Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 28 of 29  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
Entry   Minutes of the Technical integration meeting 17.04.19 , posted by Adriano Violante on 17 Apr 2019, 11:34 

SPB/SFX

  • CRL motors being tested. Today BB (AE) will check the status.
  • CSS interlock tests being planned for tomorrow.
  • Jungfrau motors -  SS (EET) fixed some cable issues. Now ok.
  • Julabo chiller: loop 5 has been updated (interlocks definition, setpoints...) AE+DET working on it. 
  • AE needs to know when Loop 9 is expected to run. SPB to check.

FXE

  • AE needs to get information on PLCs loop splitting. FXE to comment. 

SQS

  • Loop 9 will be updated.
  • AE helping for commissioning
  • AE needs priorities for the next loops. SQS to comment.

SCS

  • DSSC installation progressing. Loop 5 motion loops should run
  • In general loops have been updated. Loop 13 (part of it) being commissioned. AE needs to know then the entire loop commissionig will start.
  • Discussion with EET ongoing concerning the installation of cables for end stations. Space problem.
  • Loop 4. BKF536 and 531 being modified. Clarification with AE/EET needed.

 MID

  • Epix voltage interlocks definition and implementation. AE (MS) and CAS (CY) working on it.
  • For Loop 9 CY is preparing a change request. AE involved.
  • Loop 12 will be operable this week
  • Priorities for next loops needed by AE to plan the work.

HED

  • Mono in XTD6 has been fixed.
  • Jungfrau and epix commissioned
  • Loop 7 being commissioned
  • Loops 1, 2 , 5, 7 could be done
  • Loop9 (Smaract stages) has to be brough up. 
  • Loop10 and 11 will be needed in June. HED to confirm.

OPT Lasers

  • SA2 PPL work ongoing this and next week. ready by next week.
  • AE support is needed in order to bring the SCS laser up by the end of may. Mail has been sent. NJardon checks.

XRO

XPD

  • Loop updates procedure being finalized by AE. NK asked for MOV2 loop update during next week. AE will try to follow this up.
  • Issue repoeted from CAS: Fast ADC for MCP in SASE3 duplicates data in the 3 % of cases. DAQ is not responsible. Tests have to be made and for that the ADC servers have to undergo to short interruptions. Will be coordinated with XPD. Should not be e problem. CAS to follow the issue up.

VAC

​​DET

AE

​​ITDM

EET

CAS

  • 5Hz test follow up is being done by CAS. Especially optimization concerning train id and time stamp with DESY with the goal to make the switch between the different operation mode easier. A meeting will be planned.
  • 2,4,1. hotfix (Fast data pipeline) is being prepared

SRP

  • Oil cans in and outside SPB rackroom should be removed. A proper cabinet has been requested to TS but it is not yet ready since exhaust lines are needed.
  • Patch cables in the racks should be limited to the very necessary amount since there the material storage is not allowed . TS can help finding space for this material in the hall..
  • Schedule changes for the Summer shutdown due to modification of the interlock systems. Additional meetings needed. No info is expected before the beginning of May.

TS

  • Support for chillers. Contact people by TS are T. Bartsch and P. Schmidt. They can support concerning issues and problems with chillers for the day to day operation. LKersting supports that. For bigger project, a specific request should be made to LK.

AoB

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 15 Apr 2019, 09:55 

SPB/SFX

  • Tomorrow set up of the donwstream interaction region will start.
  • Jungfrau calibration pipeline has to be pushed. ITDM and DET involved. Can be done this week.
  • Additional motors control bein implemented by AE.
  • Request presented to CAS to resume a project concerning jetting. Library exists.
  • Issues with Train ID/ cell ID for AGIPD. Fix is ongoing.

​​FXE

SQS

  • Photonic science camera issue: fixed by CAS OCD (SB) but requires a hotfix. Will be provided after Easter
  • VAC interlocks for the NQS chamber will be implemented by AE. Definitions were provided.
  • Turbo only going to 50% when operated by Karabo. Fix ongoing
  • New devices to be implementd in karabo. Contact person informed
  • TB and AE to meet to fix some issues with motors

SCS

  • DSSC is pumping down
  • 6 Elmo motors needed for DSSC needed this week.
  • BKF controls will be tested with the DET group
  • Test of motors with the laser hutch is ongoing. Software installation ongoing.

​​MID

  • Users time ongoing. 2 Epix and Agipd being used without major issues
  • Agipd, 1 useful image every 276. This seems to be the stable configuration. ITDM asks for more optimized usage of the IT hardware next time...
  • ATT arm in the tunnel get stuck from time to time
  • for the 7th of may, 3 users motors have to be imlemented in Karabo. Via UPP, test with CY.

HED

  • Loop 7 commissiong ongoing
  • KS to give green light for next loops
  • Jngfr and epix being commissioned
  • Mono in XTD6 - issue with motor. to be fixed as soon as feasible.

 

OPT Lasers

XRO

XPD

VAC

DET

AE

​​ITDM

EET

CAS

SRP

TS

AoB

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 12 Apr 2019, 10:41 

SPB/SFX

  • Hercules students period. During the night a pump failed and recovered after a power cycle.
  • 5Hz mode tests were performed and successful
  • CSS being commissioned. X mov elmo stage still has to be configured. Will be done probably today.
  • After some updates, AGIPD run control topology light does not go to green. Start stop buttons do not work properly (cannot be seen when the detector stops aquiring data). CAS to have a look.

​​FXE

  • After some modifications in the chain fast valve-mps-plc a connector was found to be not properly reconnected and triggering the interlock. FXE should involve AE when such activities are performed in order not to cause overhead to the support groups.

SQS

 

SCS

  • Loop 4 updated. Loop 3 motors being commissioned. Loop 5 quadrant motion being finalized. Loop 12 (VAC) being prepared.
  • It is not clear when BKF 536 and 531 have to be installed by AE. SCS should comment.

MID

  • Loop 12 being prepared and should work by the end of next week.

HED

  • Loop 7 commissiong will start today. KS will send a list of crates to be put in the loops to AE (Prio-non prio PLCs)

 

OPT Lasers

  • SA2 PPL project, HW prepared.

​​XRO

XPD

 

VAC

DET

AE

​​ITDM

EET

CAS

SRP

TS

AoB

Entry   Minutes of the Technical integration meeting 10.04.19 , posted by Adriano Violante on 10 Apr 2019, 10:54 

SPB/SFX

  • CRL implementation in the hutch. Tests can start today.
  • CSS Test have been started. One elmo devide has to be implemented today. Interlocks have to be tested (later).
  • AGIPD motion. Middle layer final tests will be done during next reconfiguration od the detector.
  • Julabo chiller: loop 5 has been updated (interlocks definition, setpoints...) AE+DET working on it. seems ok.

FXE

SQS

  • Loop 8 and 11 up and running.

SCS

  • Loop 4 being updated. Loop 5 (DSSC related) will be updated this and next week.
  •  Loop 13 running with 1 crate. Part of cables will be delivered by EETf this week. 

MID

  • Smaract stages do not work propery and reliably. High priority. Has to be clarified with AE since it is not clear whether this is the same issue that SCS had and for whoch they developed a workaround. ==> BB will contact the Smaract company to address the issue.
  • Epix power issue has been fixed. The problem was a parameter not properly set in the power supply. No interlocks are being used. MID is aware of that.
  • Loop 9, 4 and 12 will be updated with interlocks next week.
  • Exapod control vs data policy issue (also affecting HED and SPB, as well as other components). The exapod control implementation via Beckhoff requires time and is planned for the end of April. For the time being SPB and MID control the exapods via software. This make somewhat difficult to store all the data in the correct way and is not fullfilling the data policy. PSPO will report the issue to TT. At this stage a reshuffling of priorities to speed up the HW implementation seems not to help, since it is anyway planned for end of April.
  • Loop 12 ready next week.

HED

  • Loop 5 being commissioned. Should be completed by today. Loop 7 cables are been reorganized and the commissioning will strat tomorrow. Planned to be completed by the end of the week. Lilla cables between patch panels and components will be asked and discussed with AE. 

 

OPT Lasers

  • SA2 PPL work ongoing. ready by next week.

XRO

  • Commissioning of M1 in SASE3 took place. An intervention concerning a limit switch has to be done (not critical)

XPD

  • Hirex 2 - Commissioning ongoing. Some imporvements, especially concerning DAQ is needed and will be discussed by AK with ITDM.

 

VAC

  • SASE2 beam permission button is hidden in the vacuum expert panel. It is not the case for SASE1 and 3... To be clarified with VAC, XRO and CAS.

DET

AE

  • 5Hz operation (HW trigger dependent on the bunch pattern) mode pre tests OK. New tests planned for tomorrow (SPB and SCS). MCP and hirex will also be included in the test with low priority.

​​ITDM

EET

CAS

SRP

  • A power supply was switched off by AE and found on again the next day despite a sign put on the device. This should not happen. SRP advices, in similar cases, also to add a contact of the person who switched off the device for safety reasons.
  • XS5000 controller in SCS issue. SRP clarifies that everybody must act in case of clear danger (e.g. preventig the access to a particular area). In this case, it was OK that UB and TS prevented the access to the SCS laser hutch to other people before the controller was put in a safe state.  Having said that, the responsibility lies with the scientific group operating the device.

TS

AoB

Entry   Report after dispatch meeting 09.30, posted by Adriano Violante on 08 Apr 2019, 10:48 

SPB/SFX

  • 5Hz mode tests started (SPB/SQS) and partially successful. A detailed report will be sent around. 2 cameras in SPB and digitizers in SQS were tested. Cameras OK. Digitizers data recordin has some issues being fixed (train id related). Next week on Thursday a test with beam is foreseen. ==> Update from AS:The whole chain, Digitizer, Karabo, DAQ worked as expected.
  • CSS being commissioned
  • AGIPD chiller: Julabo is back. Loop is being updated. Detector interlocks also being updated.

FXE

SQS

  • Loop 8 and 11 deployed
  • Triggers to be re-checked (BF+TB)
  • Configuration of motors is being finalized. 
  • Network drive in the control network. Solution will be discussed with ITDM (group access to the DESY cloud?)

SCS

  • XS5000 controllers in the laser room were not safe and need to be reworked. Technically the issue has been solved. SCS reported some unhappiness because of unclear procedures (responsibility, Elektrofachkraefte...). AV will discuss with SRP and UBr, TS and ask SRP to make a statement.
  • Shutter in the experimant hutch will stay open the entire day to allow XRO to continue the commisisoning of the mirror and mono in the tunnels.

MID

  • Epix - essentially ready for experiments this week.
  • 2nd epix module being tested.
  • Epix channel power issue (digital/analog voltage issue). Being investigated. It is not a showstopper

HED

  • Loop 5 will be commisisoned today. Loop 7 will follow (much bigger, in-vacuum components). The goal is to finish the commissioning of these 2 loops by the end of the week. 

 

OPT Lasers

​​XRO

  • SA3 commissioning during the week end (Mirror+mono). Will continue today.
  • Procedure to re start the loops in the tunnels has been discussed and modified to increase the transparency. PG will write an email summarizing the new procedure to the GLs

XPD

 

VAC

DET

  • HED epix and jungfrau calibration routines will be installed tomorrow.
  • FXE: LPD charge injection scan has to be re-scheduled.

AE

​​ITDM

EET

CAS

SRP

TS

AoB

Entry   Report after dispatch meeting 09.00, posted by Adriano Violante on 05 Apr 2019, 10:07 

SPB/SFX

  • 5Hz mode tests started (SPB/SQS) and partially successful. A detailed report will be sent around. 2 cameras in SPB and digitizers in SQS were tested. Cameras OK. Digitizers data recordin has some issues being fixed (train id related). Next week on Thursday a test with beam is foreseen. ==> Update from AS:The whole chain, Digitizer, Karabo, DAQ worked as expected.
  • Loops updates being finalized. 
  • AGIPD chiller: Spare chiller from CFEL has been placed in the hutch. Julabo chiller is being shipped back. The julabo chiller is the first option, if it is not possible to put it in operation in time, the CFEL chiller will be used. 

FXE

SQS

  • Loop 8 and 11 being put into operation. Ongoing.
  • New motors in loop1. Being configured.

SCS

  • XS5000 controllers in the laser room were not safe and need to be reworked. Loop13 crates have been switched back off.
  • First cables (WCB/laser table) will be delivered by EETf be the end of next week.

MID

  • Test with train id startin today at 10:00
  • Loop 9 - interlock definitions being implemented. Test using interlocks foreseen for next Tuesday.
  • Epix chiller has issues. Julabo chiller being used.
  • Epix channel power issue. Being investigated by CY/UB

HED

  • Cables and loops for HED instrumentation. All the phase II cables needed for operation have been installed. KS/EETf to send a Fertigmeldung to AE.  Loop 5 and 7 will be brought into operation on Monday. Other Loop priorities remain the same.

 

OPT Lasers

​​XRO

  • SA3 commissioning during the week end. DAQ and timing needed.
  • Procedure for loops restarting in the tunnels is being discussed with AE in a meeting today.

XPD

  • Hirex 2 work ongoing with the support from AE.

 

VAC

DET

  • FXE: Jungfrau modules swapped from 500 to 1Mpixel. 
  • FXE: LPD charge injection scan planned for the week end. Timing and DAQ required!

AE

  • SASE3 timing system failure - problem understood and solved.
  • MPS modules failing. It seems to be an IT problem. DESY IT and ITDM are looking into that.

​​ITDM

EET

CAS

Karabo version 2.4.0 requires update of the GIU client. Apart form special cases (MID, SPB for the AGIPD...) deployment is ongoing in the instruments.

SRP

TS

AoB

Entry   Minutes of the Technical integration meeting 03.04.19 , posted by Adriano Violante on 03 Apr 2019, 10:44 

SPB/SFX

  • CRL implementation in the hutch. Cables at the back of the crate have been re-shuffled by EETf. VAC vessel had a leak and is being re-sealed and pumped. If everything is fine and the vessel can be brought to the hutch the motors test can in principle start already this week.  Interaction SPB/SRP ongoing to define operations parameters.
  • CSS Test have been started. 3 encoder connectors need to be fixed by EETf (not sure can be done by the end of this week).
  • AGIPD motion. Test ok.
  • Julabo chiller: waiting for feedback from Julabo to know whether the chiller is going to be repaired on time for next users. If not, SPB/SFX are trying to borrow one from CFEL. VAC interlocks would not be operational due to the different type of chiller. Needs to be evaluated and eventually take the risk (DET, SPB).

FXE

SQS

  • Loop 8 and 11 HW will be prepared by AE. Ongoing (AE/SQS coordination ongoing)
  • Meeting organized by PGessler to review the recurring issues with the digitizers. The outcome is that for the next users run the zero suppression mode will not be used (only raw data - confermed by SQS). In this case, no issues are expected. In the meanwhile a general solution will be worked out.

SCS

  • DSSC undergoing tests in Hera south. If OK, next week will be brought to the hall.
  • Loop 13 running but incomplete. Loop 11 being prepared. Nano motion controls now in this loop. 

MID

  • Smaract stages do not work propery and reliably. High priority. Has to be clarified with AE since it is not clear whether this is the same issue that SCS had and for whoch they developed a workaround. ==> BB will contact the Smaract company to address the issue.
  • Loop 9 has been updated and the flow meters can now be read.
  • Epix chiller has issues. Being investigated by MID and eventually replaced.

HED

  • Cables and loops for HED instrumentation. All the phase II cables needed for operation have been promised to be installed by the end of this week. Loop 5 cannot be available before.
  • 2 weeks ago the HR mono loop was mistakenly updated twice and the second time parameters were not saved (Fri evening). Sat morning was fixed again. AE confirmed it was a misunderstanding because of paralle pulse picker tests. HR mono conversion factors commissioning ongoing.  

 

OPT Lasers

  • SA3 trigger stopped working today. PP laser is down. The timing server in the balcony rooms was found to be down. BF is investigating what happened.

XRO

XPD

  • Hirex 2 - Crates being included in the loops by AE.

 

VAC

DET

AE

  • Waiting for the finalization of the MID LDM risk assessment from SRP to allow the usage of the remote control of the device.==> SRP is working on that. 75% done.
  • 5Hz operation mode tests planned for this thursday. It has already been communicated to the instruments.

​​ITDM

EET

CAS

SRP

TS

AoB

  • Next week XTOB 1.01 will not be available. Most probably the meeting will be held at the mockup control room. AV will anyway send a reminder.
Entry   Report after dispatch meeting 09.30, posted by Adriano Violante on 01 Apr 2019, 10:21 

SPB/SFX

  • The quadrant motion system test for the AGIPD presented some issues with the limit switches. Being fixed.
  • Julabo chiller: waiting for feedback from Julabo to know whether the chiller is going to be repaired on time for next users. If not, SPB/SFX are trying to borrow one from CFEL (necessary parts availability to be checked.)
  • CSS loop restarted
  • CRL chamber will be brought down tomorrow. Cables in the rackroom will be re-shuffled by tomorrow evening.

FXE

  • No issues to report

SQS

  • NQS chamber is being cabled up
  • Crates for Loop 8 and 11 being installed by AE
  • VAC interlock definitions are being updated.
  • Solution for pnCCD has been found. To control it an existing PLC and cables will be used. Draft of the proposed solution will be sento to AE by TB.

SCS

  • Loop 13 firmware export will be provided to AE by EET on friday.

MID

  • Preparation of proposal for next users is ongoing (including AGIPD and EPIX).
  • Cabling issues for EPIX are being solved. Calibration of the detector will follow
  • One crate for epix has been changed and is being mounted back today
  • OPT VAC is now remote and being tested
  • Tomorrow CY will organize a review meeting for the epix where also needed people for the tests foreseen for 4-5.04 will be addressed.
  • Tech. commissioning of the CHILLER2 (AGIPD) will be done tomorrow

HED

  • Cabling phase II vs  loop operation: All the PRIO cables have been promised by the compoany to be installed by next friday.
  • Early next week LW will make a statement whether Loop 5 can be put in operation already during the week.
  • Installation of imagers behind the mono - Karen is organizing it. VAC supports.

OPT Lasers

XRO

  • Cooling installation in the SA1/3 mirrors ig going well. Commissioning foreseen for next WE. SQS and SCS shutters would need to be opened. Will be discussed offline with the instruments.
  • Minor works ongoing.

​​XPD

​​VAC

  • Hirex 2 has been installed
  • Support ongoing
  • Today MID mono will be opened.

AE

  • SASE3 and 1 tunnel MOV loops have been updated. Feedback to AE is needed!
  • Issue with dymaic triggers has been fixed.

ITDM

  • XFEL gateway will be updated in 15 minutes
  • Jddd usage examples will be posted by ITDM

DET

EET

CAS

  • Tunnels updated to Karabo 2.4.0. For the instruments coordination with scientist is ongoing (SCS already done)

 

AoB

  • Mail sent to the GLs asking for feedback concerning shutdown activities by GW.
Entry   Report after dispatch meeting 09.30, posted by Adriano Violante on 29 Mar 2019, 11:02 

SPB/SFX

FXE

SQS

  • Meeting to discuss the recent issues with the digitizers was organized by PGessler and took place yesterday. The outcome is that for the next users run the zero suppression mode will not be used (only raw data). In this case, no issues are expected. In the meanwhile a general solution will be worked out.

SCS

MID

  • Activities for next week include the interlock for the epix power system as well as the AGIPD chiller commissioning. BB has to be passed all the relevant issue since he is supporting CY during MS's holidays

HED

  • Cabling phase II vs  loop operation: All the PRIO cables have been promised by the compoany to be installed by next friday. Early next week LW will make a statement whether Loop 5 can be put in operation already during the week. With these milestoned in mind, AE will be able, if no major issues pop up, to bring up loops 5 and 7 in KW15, Loops 8-9 in KW 16 and Loop 6 by the end of April. HED has to say whether to continue with the users program under this conditions. 
  •  

OPT Lasers

XRO

​​XPD

​​VAC

AE

  • Issue with dymaic triggers is being fixed by DESY. This affects triggers 180, 181 and 182 thate are being patched.
  • Humidifiers failure in SPB rackroom reported by AE vs TS and TN. Now the humidifier has been switched off.  AV clarifies with TS. 

ITDM

DET

EET

CAS

  • SASE3 has been updated yesterday
  • For the karabo server 2.4.0 to work, also the GUI has to be updated to the 2.4.0.

AoB

Entry   Minutes of the Technical integration meeting 27.03.19 , posted by Adriano Violante on 27 Mar 2019, 10:48 

SPB/SFX

  • CRL implementation in the hutch will happen in April. AE and EET involved. ==> Connectors on the beckhoff frames need to be re-shuffled according to the newest version of the EPLAN documentation. EET will take care of that, so that the loop can be started as soon as possible.
  • CSS crate is ready. Loop 7 bridged (same loop as CRL). Test can start tomorrow.
  • AGIPD motion. Prelminary tests are being performed to be ready for the final tests in the march shutdown. ==> Some issues with cabling of limit switches were found. SPB will fix it today/tomorrow. ==> Test starting today. From the Karabo side seems ok.
  • AGIPD chiller has been shipper for repair. SPB/SFX are trying to find alternative solutions for the next users run.

FXE

  • 4 cables are needed to control some stages and were requested to AE/EET. After checking  by NC some rewiring from FXE side on the module side is needed to make the electronic solution proposed usable. NC is in contact wit TKorsh.

SQS

  • Loop 8 and 11 HW will be prepared by AE this week and can run by next week.
  • Interlock updates ongoing
  • Meeting organized by PGessler to review the recurring issues with the digitizers

SCS

  • When operating the machine in the train pattern (not  10 Hz) mode and pulse on demand mode the data from the XGMs in XTD10 and SCS is not recorded. ==> That's still the case and it is caused by a Doocs update not agreed with CAS. ==> Ongoing. ==> Meeting took place yesterday. Issue seeems to be closed.
  • The dangling cable of the sliding door has to be fixed. This is supposed to be done by ARathjen during the March shutdown.
  • A Change in the storage of raw data of the XGM is required. SCS is discussing with XPD (Theo). Later ITDM and CAS will be also involved.
  • Loop 13 being prepared. As well as 11. Interlock updates ongoing.

MID

  • Smaract stages do not work propery and reliably. High priority. Has to be clarified with AE since it is not clear whether this is the same issue that SCS had and for whoch they developed a workaround. ==> BB will contact the Smaract company to address the issue.
  • Loop 9 has been updated and the broncos can now be controlled.

HED

  • Cables and loops for HED instrumentation. LW is monitoring closely the installation of cables to give the go ahead to AE for the starting of tyhe loops. Loop 5 is still the priority. High priority cables for Loops 5, 7,8 should be all installed by the end of this week.

 

OPT Lasers

  • Modules for the time stamp have to be installed by AE. How long does it take? Will be discussed offiline with PG. ==> Installation dates: SASE1 in summer shutdown,  SASE3 being worked out, SASE2 will follow. Workaround with time stamp is being investigated. ==> PLCs have to be updated. HW ready.==> SASE3 OK. SASE2 crates being changed now.

XRO

XPD

  • Hirex 2 will be shipped from Cologne tomorrow and will be brought into the VAC lab. Crates ready, cables ready. AE can support local tests outside the shutdown week.==> Hirex will be installed in the shutdown and probably a couple of testt will need support from AE. These can be scheduled for the 01/02.04. Vac loop is affected.==> AE only supporting crates installation and powering.

 

VAC

DET

  • 3rd branch SA3 - one ion pump has to be included in the VAC loop (update tomorrow)

AE

  • Timing update foressen for today will rpobably happen a little bit later than expected in SASE2.
  • Waiting for the finalization of the MID LDM risk assessment from SRP to allow the usage of the remote control of the device.

​​ITDM

EET

CAS

SRP

TS

AoB

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 25 Mar 2019, 11:38 

SPB/SFX

  • The Julabo chiller for the AGIPD detector broke. After intervention from TS was clear that it was not possible to fix on the fly. Users time had to be cancelled. In generalr there are 3 solution being pushed simultaneously by SPB: Fix the existing one, buy a new one, integrate a new type of chiller. AMancuso is also preparing a document for the MB with the details of the failure.

FXE

SQS

  • REMI being removed. NQS being brought in on wednesday. Support form AE for testing and configuration will be needed.
  • Vac interlock loop updates are being coordinated with AE
  • Laser being set up. Support from AE maybe needed.

SCS

MID

  • DET and ITDM working on the AGIPD this and next week.
  • Loop 9 needs a framework update (flow control with broncos).
  • Patch panel design in eplan for epix ongoing.
  • Opt hutch VAC being implemented in karabo (w/o interlock definitions. interlock tests still outstanding)

HED

  • XGM/Pulse picker alignment has to be checked with beam. AE will come back to HED today. Has been postponed since timing was not properly implemented. 

OPT Lasers

XRO

​​XPD

​​VAC

AE

  • MOV loop in SASE1 and 3 tunnels is going to be updated tomorrow at the latest. Instruments and involved groups are supposed to check if everything is fine after the update
  • SASE2 Vac loop update today
  • ITDM is supposed to work on the redundant switches in the balcony on Wednesday. Karabo is going to be interrupted for about 30 minutes. NJardon will send an email to readiness when the activity is confirmed.
  • Timing card issue issue caused the timing signal to fail in SASE1. Issue was found to be the DESY people rebooting thr PLC without informing the relevant AE people.

ITDM

DET

EET

CAS

  • 2.4.0 released. Waiting for ITDM for DAQ tests. No deployment in the tunnels foreseen for now.

AoB

Entry   Minutes of the Technical integration meeting 20.03.19 , posted by Adriano Violante on 20 Mar 2019, 14:07 

SPB/SFX

  • CRL implementation in the hutch will happen in April. AE and EET involved. ==> ZA needs the documentation of the CRL. The point is SRP to be able to evaluate the focusing properties to give beam permission after installation. TH will ask directly PVagovic. Still pending since PV is not here.==> Still pending.
  • AGIPD motion. Prelminary tests are being performed to be ready for the final tests in the march shutdown. ==> Some issues with cabling of limit switches were found. SPB will fix it today/tomorrow.

FXE

SQS

SCS

  • When operating the machine in the train pattern (not  10 Hz) mode and pulse on demand mode the data from the XGMs in XTD10 and SCS is not recorded. ==> That's still the case and it is caused by a Doocs update not agreed with CAS. ==> Ongoing
  • The dangling cable of the sliding door has to be fixed. This is supposed to be done by ARathjen during the March shutdown.
  • A Change in the storage of raw data of the XGM is required. SCS is discussing with XPD (Theo). Later ITDM and CAS will be also involved.

MID

  • Issue with the remote control of the ion pumps.MID OPT now ok. MID exp being implemented (waiting for some HW + Support from CY). Basically understood. Will be implemented in agreement with the instrument (requires access + fixed cables)==> Loop update slot to be agreed with the instrument.
  • Smaract stages do not work propery and reliably. High priority. Has to be clarified with AE since it is not clear whether this is the same issue that SCS had and for whoch they developed a workaround. ==> no updates.

HED

  • Cables and loops for HED instrumentation. LW is monitoring closely the installation of cables to give the go ahead to AE for the starting of tyhe loops. Loop 5 is still the priority. High priority cables for Loops 5, 7,8 should be all installed by the end of this week.
  • Vacuul logic has to be implemented int he opt hutch. AE ready. Can be done tomorrow (KS, NJ)

 

OPT Lasers

  • Modules for the time stamp have to be installed by AE. How long does it take? Will be discussed offiline with PG. ==> Installation dates: SASE1 in summer shutdown,  SASE3 being worked out, SASE2 will follow. Workaround with time stamp is being investigated. ==> PLCs have to be updated. HW ready.

XRO

XPD

  • Hirex 2 will be shipped from Cologne tomorrow and will be brought into the VAC lab. Crates ready, cables ready. AE can support local tests outside the shutdown week.==> Hirex will be installed in the shutdown and probably a couple of testt will need support from AE. These can be scheduled for the 01/02.04. Vac loop is affected.

 

VAC

DET

  • LPD charge injection data seem ok.
  • MID gpu calibration foreseen for today

AE

  • Data Correlation issue test between MCP detector and XGM - PG: Workplan has been made. Additional tests needed and have to be planned with beam. ==> Beamtime will be requested by JG. ==> No updates

​​ITDM

EET

CAS

  • HED kick off meeting for preparation for users has to happen. ==> Will take place next week.

SRP

 

oB

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 18 Mar 2019, 10:04 

SPB/SFX

  • No major issues reported
  • Crates for the CRL will be installed today. Test is foreseen for next week.

FXE

  • Issue with the synchronization of the PP laser has been reported. This affects also SPB. The problem was found to be in the subsynch hutch. WP18 has been informed and is working on it.

SQS

  • Again Issue with digitizers not working was found and was  solved with the help of CAS.  For the long run PGessler proposed to have a task force with ITDM and CAS to look for eventual bottlenecks in the configuration of the chain. 
  • First CRD for the pn CCDs has been submitted. The second CRD (interlocks) is still in preparation

SCS

  • Loop 7 need to be updated (old) due to problems with readind encoders.
  • 2 fuses in the PLCs have to be replaced. AE has been informed.

MID

  • It is reported by CY that, in order to advance with the Epix readiness, would be beneficial if AE and EETF could accelerate the power system work BKF 467 crate completion (with Bernard's latest change request) plus patch-panel planning Eplan update this would be much appreciated. ==> Mails between CY and LW have been exchanged. CR implementation and Patch panel design are needed by Wednesday. 
  • Loop 9 needs a framework update today.
  • Preparation for the first users coming on Wednesay is ongoing.

HED

  • Si-Mono in XTD6 has been aligned with the cristals parallel to the beam but two issues were found: 1 - On of the movements is at ist limit and needs to be fixed. ZZ today (VAC+OPT support). 2 - One motor in Mono2 that does not work. Has to be checked (AE).
  • XGM/Pulse picker alignment has to be checked with beam. AE will come back to HED today.

OPT Lasers

XRO

​​XPD

​​VAC

AE

ITDM

  • Info was sent to the GLs concernig the use of the Maxwell cluster for users. These seemed not to be propagatet to the users since support was requested to IDTM concerning this specific issue. This is also the case for the detector calibration pipeline. These info should be proprly distributed in the future.

DET

  • FXE had small issues with LPD. DET on it.

EET

CAS

  • HED reported as an info to CAS that yesterday karabo was very slow for 2 hrs (10 seconds to push a button...) but it recovered by itself. Will be looked into... 

AoB

Entry   Minutes after dispatch meeting 09.00, posted by Adriano Violante on 15 Mar 2019, 11:27 

SPB/SFX

  • No major issues reported
  • Motors in Loop 14 have been tested and problems with the motion sign and encoder were found. AE/EET on it.

FXE

SQS

  • Issue with digitizers not working was found this morning and was reported solved during the meeting by CAS.
  • 2 CRDs for the pn CCDs are coming. Once they are there it has to be seen how to schedule the design, production of PLCs, as well as of cables.

SCS

MID

  • It is reported by CY that, in order to advance with the Epix readiness, would be beneficial if AE and EETF could accelerate the power system work BKF 467 crate completion (with Bernard's latest change request) plus patch-panel planning Eplan update this would be much appreciated. MFlade reports the request to his group.
  • Issues with Smaract stages cables. Fixed.

HED

  • Si mono in XTD6 had problems with the pitch motor whoch does not work anymore. XTD6 was opened yesterday for intervention and the system was pumping overninght. Interlock modified not to stop operation during the night for MID. This morning ZZ foreseen to complete the intervention.
  • Firmware for Loops 5 and 7 ready. KS/EET are checking whether all the cables for loop 5 have been installed. When they are, AE will be notified to switch on the loop. Same for loop 7. After the meetgin with compkany Schulz it was said that all the priority 1 cables (set by HED) will be installed by 05.04.
  • XGM/Pulse picker alignment has to be checked. On monday AE will have a look.

OPT Lasers

XRO

​​XPD

​​VAC

AE

ITDM

DET

  • Delay scan in MID was successful

EET

CAS

  • Control of personal interlock shutters will be possible through one computer for each instruments control room. PCs have been defined. Implementation can be ready by next week.

AoB

  • GW asks the intruments to check the shutdown planning, especially for the cases in which the instruments are requested as support groups (MPS?). If there a re problems or something does not make sense, please notify PSPO.
Entry   Minutes of the Technical integration meeting 13.03.19 , posted by Adriano Violante on 13 Mar 2019, 11:11 ElectricalSafety.pdf

SPB/SFX

  • CRL implementation in the hutch will happen in April. AE and EET involved. ==> ZA needs the documentation of the CRL. The point is SRP to be able to evaluate the focusing properties to give beam permission after installation. TH will ask directly PVagovic. Still pending since PV is not here.
  • AGIPD motion. Prelminary tests are being performed to be ready for the final tests in the march shutdown. Still planned.

FXE

SQS

SCS

  • When operating the machine in the train pattern (not  10 Hz) mode and pulse on demand mode the data from the XGMs in XTD10 and SCS is not recorded. ==> That's still the case and it is caused by a Doocs update not agreed with CAS.

MID

  • Issue with the remote control of the ion pumps.MID OPT now ok. MID exp being implemented (waiting for some HW + Support from CY). Basically understood. Will be implemented in agreement with the instrument (requires access + fixed cables)
  • Smaract stages do not work propery and reliably. High priority. Has to be clarified with AE since it is not clear whether this is the same issue that SCS had and for whoch they developed a workaround.

HED

  • Cables for the experiment hutch are being installed but some quality issues occured. Last pallets of cables have been sent back for proper confectioning. It is possible that there will be some delays. KA will discuss with LW how to prioritize cables to eventually minimize the impact on the commissioning. ==> Quality issues are being addressed. The company increased the manpower for cable confectioning and installation. KS prepared a list of priorities. AE informs that they will be probably able only to provide fw for loops 5 and 7 by the end of March (collision with many shutdown activities). PG will send details to KA. This will eventually require a decision concerning priorities.  Ongoing. ==> There will be a dedicated meeting after this one to discuss the details, coordinate the process (Cables/fw export/ Loops start).
  • CRL2 in XTD6 - issue with motors losing steps. Will be fixed in the March shutdown. ==> L. Batchelor
  • DAQ is ready. Data sources list has been sent to CAS. Will be also sent to ITDM for implementation.==> Status not clear
  • For the fixing of the mono's Picomotor, XTD6 will be opened tomorrow and on friday during the day. On the evenings the tunnel will be searched and closed again to allow beam in MID.

 

OPT Lasers

  • Modules for the time stamp have to be installed by AE. How long does it take? Will be discussed offiline with PG. ==> Installation dates: SASE1 in summer shutdown,  SASE3 being worked out, SASE2 will follow. Workaround with time stamp is being investigated.

XRO

XPD

  • Hirex 2 will be shipped from Cologne tomorrow and will be brought into the VAC lab. Cretes ready, cables ready. AE can support local tests outside the shutdown week.

 

VAC

  • Charge injection test (LPD, FXE) have been perfomed successfully.

DET

AE

  • Data Correlation issue test between MCP detector and XGM - PG: Workplan has been made. Additional tests needed and have to be planned with beam. ==> Beamtime will be requested by JG.
  • Hirex and DSSC integration and commissioning will most probably not be supported in the shutdown week. AE will try to support them outside that period.

​​ITDM

EET

CAS

  • Who is responsible for the bunch pattern recording for the different instruments? CAS will clarify with ITDM and AE. ==> Ongoing.
  • Karabo 2.4.0 test ongoing
  • 2.3.7. Hotfix available today (pipieline in middle layer devices has been optimized). To be decided by the instr. whether to install it or not. Recommended.
  • HED kick off meeting for preparation for users has to happen.
  • XGMs: DOOCS was updated without agreement with CAS and this lead to problems with the controls. In this condition CAS can give only limited support , because they do not know excactly what was deployed and whoch tests were done. In general, this goes against the good practice rule of not updating stuff during the beamtime.

SRP

  • The self rescue training is supposed to become part of the access requirement in the DACHS system for the tunnel. This caused a lot of concerns during the meeting (visitors? Access to components only in the very firrt part of the tunnel ). PSPO will discuss with SRP .==> SRP is trying to find a way to minimize the impact of this training on the XFEL employees. Discussion with DESY needed. ==> The implementation date is the 01.05. The legal requirements are quite strict. SRP is trying to find a solution with DESY (proper training every 3 yrs + yearly updates? to be seen). Advice from SRP is to get the training. SScherz can support booking the trainings.
  • HED Radiation interlock issues: no agreement yet to get beam permission. Another meeting is planned for tomorrow (SRP chairs).==> Solved
  • EUPs: Procedures for the electrical safety trainings and appointments are being clarified (UB, TH, WUS) ==> 2 training per week (in german) are planned for KW 13,14,15. SRP and TS will approach the GLeaders to decide who has to take the trainig first in the different groups. PGessler and SHauff point out that it is not clear whether the policy is olready in place or not. THaas mentioned that we are still in the transition phase and a presentation was given in thre STGL meeting and it was responsibility of the GLs to inform the group members. TH will send AV the material that will be circulated to the readiness mailing list and  in this elog ElectricalSafety.pdf.
  • SArslan has been appointed Safety responsible for the Exp. Hall. Access for XFEL employees will be granted by him from now on and not anymore by AViolante and GWellenreuther

AoB

Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 11 Mar 2019, 11:58 

SPB/SFX

  • Experiments were succesfull
  • Calibration pipeline has issues - being fixed
  • Detailed planning of the shutdown works is being done with AE to see whether some activities can be done before or after the critical week
  • JGFR calibration pipeline needed. SH will support SPB/SFX today
  • Motors in Loop 14 should be tested. ASilenzi can help. Then info to AE.

FXE

SQS

SCS

MID

  • Epix planning is advancing. List of activity being maintained and followed up by CY. Interface box for cables being modified by KS, CRs being implemented by AE. Ongoing. Goal date is 10.04.2019 to have the detector completely commissioned ==> Ongoing.
  • Issues with Smaract stages cables. Being fixed. (MS will help)
  • Loop 4 would need to be resterted next week.

HED

  • Si mono in XTD6 had problems with the pitch motor whoch does not work anymore. Same problems happened in other mono motors in MID and FXE in the past. MS will have a look. It has be decided how to proceed with the fixing. The mono is required for users operation in HED.
  • Loops readiness and cables readiness have to be aligned and priorities have to be set. It is not clear what can be provided by the end of March in terms of loops and cables. AV calls for  a meeting to clarify and set priorities...

OPT Lasers

XRO

​​XPD

​​VAC

AE

ITDM

DET

  • FXE JGRF was requested to be ready for last week end (done and working), but it was planned for April! In general better planning!
  • SPB calibration pipeline tests ongoing.

EET

CAS

AoB

Entry   Minutes of the dispatch meeting 09.00, posted by Adriano Violante on 08 Mar 2019, 13:01 

SPB/SFX

  • Only minor issues being addressed with the support groups.

FXE

SQS

SCS

MID

  • Epix planning is advancing. List of activity being maintained and followed up by CY. Interface box for cables being modified by KS, CRs being implemented by AE. Ongoing. Goal date is 10.04.2019 to have the detector completely commissioned

HED

OPT Lasers

XRO

​​XPD

​​VAC

AE

  • for SQS there are issue with the Karabo/digitizers communication. Workaround exists, being fixed for good (AE + CAS).
  • Given the preliminary shutdown task list sent to readiness this week, it is clear that AE does not have the resources to cope witl all the requests. The tasks do not have priorities right now and this is a problem. In general, priorities and tasks that could be dropped are needed. Instruments, Support groups and PSPO cannot decide. PSPO will address the issue to HS/TT. 

ITDM

DET

  • Calibration pipeline stability test will be performed with SPB (during shifts). CAS/DET/SPB on it.

EET

CAS

  • Hotfix 2.3.6 (GUI server, data loggers bugs fixed) deployed in SA1,2, in SA3 not yet.

AoB

 

Entry   Minutes of the Technical integration meeting 06.03.19 , posted by Adriano Violante on 06 Mar 2019, 10:31 

SPB/SFX

  • CSS component commissioning. Concept and implementation finalized. EPLAN has been modified. PLC modification has to follow.
  • Issues concerning the simultaneous operation of more Jungfrau detector modules has been solved.  Additional tests ongoing. 
  • CRL implementation in the hutch will happen in April. AE and EET involved. ==> ZA needs the documentation of the CRL. The point is SRP to be able to evaluate the focusing properties to give beam permission after installation. TH will ask directly PVagovic.
  • AGIPD motion. Prelminary tests are being performed to be ready for the final tests in the march shutdown.
  • It is possible to operate simultaneously the Agipd and Jungfrau detector. One issue is the restarting the Agipd afterwards. The issue is non critical and is being solved by DET/CAS.

FXE

SQS

  • exhaust line for explosive gases has not been tested so far and no information is available to SQS. Urgent. SRP should comment.==> MMeyer is following up the issue. ==> MM has got all the documentation and approval needed. The line can be used. XPD and CAS on it.

SCS

  • When operating the machine in the train pattern (not  10 Hz) mode and pulse on demand mode the data from the XGMs in XTD10 and SCS is not recorded.

MID

  • Issue with the remote control of the ion pumps.MID OPT now ok. MID exp being implemented (waiting for some HW + Support from CY)
  • AGIPD, Diamond and Epix detector tests succesful. AM thanks the technical groups for the support.

HED

  • Si bounce monochromators - Chiller leaks. Will be repaired in the next shutdown. ==> Waiting for delivery of parts. Not clear whether can be fixed in the next shutdown.==> Ongoing.
  • Cables for the experiment hutch are being installed but some quality issues occured. Last pallets of cables have been sent back for proper confectioning. It is possible that there will be some delays. KA will discuss with LW how to prioritize cables to eventually minimize the impact on the commissioning. ==> Quality issues are being addressed. The company increased the manpower for cable confectioning and installation. KS prepared a list of priorities. Ongoing.
  • Si- mono commissioning ongoing. Cameras for pico motors have been installed.
  • CRL2 in XTD6 - issue wit motors losing steps. Will be fixed in the March shutdown.
  • DAQ is ready. Data sources list has been sent to CAS. Will be also sent to ITDM for implementation.
  • Commissioning run proposal. Elogs to be used will be discussed with ITDM offline.
  • AE informs that they will be probably able only to provide fw for loops 5 and 7 by the end of March (collision with many shutdown activities). PG will send details to KA. This will eventually require a decision concerning priorities. 

 

OPT Lasers

  • Modules for the time stamp have to be installed by AE. How long does it take? Will be discussed offiline with PG. ==> Installation dates: SASE1 in summer shutdown,  SASE3 being worked out, SASE2 will follow. Workaround with time stamp is being investigated.

XRO

  • In SASE3 additional safety shutters issue: Hardware will be ready by middle of Feb. On the 24 and 25. the installation and the modification of the EPS loop should take place if D3, SRP agree on the change request proposed by HS and MD. ==> Still no official decision from D3 and SRP. AE would like to get as many info as possible in advance to start preparing the loop update. According to MDommach NJardon is supposed to be already in the loop. ==> Concept in written has not yet been communicated to SRP and AE. ZA will talk to HS. ==> HW is installed. Loop update can happen monday or tuesday. The proposed additional radiation safety measures for SASE3 were discussed with Zunaira Ansari. A test is foreseen for 5 March. Implementation in the SEPS system will be directly coordinated between Zunaira and Nerea. ==> Test successful. Limit for SASE3 has been nor raised to 1.3 keV.

XPD

VAC

DET

AE

  • Data Correlation issue test between MCP detector and XGM - PG: Workplan has been made. Additional tests needed and have to be planned with beam.

​​ITDM

  • Commissioning proposals form last year: The data will be moved physically to desy soon. ITDM will send an e mail aroung to inform the relevant people.

EET

CAS

  • Who is responsible for the bunch pattern recording for the different instruments? CAS will clarify with ITDM and AE. ==> Ongoing.

SRP

  • The self rescue training is supposed to become part of the access requirement in the DACHS system for the tunnel. This caused a lot of concerns during the meeting (visitors? Access to components only in the very firrt part of the tunnel ). PSPO will discuss with SRP .==> SRP is trying to find a way to minimize the impact of this training on the XFEL employees. Discussion with DESY needed. ==> The implementation date is the 01.05. The legal requirements are quite strict. SRP is trying to find a solution with DESY (proper training every 3 yrs + yearly updates? to be seen). Advice from SRP is to get the training. SScherz can support booking the trainings.
  • HED Radiation interlock issues: no agreement yet to get beam permission. Another meeting is planned for tomorrow (SRP chairs).
  • Procedures for the electrical safety trainings and appointments are being clarified (UB, TH, WUS)

AoB

Entry   Minutes of the dispatch meeting 09.30, posted by Adriano Violante on 04 Mar 2019, 10:38 

SPB/SFX

  • Ongoing discussions with the support groups to organize the shutdown activities.Update of the shutdown task list could eventually be provided.
  • X-Ray interlock system had issues in the WE and needed to be re set. Not clear why this happened.
  • Problem with Karabo freezing. CAS contact person ihas been involved and is working on the issue. This is related to the calibration running.

FXE

SQS

SCS

MID

  • Fast diodes needed on the WE. HW and Software support required and ongoing. ==> Successful
  • CY called for a  meeting on monday to collect all the requirements for the epix det to work. The det will be then tested in the common lase room. Karabo interface change is required. It will take 3 weeks.==> Epix has been moved back to the common laser room for proper testing and commisisoning. Several tasks have to be accomplished to try to make the detector work for the April's run. CY is basically organizing the technical commissioning.

HED

OPT Lasers

XRO

​​XPD

​​VAC

  • A pump for the GATT in SASE 3 had to be treplaced (borrowed from SPB).
  • Solid ATT in XTD 1 has issues with control valves. Being fixed now with a ZZ access.

AE

  • Probably the timing update planned for this morning will not be needed anymore. BF will send a notification mail.
  • there are many activities planned for the next shutdown and priorities will need to be set . PSPO agreed on sending the preliminary task list to the support groups so that they can start having an overview.

ITDM

  • Failure of the logbook during the night: Also one partition failed. Not clear why. Everything has been fixed and is back to normal.
  • Simultaneous operation of all the instruments generates competition of the resources. Priorities to be set.
  • Calibration pipeline: Only 1 server in place. POssible issues when operationg MID and SPB agipd at the same time... DET should look into that.
  • SPB requested to restart the DAQ before every shift. This can be done but it requires experts from DET and SPB to be present and to perfome some checks. This is now not always the case. To be discussed ho to find a short term solution.

 

DET

EET

CAS

  • Test Karabo 2.4.0. ongoing. Ongoing
  • List of loop updates for PLCs has to be issues by AE to CAS as soon as the activities are known.

AoB

 

Entry   Report after dispatch meeting 09.00, posted by Adriano Violante on 01 Mar 2019, 14:18 

SPB/SFX

  • Today Loop 8 could be ready (AE)
  • Agipd - visualization of data shows variable rep rate... correlations to be investigated.

FXE

SQS

SCS

MID

  • Fast diodes needed on the WE. HW and Software support required and ongoing.
  • CY called for a  meeting on monday to collect all the requirements for the epix det to work. The det will be then tested in the common lase room. Karabo interface change is required. It will take 3 weeks.
  • VAC interlock test in MID OPT to be performed. Marjian can support.

HED

  • Si(111) mono commissionig ongoing
  • VAC componennt in HED OPT being setup by KS
  • Digitizers for diodes being used.

OPT Lasers

XRO

​​XPD

​​VAC

AE

  • Timing update on monday in SASE2. BF sent an email to readiness with the details.

ITDM

DET

EET

CAS

  • Test Karabo 2.4.0. ongoing. List of PLCs AE==>CAS.
  • Problem with a solid attenuator valve in XTD1. Not enough air pressure to operate the valve properly. DFM(CAS) will contact XRO.

AoB

CAS and AE point out that there are many activities planned for the next shutdown and as soon as PSPO will issue the shutdown tasklist planning most probably priorities will need to be set by TT/ MGMT