SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 268
Entry time: 13 Oct 2021, 09:26
|
Author: |
Andreas Galler |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 13.10.2021 |
|
|
General Announcement:
- This meeting is a tool to share information/experiences across scientific and technical groups
CTRL:
DA:
EEE:
- next week
- update on GATT and EPS loop in SA3 in roder to allow for new protection of GATT for the whole beaemtime
- SA2 on Thursday (maybe Friday), try to correct backlash issue --> loop update
VAC:
- all is running
- HED VAC event
- miscommunication between operators led to this issue
XPD:
- no issue to report
- next week, during the whole week there'll be a high photon energy test at SA1 and SA2 see a big involvement of XPD
- 24 keV @SA1 (Tue)
- ~30 keVC @ SA2 (Wed/Thu)
- PI/Planner is Frank Brinker
DET:
- investigating JF1M issue of 4-6Hz instead of 10 Hz operation
ITDM:
XRO:
- SA1 M1/M2 drifts under investigation
- XRO is involved as well with next weeks high photon energy effort as well as EEE loop updates
LAS:
UNSYS:
SPB/SFX:
- user exp this week, 24 keV next week
FXE:
MID:
HED:
- next week high photon energy
SCS:
SQS:
- next week material tests, maybe also detector group.
AOB:
|