Message ID: 264     Entry time: 29 Sep 2021, 09:49
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 29.09.2021 
General Announcement:
- Tomorrow 30.09 is the deadline to submit the winter maintenance task list. In case of questions please do not hesitate in contacting XO.

CTRL:
- Nothing to report; systems are fine.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
•	Nothing to report.

XPD:
- High pulse energy in SA3: about 15-16mJ was seen at 1keV and XPD confirmed the accuracy of this value. By the other side, XPD is checking for potential damages in the YAG screens (not yet identified but 
this is close to the limit).
- A. Koch sent information on the screen limits and corresponding watchdogs. Info will be shared at the readiness mailing list.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Lasers are running. Question on spectral stability in SA3 from Monday: LAS investigated but they lack some diagnostics; LAS will need to work with SQS colleagues (Gotthard) to further complement 
diagnostic.

UNSYS:
- Alarm that PKG of SA3 is off. Nevertheless, SA3 is well performing with good temperatures.

SPB:
- Issue resolved by DRC in seeing the beam.

FXE:
- Nothing to report.

MID:
- All fine at MID; all in progress.

HED:
- Setting up experiment.

SCS:
- Progress with new setup.

SQS:
- Nothing to add; in touch with LAS.