Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 349
Entry time: 15 Aug 2022, 09:49
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 15.08.2022 |
|
|
General Announcement:
- On Saturday 4AM there was a very short power glitch. Machine kept running and to our best knowledge only the SA3 GATT had to be reset afterwards.
If any group find any other affected device, please inform XO or the PRC.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Updates for SA1 PP-laser are coordinated with LAS.
- OCD call yesterday to replace motor on site (HED?).
VAC:
- Issue with GATT on Saturday early morning. It was resolved by SQS and VAC-OCD. Under investigation; it may be related to a drop of cooling water flow.
XPD:
- Nothing to report regarding XPD and PRC duties.
DET:
- Nothing to report.
ITDM:
- Small issue related to Graphana but fixed on Saturday.
XRO:
- Nothing to report.
LAS:
- Nothing to report.
UNSYS:
- Small issue with PS cell33/SA2: fixed and working by now.
SPB:
- Nothing to report.
FXE:
- No info on the beam usage over the weekend.
MID:
- All fine.
HED:
- Used beam from Friday until Sunday 23:00.
SCS:
- Using TOPAS for laser: some instability was found and shall be checked today together with LAS.
SQS:
- No news from the user program. |