General Announcement:
- The User Operation Meetings will restart next Friday 19.07.
CTRL:
- Proceeding with bring up days.
DA:
- Busy with bring up days.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Not present.
- As PRC, Raul Villanueva informs that activities in XTD6 are planned to be finished by tomorrow, Tuesday.
DET:
- HIREX / Gotthard-II inSA2: it is fixed and installation is ongoing.
ITDM:
- Nothing to report; also involved in bring-up days.
XRO:
- An e-mail will be sent as preliminary tests will be done as preparation for SEPS tests next Monday. It is transparent to the machine.
LAS:
- Not present.
UNSYS:
- All good with undulators.
SPB:
- Nothing to report.
FXE:
- Nothing to add.
MID:
- All fine at MID.
HED:
- All fine at HED.
SCS:
- Today bring up days happening.
SQS:
- Nothing to report.
SXP:
- Not present. |