Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 23 of 31  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
ID Date Authordown Location Severity Subject Text Attachments
  208   17 Mar 2021, 09:15 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 17.03.2021General Announcement:

- nothing.

CTRL:
  
  224   12 May 2021, 09:21 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 12.05.2021General Announcement:

- User Operations Meeting takes
place on next Friday 09:00.
  
  234   16 Jun 2021, 08:37 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 16.06.2021General Announcement:

- Interlock test next 2 weeks starting
on monday - from next wednesday the photon
  
  245   26 Jul 2021, 09:20 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 26.07.2021General Announcement:

- Power glitch 3 times at night,
what brought down the beam for 1,5 hour each
  
  246   28 Jul 2021, 09:29 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 28.07.2021General Announcement:

- No general announcement.

CTRL:
  
  87   27 Nov 2019, 09:25 Andreas GallerGeneralInformationdispatch meeting Mon Nov 25 2019FXE: no issues

SPB: no issues

MID: Split & Delay line arriving
  
  88   28 Nov 2019, 15:42 Andreas GallerGeneralProblemaffected ITDM Systems after power cut tonight


XHQ.E1.092

SW-HH-AL-271
was available
  
  95   15 Jan 2020, 09:09 Andreas GallerGeneralInformationnotes Dispatch meeting Jan 13 2020

SPB:


Testing coordinated movement
  
  96   22 Jan 2020, 09:16 Andreas GallerGeneralInformationnotes Dispatch meeting Jan 20 2020

SPB:


nothing to report


FXE:
  
  99   26 Feb 2020, 09:06 Andreas GallerGeneralInformationnotes Dispatch meeting Feb 24 2020SPB:


nothing to report


FXE:


not present due to group
  
  100   04 Mar 2020, 08:49 Andreas GallerGeneralInformationnotes Dispatch meeting Mar 2 2020SPB:


AGIPD improvement campaign
great success
EEE --> 2nd C&C
  
  103   18 Mar 2020, 09:26 Andreas GallerGeneralInformationTechnical Integration Meeting 18.03.2020

SPB:


interument parked
power
  
  104   23 Mar 2020, 08:57 Andreas GallerGeneralInformationnotes Dispatch meeting Mar 23 2020Currently EuXFEL
enforces a hand-off policy for instrument/tunnel
hardware. That includes remote control of
  
  105   25 Mar 2020, 09:32 Andreas GallerGeneralInformationTechnical Integration Meeting 25.03.2020Currently EuXFEL
enforces a hand-off policy for instrument/tunnel
hardware. That includes remote control of
  
  Draft   30 Mar 2020, 08:57 Andreas Galler   CTRL:


Broker Pile Up in 4 topics
over the weekend

LAS affected
  
  107   01 Apr 2020, 09:19 Andreas GallerGeneralInformationTechnical Integration Meeting 01.04.2020

CTRL:


productive meeting with
  
  109   08 Apr 2020, 08:45 Andreas GallerGeneralInformationTechnical Integration Meeting 08.04.2020

CTRL:


no bigger issues
announcement:
  
  110   15 Apr 2020, 09:03 Andreas GallerGeneralInformationTechnical Integration Meeting 15.04.2020

CTRL:


notificagion service device
  
  145   22 Jul 2020, 09:22 Andreas GallerGeneralInformationXO integration meeting 22.07.2020General Announcement:


Default beam positions
are being implemented for each SASE at the
  
  146   27 Jul 2020, 09:05 Andreas GallerGeneralInformationNotes XO Integration Meeting 27.07.2020

General Announcement:


XO discusses the need for
  