Minutes of the Technical integration meeting 17.04.19 , posted by Adriano Violante on 17 Apr 2019, 11:34
|
SPB/SFX
CRL motors being tested. Today BB (AE) will check the status.
CSS interlock tests being planned for tomorrow.
Jungfrau
motors - SS (EET) fixed some cable issues. Now ok.
Julabo chiller: loop 5 has been updated (interlocks definition, setpoints...) AE+DET |
Status report after dispatch meeting 09.30, posted by Adriano Violante on 15 Apr 2019, 09:55
|
SPB/SFX
Tomorrow set up of the donwstream interaction region will start.
Jungfrau calibration pipeline has to be pushed. ITDM and
DET involved. Can be done this week.
Additional motors control bein implemented by AE.
Request presented to CAS to resume a project |
Status report after dispatch meeting 09.30, posted by Adriano Violante on 12 Apr 2019, 10:41
|
SPB/SFX
Hercules students period. During the night a pump failed and recovered after a power cycle.
5Hz mode tests were performed
and successful
CSS being commissioned. X mov elmo stage still has to be configured. Will be done probably today.
After some updates, |
Minutes of the Technical integration meeting 10.04.19 , posted by Adriano Violante on 10 Apr 2019, 10:54
|
SPB/SFX
CRL implementation in the hutch. Tests can start today.
CSS Test have been started. One elmo devide has to be implemented
today. Interlocks have to be tested (later).
AGIPD motion. Middle layer final tests will be done during next reconfiguration od the detector.
Julabo |
Report after dispatch meeting 09.30, posted by Adriano Violante on 08 Apr 2019, 10:48
|
SPB/SFX
5Hz mode tests started (SPB/SQS) and partially successful. A detailed report will be sent around. 2 cameras in SPB and digitizers in
SQS were tested. Cameras OK. Digitizers data recordin has some issues being fixed (train id related). Next week on Thursday a test with beam is foreseen. |
Report after dispatch meeting 09.00, posted by Adriano Violante on 05 Apr 2019, 10:07
|
SPB/SFX
5Hz mode tests started (SPB/SQS) and partially successful. A detailed report will be sent around. 2 cameras in SPB and digitizers in
SQS were tested. Cameras OK. Digitizers data recordin has some issues being fixed (train id related). Next week on Thursday a test with beam is foreseen. |
Minutes of the Technical integration meeting 03.04.19 , posted by Adriano Violante on 03 Apr 2019, 10:44
|
SPB/SFX
CRL implementation in the hutch. Cables at the back of the crate have been re-shuffled by EETf. VAC vessel had a leak and is being re-sealed
and pumped. If everything is fine and the vessel can be brought to the hutch the motors test can in principle start already this week. Interaction |
Report after dispatch meeting 09.30, posted by Adriano Violante on 01 Apr 2019, 10:21
|
SPB/SFX
The quadrant motion system test for the AGIPD presented some issues with the limit switches. Being fixed.
Julabo chiller:
waiting for feedback from Julabo to know whether the chiller is going to be repaired on time for next users. If not, SPB/SFX are trying to borrow one from |
Report after dispatch meeting 09.30, posted by Adriano Violante on 29 Mar 2019, 11:02
|
SPB/SFX
FXE
SQS |
Minutes of the Technical integration meeting 27.03.19 , posted by Adriano Violante on 27 Mar 2019, 10:48
|
SPB/SFX
CRL implementation in the hutch will happen in April. AE and EET involved. ==> Connectors on the beckhoff frames need to be re-shuffled
according to the newest version of the EPLAN documentation. EET will take care of that, so that the loop can be started as soon as possible.
CSS |
Status report after dispatch meeting 09.30, posted by Adriano Violante on 25 Mar 2019, 11:38
|
SPB/SFX
The Julabo chiller for the AGIPD detector broke. After intervention from TS was clear that it was not possible to fix on the fly. Users
time had to be cancelled. In generalr there are 3 solution being pushed simultaneously by SPB: Fix the existing one, buy a new one, integrate a new type |
Minutes of the Technical integration meeting 20.03.19 , posted by Adriano Violante on 20 Mar 2019, 14:07
|
SPB/SFX
CRL implementation in the hutch will happen in April. AE and EET involved. ==> ZA needs the documentation of the CRL. The point is
SRP to be able to evaluate the focusing properties to give beam permission after installation. TH will ask directly PVagovic. Still pending since PV is |
Status report after dispatch meeting 09.30, posted by Adriano Violante on 18 Mar 2019, 10:04
|
SPB/SFX
No major issues reported
Crates for the CRL will be installed today. Test is foreseen for next week.
FXE
Issue with the synchronization of the PP laser has been reported. This affects also SPB. The problem was found to be in the subsynch |
Minutes after dispatch meeting 09.00, posted by Adriano Violante on 15 Mar 2019, 11:27
|
SPB/SFX
No major issues reported
Motors in Loop 14 have been tested and problems with the motion sign and encoder were found. AE/EET
on it.
FXE |
Minutes of the Technical integration meeting 13.03.19 , posted by Adriano Violante on 13 Mar 2019, 11:11
|
SPB/SFX
CRL implementation in the hutch will happen in April. AE and EET involved. ==> ZA needs the documentation of the CRL. The point is
SRP to be able to evaluate the focusing properties to give beam permission after installation. TH will ask directly PVagovic. Still pending since PV is |
Status report after dispatch meeting 09.30, posted by Adriano Violante on 11 Mar 2019, 11:58
|
SPB/SFX
Experiments were succesfull
Calibration pipeline has issues - being fixed
Detailed planning of the shutdown works
is being done with AE to see whether some activities can be done before or after the critical week
JGFR calibration pipeline needed. SH will |
Minutes of the dispatch meeting 09.00, posted by Adriano Violante on 08 Mar 2019, 13:01
|
SPB/SFX
Only minor issues being addressed with the support groups.
FXE
SQS |
Minutes of the Technical integration meeting 06.03.19 , posted by Adriano Violante on 06 Mar 2019, 10:31
|
SPB/SFX
CSS component commissioning. Concept and implementation finalized. EPLAN has been modified. PLC modification has to follow.
Issues
concerning the simultaneous operation of more Jungfrau detector modules has been solved. Additional tests ongoing.
CRL implementation |
Minutes of the dispatch meeting 09.30, posted by Adriano Violante on 04 Mar 2019, 10:38
|
SPB/SFX
Ongoing discussions with the support groups to organize the shutdown activities.Update of the shutdown task list could eventually be
provided.
X-Ray interlock system had issues in the WE and needed to be re set. Not clear why this happened.
Problem with Karabo freezing. |
Report after dispatch meeting 09.00, posted by Adriano Violante on 01 Mar 2019, 14:18
|
SPB/SFX
Today Loop 8 could be ready (AE)
Agipd - visualization of data shows variable rep rate... correlations to be investigated.
FXE
SQS |