Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 270
Entry time: 20 Oct 2021, 10:28
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 20.10.2021 |
|
|
General Announcement:
- XO received some enquires on the status of the winter maintenance scheduling: We have about 750 tasks submitted and we are currently analyzing all of them to spot conflicts to be solved as well as
identifying the infrastructure dates.
In case you have any question or would like to bring any point to our attention, please feel free to contact us at XO.
CTRL:
- Nothing to report.
DA:
- Today a minor update of offline calibration system occurs at 10:00. No service interruptions will happen.
EEE:
- From the PLC team: 1. An e-mail will be sent as reminder for tomorrow SA2 move2 update (together with XRO); 2. Today SA3 GATT EPS update will take place.
VAC:
- Not present.
XPD:
- XPD team is busy with the facility development week as well as with a beamtime at Flash.
- SA1 is setting up to 24keV. Is under tuning and has so far achieved 500uJ intensity
DET:
- Nothing to report.
ITDM:
- All fine.
XRO:
- SA1 beam transport is aligned with 24keV beam.
- SA2 will be also aligned from today using 30keV beam.
LAS:
- Not present.
UNSYS:
- Issue with 1 motor in the chicane cell#18 / SA2 (crystal) that triggered the limit switch. The motor is stuck and an attempt to remotely fix it will take place.
SPB:
- From tomorrow SPB/SFX will work with beam.
FXE:
- Preparing activities and all is OK.
MID:
- All fine at MID.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Nothing to report. |