354
|
31 Aug 2022, 10:16 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 21.03.2022 |
General Announcement:
- Announcement from Martin Doering on the next Winter maintenance period: 1. presented timeline for the coming WMP; 2. minor changes to the maintenance task list; 3. pre-announce the electrical
interruption that will happen on Dec. 3rd;
- Release of MTL takes place in 02.09; deadline for submitting MTL on Sep.30th; release of summary task list on Oct. 28th. WMP starts on Nov.29th.
- Electrical Interruption on December 3rd:
Two interventions to be done (by TS and MKK1) in order to connect power to XHO1 and XHV and to upgrade transformer at XHVAC (allowing uninterrupted maintenances in future).
Affected locations: XHQ, XHEXP1, XHWS, XHVAC, media duct XHVAC and XHPSC; tunnels XTD4,6,7,8,9,10; XSDU-1 and XSDU-2. No power on 03/Dec. from 06:00 to 18:00. No access to campus during this time.
Ramp-down of equipment on 02.12 up to 24:00: all systems have to be powered off.
Electrical work conducted on 03/12.
Ramp-up on Sunday 04 and Monday 05 December. Sunday is for critical devices that can not wait until Monday to be switched ON.
Safety choice is to power OFF all equipment, regardless of the secondary power line; Saturday is chosen as has the least overall impact at the facility and in working conditions.
- For questions please contact xo-planning@xfel.eu.
CTRL:
- Issue with PP-laser bunch configurator still remains and is under investigation.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- FXE detector issue: problem remains but instrument manages to conduct experiment. Board has to be first exchanged by the expert who returns next week.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Issue with PP-laser multi pattern with CTRL.
- Random trigger issue with SA1: had to set back-up again. DOC is investigating.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- All fine at MID.
HED:
- Nothing to report.
SCS:
- Beam operation last night: problems with 2-color in the night and also problem with a motor; both solved.
- Light from SA1 has been seen and will be investigated today.
SQS:
- Not present. |
492
|
21 Feb 2024, 10:05 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 21.02.2024 |
General Announcement:
- The HED/HIBEF pulser will be fired today for the first time. If other groups see spurious effects on electronics please report back to XO.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
- Issue with FXE dark run calibrations: follow up problems with not correct Jungfrau DAQ; with installing new DAQ this can be solved; a work around exists for the old version.
EEE:
- Nothing major to report.
VAC:
- Nothing to report.
XPD:
- Not present.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Nothing to report; no updates on last week's SA1 jitter fluctuations.
LAS:
- Nothing to report.
UNSYS:
- SA3 cell 12 Phase shifter needs the ZZ to be done on March 5th.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- All great at MID.
HED:
- Nothing to report.
SCS:
- Not present.
SQS:
- Nothing to report.
SXP:
- Not present. |
302
|
21 Feb 2022, 11:57 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 21.02.2022 |
General Announcement:
- Philipp S. says a downtime for the calibration / GPFS update is to be done today at 12:00.
- Raul V. says that the biggest issue of last PRC week was related to the FXE beam pointing. In general, was a quiet and productive week. Please, instrument shall remind to make entries in the operation e-
log.
CTRL:
- In SA3 GATT activity will be performed today (fix to slowness) as beam is down and there is no activity.
DA:
- Announcement will come today: restart GPFS issue / Maxwell to be restarted.
EEE:
- One OCD on Saturday: issue with SDL motors in MID; to be followed up today.
VAC:
- Nothing else apart of the Gatt fix.
XPD:
- Shimadzu camera is installed in XTD6. A test has to be done and organized with instruments.
DET:
- Nothing to report.
ITDM:
- Fix to be deployed today: plan is to deploy Maxwell cluster done in the background; it shall not disturb any user of the system. All other storages with login to be done in March and still to be
confirmed.
- Slow data investigated: get wrong values with time stamp that could be corrected. Further investigation will take place this week.
XRO:
- FXE stability pointing issues on Friday afternoon: Raul V. placed a report in Operation E-log.
LAS:
- Nothing to report.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
FXE:
- Pointing issue from Friday;
- In DAQ the BAM device name has changed and could not be used. Please keep the compatibility for names; A. Silenzi will check with CTRL.
MID:
- Motor problems: in touch with CTRL.
- Today morning the CRL2 lenses were retracted but not giving the proper signal. It has been under investigation.
- Issue with DAQ: slow devices were saving empty data (no entries); at least happening with two devices. It has been reported and one is fixed and the second is under investigation.
HED:
- Initial setup this afternoon for the two-color operation.
SCS:
- Not present.
SQS:
- Not present. |
479
|
20 Dec 2023, 09:43 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 20.12.2023 |
General Announcement:
- This is the last XO Integration meeting for this year.
CTRL:
- Issue with upgrade of dataloggers was fixed and is now done. This time it runs smoothly.
- Issue with PP-lasers was solved by Desy colleagues.
DA:
- Nothing to report.
EEE:
- Finishing PLC tasks for the tunnels.
- HED will have an update today.
VAC:
- Not present.
XPD:
- Main ongoing task is the implementation of Gotthard-II in SA1 Hirex. Progress is being made.
DET:
- Nothing to report.
ITDM:
- E-mail was sent to xo-info on the office switches maintenance taking place next week 27.12. Control network is not affected.
XRO:
- Not present.
LAS:
- Pattern device is working, as reported by CTRL.
UNSYS:
- Not present.
SPB:
- Not present.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Flooding on the HED experimental hutch due to maintenance on AC.
Tobias Clever informs that during the maintenance some pumps were unplugged and was forgotten to be connected back due to the human error.
SCS:
- Nothing to report.
SQS:
- Nothing to report.
SXP:
- Not present. |
567
|
20 Nov 2024, 09:47 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 20.11.2024 |
General Announcement:
-
CTRL:
- Nothing to report.
DA:
- All fine with DA.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Everything fine for XPD.
- As PRC, J. Gruenert also has nothing to report.
DET:
- LPD burned power connectors: DET is aware of an issue happening last Friday; EEE was working without need of DET.
- M. Knoll said a connector showed a bad connection (smell could be sensed) and a by-pass for a power supply was done.
ITDM:
- Nothing to report.
XRO:
- Not present.
LAS:
- SCS smaract controller for the compressor is under investigation.
- SA1 PP-laser power improve: no news.
UNSYS:
- Nothing new to report.
- Cell#5 SA2: not clear if segment moved; the local control system did not get information from Phase Shifter, which actually moved gap.
SPB:
- Question beam delivery this week: files for 15keV and 17.5keV are prepared and will be delivered at best effort.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Not present.
SXP:
- Not present. |
470
|
20 Nov 2023, 10:01 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 20.11.2023 |
General Announcement:
-
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- AGIPD SPB still offline with issues on Julabo chiller.
- Adam R. adds the AGIPD is not mandatory for the coming week of operation. Jola S.-D. adds they are in touch with SPB and the issue will be further investigated after run is ended.
In addition, AGIPD is let out of beam for this week's operation.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Fire alarm on Friday brought down all Lasermet systems (SA3 PP-laser and E.0 systems). Needs further investigation. PP-L is not needed for the current week.
- Fire alarm was due to smoke detectors triggering it accidentally
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
- Adam R. adds AGIPD detector may not be needed this week but it is good for checking.
FXE:
- Affected by fire alarm (timing sync down).
MID:
- Nothing to report.
HED:
- Experiment with PP-laser on Sat night faced a drop in pp-laser energy (not clear from LAS why);
- Users using hazards samples let contamination at chamber. Needs to be addressed with SRP.
- Covid-19 impacted personnel.
SCS:
- Nothing to report.
SQS:
- Since laser went down, the R&D was impacted.
SXP:
- Not present. |
270
|
20 Oct 2021, 10:28 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 20.10.2021 |
General Announcement:
- XO received some enquires on the status of the winter maintenance scheduling: We have about 750 tasks submitted and we are currently analyzing all of them to spot conflicts to be solved as well as
identifying the infrastructure dates.
In case you have any question or would like to bring any point to our attention, please feel free to contact us at XO.
CTRL:
- Nothing to report.
DA:
- Today a minor update of offline calibration system occurs at 10:00. No service interruptions will happen.
EEE:
- From the PLC team: 1. An e-mail will be sent as reminder for tomorrow SA2 move2 update (together with XRO); 2. Today SA3 GATT EPS update will take place.
VAC:
- Not present.
XPD:
- XPD team is busy with the facility development week as well as with a beamtime at Flash.
- SA1 is setting up to 24keV. Is under tuning and has so far achieved 500uJ intensity
DET:
- Nothing to report.
ITDM:
- All fine.
XRO:
- SA1 beam transport is aligned with 24keV beam.
- SA2 will be also aligned from today using 30keV beam.
LAS:
- Not present.
UNSYS:
- Issue with 1 motor in the chicane cell#18 / SA2 (crystal) that triggered the limit switch. The motor is stuck and an attempt to remotely fix it will take place.
SPB:
- From tomorrow SPB/SFX will work with beam.
FXE:
- Preparing activities and all is OK.
MID:
- All fine at MID.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Nothing to report. |
453
|
20 Sep 2023, 10:04 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 20.09.2023 |
General Announcement:
- The access and maintenance day is taking place today. Current ZZs at the accelerator are scheduled until 10AM and then it follows the tuning for cw38 beam delivery that starts from tomorrow at 7AM.
- Martin Doering announces that next Monday 25.09 a short presentation on the 2023 Winter Maintenance will be made in this meeting series.
Please a representative from every group is welcome to be present. The Maintenance task list is going to be send to instrument and support groups next week.
- As PRC, Jan reports so far the week looks good. Downtime from Mond-Tue of 1:15 which is being looked today at tunnel (LINAC);
- J. Gruenert (as PRC) reminds instruments to post at least once a day a report at the Operations e-log; In addition, for SA1, it is introduced a power limit of 5W to protect CRL1 lens when operating low
photon energies (this will be discussed with SPB/SFX).
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Nothing to report;
- Reminder that forbidden XGM ranges (SPB/SFX): in SA1 the two XGMs do not have the same gas. Upstream has Kr to be able to run 5.5keV; SPB/SFX can run with 7keV at this XGM and their own on with Xe
instead;
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Not present.
UNSYS:
- Quad issue in SA2/cell28: ZZ is done and successfully fixed.
SPB:
- Nothing to report.
FXE:
- Drop SASE Intensity when changing photon energy from FXE side: current understanding is that in some way the phase shifters are not set properly if the wavelength change is triggered from the Karabo.
- Wavelength changes/scans work properly when done by BKR.
- Test this afternoon from both sides (BKR and FXE) to understand and solve the issue. Possible workaround is to ask BKR to operate the undulators.
MID:
- Not present.
HED:
- Calibration for Jungfrau had problems with MyMDC starting only Thursday. Needs to discuss with DATA department on this scheduling issue.
- Status of sample stages with EEE: being further investigated.
SCS:
- Nothing to report.
SQS:
- Not present.
SXP:
- Not present. |
261
|
20 Sep 2021, 10:19 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 20.09.2021 |
General Announcement:
- On last week's cryogenic failure at the machine: the root cause is tracked to a failed temperature sensor that bring down several pumps.
CTRL:
- Time slot for Beckhoff update of Mc2 motors is tomorrow between 09:30-11:00. This update is for all topics in tunnels and experiments.
Change of parameters must not occur (for the ones which are stored in Beckhoff). Nevertheless, it is good for groups to check parameters that are not stored.
An e-mail will be sent to communicate it and a second one when the update is finished.
DA:
- Nothing to report.
EEE:
- EEE supports the mentioned loop updates (care of PLC system).
- Cabling installation in FXE and HED have started and are ongoing during this week.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- Gitlab update takes this week, on Thursday at 16:00. An e-mail will be sent to readiness.
XRO:
- Nothing to report.
LAS:
- Nothing to report.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
FXE:
- Stable operation during the weekend with a problem solved by DOC. A beam jitter was also observed on the weekend related to a feedback.
MID:
- All fine at MID.
HED:
- Finished user experiment; nothing to report.
SCS:
- Nothing to report.
SQS:
- Not present. |
343
|
20 Jul 2022, 09:30 |
Andreas Galler | General | Information | Notes XO Integration Meeting 20.07.2022 |
General Announcement:
CTRL:
DA:
- currently there is a gpfs issue affecting the online cluster
- delays in online analysis have to be expected
- delays in obtaining new constants, can take much longer than normally -->
EEE:
- nothing to report
- a couple of boards are not reachable, maybe connected to the power glitch we've had
VAC:
- ongoing activities
- XTD 6&9
- HED Mono works closing
- SXP beamline ready for beam
- operation at very low photon energies at SA3:
- GATT will use Ar --> System had been tested
- power glitch yesterday was seen in water distribution
XPD:
- ZZ on Tuesday for XTD1 SR imager camera
DET:
ITDM:
XRO:
LAS:
UNSYS:
SPB/SFX:
- issue with Elmo motors had been mitigated
- DA and Detector recovery
FXE:
- acces to air comperssor and support for moving LPD required for July 22nd for BTM tests.
MID:
- after loop update wrong parameters had been put to LDM motors
HED:
SCS:
SQS:
DRC
PRC
|
144
|
20 Jul 2020, 14:18 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 20.07.2020 |
General Announcement:
- Regarding Operation, VAC and PRC had a workaround to restore the North branch beam permission on Sunday.
- XTD9 Turnstiles were not working this morning for ZZ access planned by FXE.
During the meeting we heard the information that Michael Prollius / SRP has fixed it by rebooting the computer.
CTRL:
- Since Wednesday CTRL had one OCD call regarding the SA3/GATT gauges and controller configuration.
- SQS server - issues with interactions. Work ongoing.
- INFLUX roll out: test on CAS monitor topic is successful. For the double loggers, there will be an impact of 5-10 minutes down time when login.
This will happen on FXE (2x10min without data): it is OK for FXE and for LAS today. IF that is successful, CTRL will contact other instruments.
DA:
- Nothing to report
EEE:
- It has been working on the follow-up of HED topics.
- EEE OCD had a call on the SA3/GATT gauge controller.
VAC:
- Severe trouble with SA3 GATT: damage on the gauge controllers was a result of series of problems.
- Bearing of a downstream booster pump make vibration and developed two leaks; then pressure went bad;
vacuum gauges showed wrong numbers and resulting in electronic damage in the controller cards.
- The booster pump was exchanged on Friday; on Sunday a leak test found a broken vacuum welding and part was removed.
Currently ZM3 at Desy is fixing it. Expected to be ready for tunnel installation by 10AM.
- Sunday from 13:00: the GATT was in UHV mode to allow beam permission and lasing in SA1 and SA3 up to Monday 6AM.
- Currently XTD10 is open for GATT repair and PES exchange of turbo pump.
- CTRL mailing service worked quite well: an alarm e-mail of GATT fault was sent every 12 hours.
XPD:
- SA3/XGM valve was also OFF on Friday. Martin Dommach will contact Theo while in tunnel.
DET:
- Business as usual.
ITDM:
- Nothing to report.
XRO:
- Not present due to the night shift for beamline transport alignment activities.
- F. Wolff-Fabris informs the pre-shutters are commissioned by XRO during Sunday's shift.
LAS:
- Nothing to report
UNSYS:
- Nothing to report
SPB:
- Work is ongoing.
FXE:
- Preparing for beam operation: no big problems.
- Thursday we reported issues with motors not moving. EEE helped and it was found the current of the motors were not correctly migrated.
Now motors are working. Currents were set too low - this no risk of damage.
MID:
- Preparing for beam.
HED:
- Preparing and checking equipment.
SCS:
- Preparing for beam tomorrow.
- FFT end station problems reported last week are solved.
SQS:
- Waiting for the beam. |
334
|
20 Jun 2022, 10:33 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 20.06.2022 |
General Announcement:
- Summer maintenance period starts tomorrow; today the ramp down activities is taking place and two studies: beam stability at SA1/SA2 correlated to the air conditioning; radiation studies in SA3
Afterburner.
From tomorrow the tunnels are open at 07:00AM. Interlock tests at XHEPXP1 takes place between 13-15 July. In case of questions please contact Martin Doering at xo-planning@xfel.eu
CTRL:
- Starting to prepare the Karabo update that takes place from next week.
DA:
- Last week was quiet.
EEE:
- On the weekend an issue with digitizer for SQS: timing system card was misbehaving. This is a new issue, never seen before. The outputs of the timing card were generating wrong values.
Fixed during the weekend by rewiring the digitizers/crates. Reason is not yet fully understood and may relate to config files at DOOCS.
VAC:
- Nothing to report.
XPD:
- Beam stability study this afternoon: influence of tunnel ventilation on the beam for SA1 and SA2. It takes place from 14:00-16:00.
- Participating on ramp down activities today.
DET:
- AGIPD 1M module at SPB: to be tested today.
ITDM:
- Nothing to report.
XRO:
- Busy with ramp down activities.
LAS:
- Shutdown activities.
UNSYS:
- Nothing to report; preparing for the summer maintenance.
SPB:
- Starting with AGIPD intervention today.
- Successful last week night shifts.
FXE:
- Pulse numbering issue between Karabo / DOOCS: 1 and 0 pulses. To contact CTRL for investigation.
- Damage Si filter in XTD2 attenuator.
- Problems with beam stability during the weekend (lost 8 hours).
- FXE had data saving blocked. Origin was a not clear communication that first user should remain open until Monday 20.06. It was re-opened by ITDM after XO clearance on Friday 20:00.
MID:
- User run was cancelled on Friday evening as HXRSS was dominated by background.
- Busy with maintenance period.
- Mirror chamber issue: it needs EEE to solve.
HED:
- Busy with tests today on the stability task. Parasitic alignment of monochromator with XRO.
- Starting shutdown activities.
SCS:
- Nothing to report.
SQS:
- Start the shutdown activities. Successful beamtime last week. |
123
|
22 May 2020, 08:57 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 20.05.2020 |
General Announcement:
- XO Integration Meeting will not take place next Friday 22.05 due to the bridge holiday.
- MPS group shared some info on the SA1 emergency power off event that happened last week. Further investigations are ongoing.
- No conflicts have been reported for the activities on control network systems.
- Today 20.05 is the deadline for the groups to send via e-mail the updated summer shutdown tasks.
- MXL/Desy has planned to start on next Saturday and Sunday the SA2 photon search and operation.
CTRL:
- CTRL works together with XPD in the Doocs images for the IMG devices. A new control update will be deployed. The data is no longer corrupted.
- Today CTRL is deploying Karabo9 at MID. This serves as a small scale test prior the deployment on the other parts/groups of EuXFEL.
During the summer shutdown it will be deployed at the BKR photon computers.
DA:
- Working with the Karabo deployment.
- Group is available for data analysis and troubleshooting in devices, e.g. the Detectors.
EEE:
- EEE reminds the cables in the MPS room still remain to be connected (linked to the emergency off event of last Friday).
MPS group do not know yet when this will be done. As soon as XO know it will be informed.
- SQS cabling installation is done. FXE cabling work has started: it has an open issue with HV cables but it will be solved today.
Over lengths of cables are currently stored in the instruments but will be moved later.
VAC:
- Working in tunnel activities: MID pre-shutter; SA3 re-alignment ongoing.
- SA3 re-alignment: today we end at the PES - work ongoing accordingly to the plan. Upstream side of the gas attenuator will start on next Monday.
- No issues to report.
XPD:
- XPD is finishing XTD2 and XTD9 tunnels works: water cooling, pumps, boxing electronics; XPD will try to do activities in XTD10 in parallel with the re-alignment.
- All working fine - an updated file for the summer shutdown list will be send later today.
DET:
- The AGIPB detector at MID was re-started yesterday.
- SPB detector will be tested today or Friday (complete test after the emergency off event).
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Nothing to report.
SPB:
- Nothing to report. No damages due to the emergency off event but still has to test the detectors.
FXE:
- Nothing to report - no damage associated to the emergency off event.
MID:
- It is planned to check the power modes.
- MID gets confirmation it can access XTD6 today.
HED:
- Not present.
SCS:
- Not present.
SQS:
- Just protective rules on the OFF buttons were changed - nothing has been done on the functionality side. |
318
|
20 Apr 2022, 10:07 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 20.04.2022 |
General Announcement:
- Steffen H. reminds on the Karabo developer training that will take place next week. Registrations are still possible.
- Martin Doering informs that next week Friday 29.04 is the deadline for submitting the summer maintenance lists. In case of needed help, please contact xo-planning@xfel.eu.
CTRL:
- Issue with Influx issue in cw14: data logging is now protected and a Karabo update in only the data loggers machines has to be done.
It is proposed to make it today at 13:00 (it is transparent for the users and takes about 30mins). An e-mail will be sent to the xo-info@xfel.eu.
- Beckoff updates in software level to be performed on next Monday 25.04 at 13:00. This affects mainly tunnels; with instruments the coordination will be done.
DA:
- Nothing to report.
EEE:
- Minor things being supported but nothing major to report.
VAC:
- Nothing to report.
XPD:
- A. Koch asks on the Beckhoff update: only hardware in tunnels will be updated and only Karabo software.
- J. Laksman says that during the Eastern beamtime at SQS a gas needle opened very fast and the pressure of chamber went very fast, posing a damage risk.
A Redmine ticket was placed for that it does not open too fast. An offline discussion will take place with EEE and CTRL.
DET:
- DSSC is back online at SCS after months of non-operation. There are issues to be fixed and investigations are in progress. The DSSC expert is on OCD this week and DOC can also help.
ITDM:
- Nothing to report.
- Marcin S. asks on the plan for limiting the raw data process per run in this current beamtime. SPB staff was told that they can't have more than 10 processes running;
K. Wrona informed this was talked to users and it was agreed with the limited number of 10. An offline discussion will take place and if more is needed this can be accommodated.
XRO:
- Nothing to report.
LAS:
- Not present.
UNSYS:
- Nothing to report.
SPB:
- See Marcin S. question above. Nothing else.
FXE:
- Nothing to report.
MID:
- All fine at MID.
HED:
- Not present.
SCS:
- Under operation and issue with DSSC was already mentioned.
SQS:
- Not present. |
500
|
20 Mar 2024, 10:12 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 20.03.2024 |
General Announcement:
-
CTRL:
- Nothing to report.
DA:
- All fine at DA.
EEE:
- PLC team received SCS calls regarding interlocks; under investigation.
VAC:
- Last weeks a shutdown on seven ion pumps happened on Friday but was restarted remotely.
XPD:
- All running good from XPD.
DET:
- AGIPD follow-up: nothing obvious was found, but module started working again after quadrant was moved; it may relate to vacuum issues and results from operation or electrical connection.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Nothing to report.
UNSYS:
- Everything is fine;
- On Monday successful operation from BKR operators regarding Apple-X.
A. Galler clarifies the Apple-X is not yet available for instruments and coordination with Unsys, machine and photon RCs are still needed.
SPB:
- Nothing to report.
FXE:
- Taking the beam and everything is fine so far.
MID:
- Nothing to report.
HED:
- Not present.
SCS:
- Since yesterday, Tuesday, an issue with a O2 sensor happens but TS and TN were informed.
- Interlock issues that EEE is also informed.
SQS:
- Not present.
SXP:
- Not present. |
404
|
20 Mar 2023, 09:43 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 20.03.2023 |
General Announcement:
- An e-mail was sent to xo-info list about the pressurized air that is being serviced at XHEXP1. Some vacuum valves may close and please check for components connected to pressurized air.
This intervention had to be done as the system is being reconnected due to an extension.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Nothing to be reported.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Chiller from SCS taken and installed at SPB/SFX for AGIPD cooling, working fine
- MPOD problem at SPB/SFX required installation of a spare card, now working fine.
ITDM:
- Nothing to report.
XRO:
- Nothing major to report.
LAS:
- Nothing to report.
UNSYS:
- Nothing to report.
SPB:
- Confirm that Julabo chiller was replaced and is operation.
- An MPOD was replaced and works again.
FXE:
- FXE review happening and FXE will not use night beam on Tuesday and Wednesday; SPB/SFX can use the beam.
MID:
- Nothing to report.
HED:
- Nothing to report.
SCS:
- Nothing to report.
- SCS will contact Nerea J. to discuss a question/issue.
- A. Galler asks Jan Torben D. to verify with SCS colleagues on the reported jitter due to SA2 tuning.
SQS:
- Nothing to report.
SXP:
- Nothing to report. |
396
|
20 Feb 2023, 11:05 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 20.02.2023 |
General Announcement:
- Accesses to XTD10 and XTD4 are happening this morning. The South branch sees continuation with beam activities and preparation for this week of operation.
CTRL:
- Two Announcements:
1. Today at 13:00 a fix for influx proxy will be deployed. A short downtime will happen;
2. Also 13:00 a fix for the delay timers will be deployed everywhere. A contact person at instruments will restart the device.
DA:
- Nothing to report.
EEE:
- One OCD call related to HED encoder: to be investigated and fixed this week.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- SA3 intervention for SCS exit slit ongoing this morning.
LAS:
- SA3 PP-laser will be ready at the end of today.
UNSYS:
- A ZZ in SA3/XTD4 will take place today.
SPB:
- Pointing always had to be corrected at 7AM after beam back from night shift at FXE.
- Transmission with XPD last week: higher intensity at the calorimeter was seen (also high fluctuation 10-15%).
FXE:
- Pump probe beam shape showed some problems. LAS will investigate today.
MID:
- Nothing to report.
HED:
- Beam jitter in order of 50-100us is not like best performance seen last year.
- Everything else went fine.
SCS:
- Nothing to report.
SQS:
- Nothing to report.
SXP:
- Nothing to report. |
580
|
20 Jan 2025, 09:50 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 20.01.2025 |
General Announcement:
- E. Boyd reminds on the return of the beam shutter keys: actual plan is to return keys no later than Friday. The SA3 hutches are to be closed on the weekend.
- The User & Operation meeting will start from next week, Friday 31.01.
CTRL:
- Proceeding with bring up days.
DA:
- Busy with bring up days.
EEE:
- OCD was called due to rack 1.1 (SRA motors in SA1). ZZ was done yesterday and today another access at 10:00 to replace fuses.
VAC:
- Everything fine.
XPD:
- For XPD all is fine;
- As PRC Jan Gruenert reports on Friday problems with SRA slits in SA1 with motors in error and could not move. At some point it was moved but with wrong calibration;
On Sunday a fire alarm in rack 1.1 and extinguisher bottle was empty. No fire was found; Similar issue happened in November but this time the terminals seem to be OK - it seems to be only the fuse.
The gas bottle has to be exchanged and an access request is placed.
DET:
- Nothing to report; involved in bring-up days.
ITDM:
- An e-mail will be sent to announce on Thursday this week an upgrade to the Zulip backend of myLog to be done.
XRO:
- SA1 accident with SRA rack; nothing else to report.
LAS:
- Nothing to report.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- Busy at their satellite meeting.
HED:
- Busy with bring-up days;
- Power went down on Wednesday due to emergency OFF triggered by D3. XO is following up: no task that would trigger it was planned; mitigations will be done for the future.
SCS:
- Planned emergency OFF was successful and thanks to everyone who helped.
SQS:
- Not present.
SXP:
- Nothing to report. |
192
|
20 Jan 2021, 10:32 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 20.01.2021 |
General Announcement:
- A. Galler encourages attendants to pose questions on the authorities decision of lockdown prolongation:
Zunaira A. asks on travel restrictions between different cities: The commuting continues to be allowed, but not business travels;
Adriano V. asks on business/meetings that were postponed (MID/AGIPD intervention) to February in order to plan work that will happen during the summer shutdown: Andreas
G. says that if meeting can't be decided by Zoom, please send an e-mail to the task force with this enquire;
P. Gessler asks if EuXFEL considers to prepare documents (passport) again as in the first lockdown: A. Galler answers that this is in discussion but currently it will not
to be implemented once no curfew is ongoing.
CTRL:
- Working with ITDM to get the Docs system running again.
- Working with EEE to have systems running by Friday.
DA:
- Nothing to report.
EEE:
- EEE reminds the update of SA1 motion loop (to allow work for Hirex) will take place today.
VAC:
- Not present.
XPD:
- Progressing with tunnel works, e.g. installation of viewports.
- A. Koch asks on the tunnel closure plans for XTD6 and XTD9.
A. Galler says XTD9 will close around February 5th and for XTD6 one has to discuss with MXL-DESY on the possibility to keep it open for one week longer (until 12.02).
DET:
- Nothing to report on detector operation.
ITDM:
- ITDM needs to finalize GPFS work which requires one day maintenance. The proposed date is next Monday 25.01. It means no access to data from Maxwell during the all day.
Instruments shall contact ITDM until tomorrow 21.01 in case of restrictions.
- Tickets on e-mail lists (e.g. not authorized sending e-mails to some lists): ITDM is investigating.
XRO:
- XTD6 will have photon beam for recommissioning during the third week of February.
LAS:
- LAS asks instruments on their plans for when to use lasers (mid-February?). HED and MID confirm plans to have it by middle February. SQS, FXE and SCS will consult
internally and let LAS known.
UNSYS:
- Two quad movers in SA2 are working again.
- Afterburner (winter shutdown tasks): Fire extinguishing system to be build; Cleaning the tunnel has to be made prior switching on the PKG.
SPB:
- Nothing to report.
FXE:
- Upgrade of Jungfrau and related work is postponed to Friday.
MID:
- All fine at MID.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Nothing to report. |
383
|
19 Dec 2022, 10:01 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 19.12.2022 |
General Announcement:
- This is the last XO Integration meeting of this meeting.
- An electrical issue in SA2 experimental area happen: issue with UPSs - rack rooms could be affected. TS is investigating. PP-lasers were unaffected.
CTRL:
- Concluded Karabo updates basically in all topics.
- Further updates ongoing this week.
DA:
- Nothing to report.
EEE:
- Nothing to report.
- Train-IDs for SA2 instruments were missing during the weekend (likely related to the UPS failure) but are back since about an hour ago and then maybe only PLCs were affected.
VAC:
- All fine with VAC.
XPD:
- Work ongoing as planned.
DET:
- Nothing to report.
ITDM:
- Maxwell maintenance taking place this week.
- Servers for SA2 apparently were not affected due to the issue with UPS. To be further checked.
XRO:
- Not present.
LAS:
- Nothing to report.
UNSYS:
- Five undulators in SA3 have faulty encoders and are not moving after a power cut on 06.12 (seen in history of local PLCs - happened from cell14 to cells23). Reason for power down is not known. The power
was ON from cell1-13.
- Replacement of linear encoders are not possible with vacuum chamber between girders as needs alignment.
- First UNSYS will try to operate with rotatory encoders, if does not succeed, segments will be taken out.
- There are 4 spare encoders to repair 3 segments. Delivery time for new spares is 3-4 Months.
- Needs investigation to discover reason for the power outage in cells#14-23.
- Cell 33 in SA2 is fully operational.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- Power failure of UPS happened on Saturday on the SA2 experimental Hall area – will further investigate for affected systems.
HED:
- Will investigate any effect of the UPS failure.
SCS:
- Nothing to report.
SQS:
- Nothing to report. |