Group Selection Page HELP Controls Group Data Analysis Group ITDM WP76 DET Vacuum EEE WP78 FXE SPB MID HED SQS SXP Sample Environment Operation PSPO XO TS Migrated2Zulip
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 23 of 31  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
ID Date Authordown Location Severity Subject Text Attachments
  187   16 Dec 2020, 09:11 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 16.12.2020General Announcement:

- Today is the last
xo-integration meeting for this year. Xo
  
  188   06 Jan 2021, 09:05 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 06.01.2021General Announcement:


Due to work restrictions,
some of shutdown activities will not end
  
  193   25 Jan 2021, 09:28 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 25.01.2021General Announcement:

- Test of automatic switch
of power bridge is shifted to Feb.2: this
  
  194   27 Jan 2021, 09:08 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 27.01.2021General Announcement:

- FFP2-Masks needs to be used in
the experiment control hutches from now on
  
  195   01 Feb 2021, 09:06 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 01.02.2021General Announcement:

- The test of the emergency automatic
switch of power bridge is scheduled for Tuesday, 2nd
  
  196   03 Feb 2021, 09:26 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 03.02.2021General Announcement:

- Automatic Power Switch Testing
was done yesterday. The switches are working
  
  197   08 Feb 2021, 08:30 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 08.02.2021General Announcement:

- XTD10 tunnel was closed
last Friday; XTD9 to be closed by end of
  
  198   10 Feb 2021, 09:20 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 10.02.2021General Announcement:

- Tunnel closure: it has been
decided both XTD6 and XTD9 will be searched
  
  200   17 Feb 2021, 09:27 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 17.02.2021General Announcement:



CTRL:
  
  202   24 Feb 2021, 09:03 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 24.02.2021General Announcement:

- Due to a failure alarm in the
smoke extraction system in XTD6+8+9, Desy
  
  204   03 Mar 2021, 09:23 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 03.03.2021General Announcement:

- Hick-ups in the beam operation
are happening since last night. There is
  
  206   10 Mar 2021, 09:20 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 10.03.2021General Announcement:

- nothing for now

CTRL:
  
  208   17 Mar 2021, 09:15 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 17.03.2021General Announcement:

- nothing.

CTRL:
  
  224   12 May 2021, 09:21 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 12.05.2021General Announcement:

- User Operations Meeting takes
place on next Friday 09:00.
  
  234   16 Jun 2021, 08:37 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 16.06.2021General Announcement:

- Interlock test next 2 weeks starting
on monday - from next wednesday the photon
  
  245   26 Jul 2021, 09:20 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 26.07.2021General Announcement:

- Power glitch 3 times at night,
what brought down the beam for 1,5 hour each
  
  246   28 Jul 2021, 09:29 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 28.07.2021General Announcement:

- No general announcement.

CTRL:
  
  87   27 Nov 2019, 09:25 Andreas GallerGeneralInformationdispatch meeting Mon Nov 25 2019FXE: no issues

SPB: no issues

MID: Split & Delay line arriving
  
  88   28 Nov 2019, 15:42 Andreas GallerGeneralProblemaffected ITDM Systems after power cut tonight


XHQ.E1.092

SW-HH-AL-271
was available
  
  95   15 Jan 2020, 09:09 Andreas GallerGeneralInformationnotes Dispatch meeting Jan 13 2020

SPB:


Testing coordinated movement
  
ELOG V3.1.4-7c3fd00