Notes XO Integration Meeting 10.05.2021, posted by Frederik Wolff-Fabris on 10 May 2021, 10:05
|
General Announcement:
- Two smoke sensors affected in SA3 triggering fire alarm: The first one could be reset but for the second one the reset did not work and fire brigade
was in.
|
Notes XO Integration Meeting 05.05.2021, posted by Frederik Wolff-Fabris on 05 May 2021, 10:20
|
General Announcement:
-
|
Notes XO Integration Meeting 03.05.2021, posted by Frederik Wolff-Fabris on 03 May 2021, 10:06
|
General Announcement:
- The deadline for submitting the summer maintenance tasks is ended. In case you have not done so, please submit it as soon as possible.
- Monica T. as DRC invites people to attend the DRC jour-fixe meeting.
|
Notes XO Integration Meeting 28.04.2021, posted by Frederik Wolff-Fabris on 28 Apr 2021, 10:04
|
General Announcement:
- A. Galler points to the deadline for submitting summer maintenance task list on April 30th.
- XO would like to remind instruments that in case of operation failure related to Interlocks issue, please also include the PRCs (prc@xfel.eu) on the |
Notes XO Integration Meeting 26.04.2021, posted by Frederik Wolff-Fabris on 26 Apr 2021, 11:08
|
General Announcement:
- The deadline to submit the maintenance task list is on 30.04. We thank all the groups that have already submitted. In case of any question and comments,
please contact
|
Notes XO Integration Meeting 21.04.2021, posted by Frederik Wolff-Fabris on 21 Apr 2021, 10:50
|
General Announcement:
- XO reminds on the deadline of 30.04 for submitting the Summer maintenance task lists. For this, please do so sending the list to xo-planning@xfel.eu.
|
Notes XO Integration Meeting 19.04.2021, posted by Frederik Wolff-Fabris on 19 Apr 2021, 11:39
|
General Announcement:
- Remind on the Summer maintenance period: deadline to submit task list is April 30th. XO invite all groups to submit by this date.
|
Notes XO Integration Meeting 14.04.2021, posted by Frederik Wolff-Fabris on 14 Apr 2021, 10:50
|
General Announcement:
- We would like to remind groups that the deadline for submitting to XO the feedback on the planned activities for the Summer/21 maintenance time is on
April 30rd.
|
Notes XO Integration Meeting 12.04.2021, posted by Frederik Wolff-Fabris on 12 Apr 2021, 14:40
|
General Announcement:
-
|
Notes XO Integration Meeting 07.04.2021, posted by Andreas Galler on 07 Apr 2021, 08:52
|
General Announcement:
.
CTRL: |
Notes XO Integration Meeting 31.03.2021, posted by Frederik Wolff-Fabris on 31 Mar 2021, 11:01
|
General Announcement:
- There is no UOM on next Friday April 02.
- The next XO Int. Meeting takes place on Wednesday 07.04.
|
Notes XO Integration Meeting 29.03.2021, posted by Frederik Wolff-Fabris on 29 Mar 2021, 10:45
|
General Announcement:
- The UOM does not take place on next Friday 02.April.
- Pouneh S. informs the SCS panic button is not properly working (the search hutch does not perform as expected). This does not prevent operation and will |
Notes XO Integration Meeting 24.03.2021, posted by Frederik Wolff-Fabris on 24 Mar 2021, 10:06
|
General Announcement:
-
|
Notes XO Integration Meeting 22.03.2021, posted by Frederik Wolff-Fabris on 22 Mar 2021, 10:14
|
General Announcement:
- The Covid-19 health task force is looking into testing schemes to be employed on-site. In the future there will be an opportunity to do the self-tests
on-site for
|
Notes XO Integration Meeting 17.03.2021, posted by Arvid Gebhardt on 17 Mar 2021, 09:15
|
General Announcement:
- nothing.
CTRL: |
Notes XO Integration Meeting 15.03.2021, posted by Frederik Wolff-Fabris on 15 Mar 2021, 11:26
|
General Announcement:
- Following Desy e-mail to all EUXFEL staff, the emergency call system of the elevators will be offline on Thursday March 18th during the morning. Please
avoid using the
|
Notes XO Integration Meeting 10.03.2021, posted by Arvid Gebhardt on 10 Mar 2021, 09:20
|
General Announcement:
- nothing for now
CTRL: |
Notes XO Integration Meeting 08.03.2021, posted by Frederik Wolff-Fabris on 08 Mar 2021, 10:49
|
General Announcement:
- SPB/SFX will continue receiving beam this week for commissioning.
- Issues with access to the Operations/21 e-log: SPB run coordinator wrote to wrote to the admin but no answer so far. Entries by Adrian M. while using |
Notes XO Integration Meeting 03.03.2021, posted by Arvid Gebhardt on 03 Mar 2021, 09:23
|
General Announcement:
- Hick-ups in the beam operation are happening since last night. There is no obvious indications on the origin of the problem and MXL is investigating
to restore a normal beam delivery condition. |
Notes XO Integration Meeting 01.03.2021, posted by Frederik Wolff-Fabris on 01 Mar 2021, 10:49
|
General Announcement:
- An e-mail from Steve Aplin informs on how to contact the DATA operation center during beam delivery times. It changes contact phone numbers for OCDs.
|