Fabris on 16 Jun 2025, 09:41 
General Announcement:
- A. Galler says a second Cryo issue happened on Saturday but it was possible to recovered by 18:00.
- LIMP-25 is about to start in one week. In case of questions please do not hesitate in contacting Martin Doering and XO.
Entry   Notes XO Integration Meeting 11.06.2025, posted by Frederik Wolff-Fabris on 11 Jun 2025, 09:48 
General Announcement:
-  
Entry   Notes XO Integration Meeting 04.06.2025, posted by Frederik Wolff-Fabris on 04 Jun 2025, 09:44 
General Announcement:
-  
Entry   Notes XO Integration Meeting 02.06.2025, posted by Frederik Wolff-Fabris on 02 Jun 2025, 09:51 
General Announcement:
- The ongoing delivery sees a HXRSS at 12GeV with 1mJ total intensity (~350uJ background). 
Entry   Notes XO Integration Meeting 28.05.2025, posted by Frederik Wolff-Fabris on 28 May 2025, 09:42 
General Announcement:
-  
Entry   Notes XO Integration Meeting 26.05.2025, posted by Frederik Wolff-Fabris on 26 May 2025, 09:56 
General Announcement:
- A. Galler mentions the V0 was operated by another group after being interlock on Saturday by a vacuum issue in XTD6 while VAC-OCD was investigating the
issue. 
Entry   Notes XO Integration Meeting 21.05.2025, posted by Frederik Wolff-Fabris on 21 May 2025, 09:36 
General Announcement:
-  
Entry   Notes XO Integration Meeting 19.05.2025, posted by Frederik Wolff-Fabris on 19 May 2025, 09:42 
General Announcement:
- Harald Sinn inform on the first lasing for XFELO on Sunday morning shift; 100 bunches in the pulse train was giving synchrotron already on Saturday showing
the cavity was aligned. 
Entry   Notes XO Integration Meeting 14.05.2025, posted by Frederik Wolff-Fabris on 14 May 2025, 09:39 
General Announcement:
- As PRC, Jan Gruenert reports a problem with fire detection system in XTD4 needed the entire day yesterday to fix and by 18:00 was concluded. The North
branch was 
Entry   Notes XO Integration Meeting 12.05.2025, posted by Frederik Wolff-Fabris on 12 May 2025, 09:36 
General Announcement:
- Successful delivery last days with exceptional machine performance. From tomorrow we have a FD week followed by a 12GeV week.
Entry   Notes XO Integration Meeting 07.05.2025, posted by Frederik Wolff-Fabris on 07 May 2025, 09:50 
General Announcement:
-  
Entry   Notes XO Integration Meeting 05.05.2025, posted by Frederik Wolff-Fabris on 05 May 2025, 09:55 
General Announcement:
-  
Entry   Notes XO Integration Meeting 30.04.2025, posted by Frederik Wolff-Fabris on 30 Apr 2025, 10:12 
General Announcement:
- Kimon F. informs that tests for a multi-mode fiber communication in XTD4 have to be scheduled with an external company. XO will organize it.
Entry   Notes XO Integration Meeting 28.04.2025, posted by Frederik Wolff-Fabris on 28 Apr 2025, 09:44 
General Announcement:
- From PRC, Maurizio V. and Raul V. have no new things to report, apart of the HXRSS difficult tuning.
- As DRC, Luis Maia says the main points were discussed (see below).
Entry   Notes XO Integration Meeting 23.04.2025, posted by Andreas Galler on 23 Apr 2025, 09:27 
General Announcement:


 


CTRL:


guiserver at MID

backbone services moved to a new machine --> should mitigate the issue




DA:
ELOG V3.1.4-7c3fd00