Subject: Notes XO Integration Meeting 15.01.2025 
General Announcement:
- A. Galler announces that yesterday the cooling water of 20C was leaking. The reason is still to be found, as per e-mail from TS sent to the xo-info.

CTRL:
- Proceeding with updates and nothing to report.

DA:
- Ready for bring-up days.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Information: in XTD6 the PLC loop was repaired.
- XGMs are started (upstream ones).
- As PRC, J. Gruenert says a ZZ is ongoing in XTD10.

DET:
- Nothing to report; prepared for bring-up days.

ITDM: 
- Nothing to report.

XRO:
- The XTD10 H-slit access is finished and cable connection is fixed;
- M. Vannoni sent the draft for the ramp-up plan during next week to the instruments.

LAS:
- Continuing with maintenance tasks.

UNSYS:
- Trying to understand why alignment quadrupoles were inserted in cell#24.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- Not present.

SCS:
- Not present due to interlock tests.

SQS:
- Not present.

SXP:
- Not present.