Notes XO Integration Meeting 12.04.2021, posted by Frederik Wolff-Fabris on 12 Apr 2021, 14:40
|
General Announcement:
-
|
Notes XO Integration Meeting 07.04.2021, posted by Andreas Galler on 07 Apr 2021, 08:52
|
General Announcement:
.
CTRL: |
Notes XO Integration Meeting 31.03.2021, posted by Frederik Wolff-Fabris on 31 Mar 2021, 11:01
|
General Announcement:
- There is no UOM on next Friday April 02.
- The next XO Int. Meeting takes place on Wednesday 07.04.
|
Notes XO Integration Meeting 29.03.2021, posted by Frederik Wolff-Fabris on 29 Mar 2021, 10:45
|
General Announcement:
- The UOM does not take place on next Friday 02.April.
- Pouneh S. informs the SCS panic button is not properly working (the search hutch does not perform as expected). This does not prevent operation and will |
Notes XO Integration Meeting 24.03.2021, posted by Frederik Wolff-Fabris on 24 Mar 2021, 10:06
|
General Announcement:
-
|
Notes XO Integration Meeting 22.03.2021, posted by Frederik Wolff-Fabris on 22 Mar 2021, 10:14
|
General Announcement:
- The Covid-19 health task force is looking into testing schemes to be employed on-site. In the future there will be an opportunity to do the self-tests
on-site for
|
Notes XO Integration Meeting 17.03.2021, posted by Arvid Gebhardt on 17 Mar 2021, 09:15
|
General Announcement:
- nothing.
CTRL: |
Notes XO Integration Meeting 15.03.2021, posted by Frederik Wolff-Fabris on 15 Mar 2021, 11:26
|
General Announcement:
- Following Desy e-mail to all EUXFEL staff, the emergency call system of the elevators will be offline on Thursday March 18th during the morning. Please
avoid using the
|
Notes XO Integration Meeting 10.03.2021, posted by Arvid Gebhardt on 10 Mar 2021, 09:20
|
General Announcement:
- nothing for now
CTRL: |
Notes XO Integration Meeting 08.03.2021, posted by Frederik Wolff-Fabris on 08 Mar 2021, 10:49
|
General Announcement:
- SPB/SFX will continue receiving beam this week for commissioning.
- Issues with access to the Operations/21 e-log: SPB run coordinator wrote to wrote to the admin but no answer so far. Entries by Adrian M. while using |
Notes XO Integration Meeting 03.03.2021, posted by Arvid Gebhardt on 03 Mar 2021, 09:23
|
General Announcement:
- Hick-ups in the beam operation are happening since last night. There is no obvious indications on the origin of the problem and MXL is investigating
to restore a normal beam delivery condition. |
Notes XO Integration Meeting 01.03.2021, posted by Frederik Wolff-Fabris on 01 Mar 2021, 10:49
|
General Announcement:
- An e-mail from Steve Aplin informs on how to contact the DATA operation center during beam delivery times. It changes contact phone numbers for OCDs.
|
Notes XO Integration Meeting 24.02.2021, posted by Arvid Gebhardt on 24 Feb 2021, 09:03
|
General Announcement:
- Due to a failure alarm in the smoke extraction system in XTD6+8+9, Desy colleagues will need to reboot a crate and exchange one module. This
will bring down the air conditioning for the tunnels during about two hours. The activity is scheduled for March 1st starting at 11:30AM and |
Notes XO Integration Meeting 22.02.2021, posted by Frederik Wolff-Fabris on 22 Feb 2021, 10:14
|
General Announcement:
- In case someone has any remaining question on the use of masks in the hutches please feel free to ask in this meeting series or write XO an e-mail.
- Racks for the SXP will be delivered and moved around XHEXP1 in March. The calendar for such activities will appear in the EXFEL infrastructure calendar. |
Notes XO Integration Meeting 17.02.2021, posted by Arvid Gebhardt on 17 Feb 2021, 09:27
|
General Announcement:
-
CTRL: |
Notes XO Integration Meeting 15.02.2021, posted by Frederik Wolff-Fabris on 17 Feb 2021, 08:52
|
General Announcement:
- It had been a cooling water issue with SA1 and SA3 PPLs on Saturday. Other groups are encouraged to check their components for eventual damage. Cooling
water is back
|
Notes XO Integration Meeting 10.02.2021, posted by Arvid Gebhardt on 10 Feb 2021, 09:20
|
General Announcement:
- Tunnel closure: it has been decided both XTD6 and XTD9 will be searched and closed on Monday 15.02.
- Temporary tunnel access requests: for ZZ access please be aware of the new Redmine ticket for access requests. The link to it appears |
Notes XO Integration Meeting 08.02.2021, posted by Arvid Gebhardt on 08 Feb 2021, 08:30
|
General Announcement:
- XTD10 tunnel was closed last Friday; XTD9 to be closed by end of this week; XTD6 is undefined – mostly likely by Monday. Any schedule
deviation will be communicated. |
Notes XO Integration Meeting 03.02.2021, posted by Arvid Gebhardt on 03 Feb 2021, 09:26
|
General Announcement:
- Automatic Power Switch Testing was done yesterday. The switches are working as expected and a protocol has been produced. Torsten Schoen
informs this test is done every 4 years; from now on equipment can be connected again to the orange and green power outlets. |
Notes XO Integration Meeting 01.02.2021, posted by Arvid Gebhardt on 01 Feb 2021, 09:06
|
General Announcement:
- The test of the emergency automatic switch of power bridge is scheduled for Tuesday, 2nd of February 2021, 09:00. This will
affect orange outlets in XHQ and green and orange outlets in XHEXP1. A short interruption in the power supply lines will happen. We expect all groups have |