Notes XO Integration Meeting 27.01.2021, posted by Arvid Gebhardt on 27 Jan 2021, 09:08
|
General Announcement:
- FFP2-Masks needs to be used in the experiment control hutches from now on regardless the number of people working in this areas. Regulations
concerning the maximum number of staff in this areas remain the same. |
Notes XO Integration Meeting 25.01.2021, posted by Arvid Gebhardt on 25 Jan 2021, 09:28
|
General Announcement:
- Test of automatic switch of power bridge is shifted to Feb.2: this affects all devices connected to orange or green power sockets (no
power for few seconds/minute). General e-mail will be sent. Instruments will need to care for equipment which is connected to these sockets. This also |
Notes XO Integration Meeting 20.01.2021, posted by Frederik Wolff-Fabris on 20 Jan 2021, 10:32
|
General Announcement:
- A. Galler encourages attendants to pose questions on the authorities decision of lockdown prolongation:
Zunaira A. asks on travel restrictions between different cities: The commuting continues to be allowed, but not business travels;
|
Notes XO Integration Meeting 18.01.2021, posted by Frederik Wolff-Fabris on 18 Jan 2021, 09:44
|
General Announcement:
- Clarification on the definition of a critical work will be made this afternoon during a discussion with group leaders and will be communicated to the
staff.
|
Notes XO Integration Meeting 13.01.2021, posted by Frederik Wolff-Fabris on 13 Jan 2021, 10:04
|
General Announcement:
- Test of power grid switching affecting green and orange power sockets: this was planned for tomorrow 14.01 but it is not shifted to 02.02.
For a second or so it may trigger power OFF in equipment. Groups have to identify devices that are connected to these sockets, for example at the instrument |
Notes XO Integration Meeting 11.01.2021, posted by Frederik Wolff-Fabris on 11 Jan 2021, 10:54
|
General Announcement:
- The Interlock test light in the hutches take place on January 13th. From tomorrow is starts in the tunnels.
We understand no support from instruments are needed and we thank HED and FXE for making their hutches available for these tests.
|
Notes XO Integration Meeting 06.01.2021, posted by Arvid Gebhardt on 06 Jan 2021, 09:05
|
General Announcement:
Due to work restrictions, some of shutdown activities will not end as planned in time. This leads to a prolongation of the start-up phase
starting next week. It means re-start of Accelerator and South branch will be delayed by 2-4 days while the North branch by about 1 week.
The |
Notes XO Integration Meeting 16.12.2020, posted by Arvid Gebhardt on 16 Dec 2020, 09:11
|
General Announcement:
- Today is the last xo-integration meeting for this year. Xo wants to thank everyone for the participating in this meeting series
while sharing information and giving updates. |
Notes XO Integration Meeting 14.12.2020, posted by Arvid Gebhardt on 14 Dec 2020, 09:00
|
General Announcement:
- Please write to xo.planning, if something comes up with intteruption of the maintenance due to new COVID-19 regulations.
CTRL: |
Notes XO Integration Meeting 09.12.2020, posted by Frederik Wolff-Fabris on 09 Dec 2020, 10:24
|
General Announcement:
- Regarding the e-mail related to the general radiation training and procedure to deliver a signed certificate, one can also send it by conventional post
to Zunaira A.
|
Notes XO Integration Meeting 07.12.2020, posted by Frederik Wolff-Fabris on 07 Dec 2020, 11:08
|
General Announcement:
-
|
Notes XO Integration Meeting 02.12.2020, posted by Frederik Wolff-Fabris on 02 Dec 2020, 10:21
|
General Announcement:
- Laser interlocks activities in SA2 are delayed by two days. Therefore, activity in SA1 will start later.
- Gerd W. reports the cooling water in SA3 was refilled; air conditionings are running and maintenance on them are ongoing;
|
Notes XO Integration Meeting 30.11.2020 , posted by Arvid Gebhardt on 30 Nov 2020, 09:15
|
General Announcement:
- /
CTRL: |
Notes XO Integration Meeting 25.11.2020, posted by Frederik Wolff-Fabris on 25 Nov 2020, 10:14
|
General Announcement:
- There is no UOM or XO Int. Meeting next Friday 27.11. We will continue with XO Int. Meeting next Monday 30.11.
|
Notes XO Integration Meeting 23.11.2020, posted by Frederik Wolff-Fabris on 23 Nov 2020, 11:33
|
General Announcement:
- An e-mail to the readiness and stgl mailing lists was sent regarding the calendar share and updated task list. Please contact xo-planning@xfel.eu in
case of any issue.
|
Notes XO Integration Meeting 18.11.2020, posted by Frederik Wolff-Fabris on 18 Nov 2020, 11:23
|
General Announcement:
- Updates on the maintenance schedule will be made available in Alfresco. Guidelines in how to integrate calendars will be sent to readiness mailing list,
for example.
|
Notes XO Integration Meeting 16.11.2020, posted by Frederik Wolff-Fabris on 16 Nov 2020, 13:14
|
General Announcement:
-
|
Notes XO Integration Meeting 11.11.2020, posted by Frederik Wolff-Fabris on 11 Nov 2020, 10:49
|
General Announcement:
- XO is in contact with some groups regarding the winter shutdown, in order to get additional information or solve potential conflicts.
If there are any question, please contact us in this meeting or via e-mail.
|
Notes XO Integration Meeting 09.11.2020, posted by Frederik Wolff-Fabris on 10 Nov 2020, 10:53
|
General Announcement:
- Maintenance summary task list has been made available at the S:\ folder as well as in the XO Alfresco page.
|
Notes XO Integration Meeting 04.11.2020, posted by Frederik Wolff-Fabris on 04 Nov 2020, 10:55
|
General Announcement:
- XO reminds on the 4.5MHz operation: MXL tested a 12hs switching mode and this will be used along the week.
The night shift operates at 4.5 MHz and day shift at 2.25MHz to avoid sending unnecessary bunches to the dumps.
|